Revisions to the Filing Process for Commission Forms; Notice of Eforms Updates, Termination of Visual Foxpro Filings, and Extension of Filing Deadlines, 16591-16592 [2021-06477]
Download as PDF
Federal Register / Vol. 86, No. 59 / Tuesday, March 30, 2021 / Notices
• Specify a system-wide voltage
schedule (which is either a range or a
target value with an associated tolerance
band) as part of its plan to operate
within SOLs and IROLs, and to provide
the voltage schedule to its Reliability
Coordinator and adjacent Transmission
Operators upon request (Requirement
R1);
• Schedule sufficient reactive
resources to regulate voltage levels
(Requirement R2);
• Operate or direct the operation of
devices to regulate transmission voltage
and reactive flows (Requirement R3);
• Develop a set of criteria to exempt
generators from certain requirements
under Reliability Standard VAR–002–
4.1 related to voltage or Reactive Power
schedules, automatic voltage
regulations, and notification
(Requirement R4);
• Specify a voltage or Reactive Power
schedule (which is either a range or a
target value with an associated tolerance
band) for generators at either the high or
low voltage side of the generator stepup transformer, provide the schedule to
the associated Generator Operator,
direct the Generator Operator to comply
with that schedule in automatic voltage
control mode, provide the Generator
Operator the notification requirements
for deviating from the schedule, and, if
requested, provide the Generator
Operator the criteria used to develop the
schedule (Requirement R5); and
• Communicate step-up transformer
tap changes, the time frame for
completion, and the justification for
these changes to Generator Owners
(Requirement R6).
Reliability Standard VAR–002–4.1
This Reliability Standard includes an
information collection activity for
‘‘Requirement R1’’ and a separate
information collection activity for
‘‘Requirements R2 through R6.’’
This Reliability Standard requires
Generator Operators to:
• Operate each of its generators
connected to the interconnected
transmission system in automatic
voltage control mode or in a different
control mode as instructed by the
Transmission Operator, unless the
Generator Operator (1) is exempted
pursuant to the criteria developed under
VAR–001–5, Requirement R4, or (2)
makes certain notifications to the
Transmission Operator specifying the
reasons it cannot so operate
(Requirement R1);
• Maintain the Transmission
Operator’s generator voltage or Reactive
Power schedule, unless the Generator
Operator (1) is exempted pursuant to the
criteria developed under VAR–001–5,
Requirement R4, or (2) complies with
16591
the notification requirements for
deviations as established by the
Transmission Owner pursuant to VAR–
001–5, Requirement R5 (Requirement
R2);
• Notify the Transmission Operator of
a change in status of its voltage
controlling device within 30 minutes,
unless the status is restored within that
time period (Requirement R3); and
• Notify the Transmission Operator of
a change in reactive capability due to
factors other than those described in
VAR–002–4.1, Requirement R3 within
30 minutes unless the capability has
been restored during that time period
(Requirement R4).
• Provide information on its step-up
transformers and auxiliary transformers
within 30 days of a request from the
Transmission Operator or Transmission
Planner (Requirement R5); and
• Comply with the Transmission
Operator’s step-up transformer tap
change directives unless compliance
would violate safety, an equipment
rating, or applicable laws, rules or
regulations (Requirement R6).
Type of Respondents: Generator
owners and transmission operators.
Estimate of Annual Burden: 4 The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–725X, MANDATORY RELIABILITY STANDARDS: VOLTAGE AND REACTIVE (VAR) STANDARDS
VAR–001–5 (Requirements R1–
R6).
VAR–002–4.1 (Requirement R1)
VAR–002–4.1 (Requirements
R2–R6).
jbell on DSKJLSW7X2PROD with NOTICES
Total ...................................
Number of
respondents 5
Annual number
of responses
per respondent
Total number
of responses
Average burden & cost
per response 6
Total annual burden hours &
total annual cost
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
167 (TOP) ........
1
167
160 hrs.; $11,721.73 ....
26,887 hrs.; $1,887,198.53 .......
$11,721.73
937 (GOP) ........
937 (GOP) ........
1
1
937
937
80 hrs.; $5,615.20 ........
120 hrs.; $8,422.80 ......
74,960 hrs.; $5,261,442.4 .........
112,440 hrs.; $7,892,163.6 .......
5,615.20
8,422.80
..........................
..........................
2,041
.......................................
214,287 hrs.; $15,040,804.53.
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
4 The Commission defines burden as the total
time, effort, or financial resources expended by
persons to generate, maintain, retain, or disclose or
provide information to or for a Federal agency. For
further explanation of what is included in the
VerDate Sep<11>2014
17:59 Mar 29, 2021
Jkt 253001
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
DEPARTMENT OF ENERGY
Dated: March 24, 2021.
Kimberly D. Bose,
Secretary.
[Docket No. RM19–12–000]
[FR Doc. 2021–06504 Filed 3–29–21; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
Revisions to the Filing Process for
Commission Forms; Notice of Eforms
Updates, Termination of Visual Foxpro
Filings, and Extension of Filing
Deadlines
As provided for in the July 17, 2020
Order on Technical Conference, notice
information collection burden, reference 5 Code of
Federal Regulations 1320.3.
5 TOP = transmission operator; GOP = generator
operators. Respondent counts based of the NERC
Compliance Registry numbers February 5, 2021.
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
6 The estimate for hourly cost is $70.19/hour.
This figure is the average salary plus benefits for an
electrical engineer (Occupation Code: 17–2071)
from the Bureau of Labor Statistics at https://
www.bls.gov/oes/current/naics2_22.htm.
E:\FR\FM\30MRN1.SGM
30MRN1
16592
Federal Register / Vol. 86, No. 59 / Tuesday, March 30, 2021 / Notices
is hereby given that on April 15, 2021,
the eXtensible Business Reporting
Language (XBRL) taxonomies,
validation rules, and rendering files
needed to file FERC Form Nos. 1, 1–F,
3–Q (electric), 2, 2–A, 3–Q (natural gas),
6, 6–Q (oil), 60, and 714 (collectively,
Commission Forms),1 will be updated to
Release 1.5.2 The updated taxonomies
will be available in the Yeti viewer at
https://xbrlview.ferc.gov/.3 The updated
validation rules and rendering files will
be available at https://www.ferc.gov/
ferc-online/ferc-online/filing-forms/
eforms-refresh. The eForms system will
incorporate the updated (Release 1.5)
taxonomies, validation rules, and
rendering files and use them to process
filers’ test-only submissions in May
2021. In addition, as noted below, the
deadlines for submitting the third
quarter 2021 filings of FERC Form Nos.
3–Q (electric), 3–Q (natural gas), and
6–Q (oil) are extended until December
31, 2021.
The updated (Release 1.5)
taxonomies, validation rules, and
rendering files will become effective
beginning with the third quarter 2021
filings of FERC Form Nos. 3–Q
(electric),
3–Q (natural gas), and 6–Q (oil). The
current Visual FoxPro-based system for
filing Commission Forms will no longer
be available for submissions after
September 30, 2021. Therefore, all
subsequent filings and any future
refilings, i.e., all post-September 30,
2021 filings and refilings, of the FERC
Form Nos. 3–Q (electric), 3–Q (natural
gas), and 6–Q (oil) and the other
Commission Forms (i.e., FERC Form
Nos. 1, 1–F, 2, 2–A, 6, 60, and 714) must
be made using the applicable
taxonomies, validation rules, and
rendering files for the relevant form, as
indicated on the eForms portal.
To provide the additional time
necessary to complete the transition to
an XBRL-based system, the deadlines
for the third quarter filings of the FERC
jbell on DSKJLSW7X2PROD with NOTICES
1 The
Commission adopted the XBRL process for
filing the Commission Forms in Order No. 859.
Revisions to the Filing Process for Comm’n Forms,
Order No. 859, 167 FERC ¶ 61,241 (2019).
2 The Commission adopted the final XBRL
taxonomy, protocols, implementation guide, and
other supporting documents, and established the
implementation schedule for filing the Commission
Forms following a technical conference in this
proceeding. Revisions to the Filing Process for
Comm’n Forms, 172 FERC ¶ 61,059 (2020). The
Commission also stated that technical updates, such
as the updates referenced here, will not take effect
until at least 60 days after issuance of a notice from
the Office of the Secretary. Id. P 26.
3 These technical updates incorporate feedback
on the taxonomies submitted by interested parties
through various means, including the Yeti review
tool.
VerDate Sep<11>2014
17:59 Mar 29, 2021
Jkt 253001
Form Nos. 3–Q (electric), 3–Q (natural
gas), and 6–Q (oil) are hereby extended.
Accordingly, the deadline for filing
the FERC Form No. 3–Q (electric) for
Major Electric Utilities, Licensees, and
Others for the third quarter of 2021 is
extended from November 29, 2021 until
December 31, 2021. The deadline for
filing the FERC Form No. 3–Q (electric)
for Non-major Public Utilities and
Licensees for the third quarter of 2021
is extended from December 9, 2021 until
December 31, 2021.
In addition, the deadline for filing the
FERC Form No. 3–Q (natural gas) for
Major Natural Gas Companies for the
third quarter of 2021 is extended from
November 29, 2021 until December 31,
2021. The deadline for filing the FERC
Form No. 3–Q (natural gas) for Nonmajor Gas Companies for the third
quarter of 2021 is extended from
December 9, 2021 until December 31,
2021.
Finally, the deadline for filing the
FERC Form No. 6–Q (oil) for Oil
Pipeline Companies for the third quarter
of 2021 is extended from December 9,
2021 until December 31, 2021.
Dated: March 23, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021–06477 Filed 3–29–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 6731–000[
Coneross Power Corporation; Notice
of Authorization for Continued Project
Operation
On February 28, 2019 Coneross Power
Corporation, licensee for the Coneross
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Coneross Hydroelectric Project is
on the Coneross Creek, in Oconee
County, South Carolina
The license for Project No.6731 was
issued for a period ending February 28,
2021. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No.6731 is
issued to the Coneross Power
Corporation for a period effective March
1, 2021 through February 28, 2022, or
until the issuance of a new license for
the project or other disposition under
the FPA, whichever comes first. If
issuance of a new license (or other
disposition) does not take place on or
before February 2022, notice is hereby
given that, pursuant to 18 CFR 16.18(c),
an annual license under section 15(a)(1)
of the FPA is renewed automatically
without further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the Coneross Power Corporation, is
authorized to continue operation of the
Coneross Hydroelectric Project, until
such time as the Commission acts on its
application for a subsequent license.
Dated: March 24, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–06511 Filed 3–29–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–67–000.
Applicants: Ventura Energy Storage,
LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act of Ventura Energy
Storage, LLC.
Filed Date: 3/22/21.
E:\FR\FM\30MRN1.SGM
30MRN1
Agencies
[Federal Register Volume 86, Number 59 (Tuesday, March 30, 2021)]
[Notices]
[Pages 16591-16592]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-06477]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. RM19-12-000]
Revisions to the Filing Process for Commission Forms; Notice of
Eforms Updates, Termination of Visual Foxpro Filings, and Extension of
Filing Deadlines
As provided for in the July 17, 2020 Order on Technical Conference,
notice
[[Page 16592]]
is hereby given that on April 15, 2021, the eXtensible Business
Reporting Language (XBRL) taxonomies, validation rules, and rendering
files needed to file FERC Form Nos. 1, 1-F, 3-Q (electric), 2, 2-A, 3-Q
(natural gas), 6, 6-Q (oil), 60, and 714 (collectively, Commission
Forms),\1\ will be updated to Release 1.5.\2\ The updated taxonomies
will be available in the Yeti viewer at https://xbrlview.ferc.gov/.\3\
The updated validation rules and rendering files will be available at
https://www.ferc.gov/ferc-online/ferc-online/filing-forms/eforms-refresh. The eForms system will incorporate the updated (Release 1.5)
taxonomies, validation rules, and rendering files and use them to
process filers' test-only submissions in May 2021. In addition, as
noted below, the deadlines for submitting the third quarter 2021
filings of FERC Form Nos. 3-Q (electric), 3-Q (natural gas), and 6-Q
(oil) are extended until December 31, 2021.
---------------------------------------------------------------------------
\1\ The Commission adopted the XBRL process for filing the
Commission Forms in Order No. 859. Revisions to the Filing Process
for Comm'n Forms, Order No. 859, 167 FERC ] 61,241 (2019).
\2\ The Commission adopted the final XBRL taxonomy, protocols,
implementation guide, and other supporting documents, and
established the implementation schedule for filing the Commission
Forms following a technical conference in this proceeding. Revisions
to the Filing Process for Comm'n Forms, 172 FERC ] 61,059 (2020).
The Commission also stated that technical updates, such as the
updates referenced here, will not take effect until at least 60 days
after issuance of a notice from the Office of the Secretary. Id. P
26.
\3\ These technical updates incorporate feedback on the
taxonomies submitted by interested parties through various means,
including the Yeti review tool.
---------------------------------------------------------------------------
The updated (Release 1.5) taxonomies, validation rules, and
rendering files will become effective beginning with the third quarter
2021 filings of FERC Form Nos. 3-Q (electric), 3-Q (natural gas), and
6-Q (oil). The current Visual FoxPro-based system for filing Commission
Forms will no longer be available for submissions after September 30,
2021. Therefore, all subsequent filings and any future refilings, i.e.,
all post-September 30, 2021 filings and refilings, of the FERC Form
Nos. 3-Q (electric), 3-Q (natural gas), and 6-Q (oil) and the other
Commission Forms (i.e., FERC Form Nos. 1, 1-F, 2, 2-A, 6, 60, and 714)
must be made using the applicable taxonomies, validation rules, and
rendering files for the relevant form, as indicated on the eForms
portal.
To provide the additional time necessary to complete the transition
to an XBRL-based system, the deadlines for the third quarter filings of
the FERC Form Nos. 3-Q (electric), 3-Q (natural gas), and 6-Q (oil) are
hereby extended.
Accordingly, the deadline for filing the FERC Form No. 3-Q
(electric) for Major Electric Utilities, Licensees, and Others for the
third quarter of 2021 is extended from November 29, 2021 until December
31, 2021. The deadline for filing the FERC Form No. 3-Q (electric) for
Non-major Public Utilities and Licensees for the third quarter of 2021
is extended from December 9, 2021 until December 31, 2021.
In addition, the deadline for filing the FERC Form No. 3-Q (natural
gas) for Major Natural Gas Companies for the third quarter of 2021 is
extended from November 29, 2021 until December 31, 2021. The deadline
for filing the FERC Form No. 3-Q (natural gas) for Non-major Gas
Companies for the third quarter of 2021 is extended from December 9,
2021 until December 31, 2021.
Finally, the deadline for filing the FERC Form No. 6-Q (oil) for
Oil Pipeline Companies for the third quarter of 2021 is extended from
December 9, 2021 until December 31, 2021.
Dated: March 23, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021-06477 Filed 3-29-21; 8:45 am]
BILLING CODE 6717-01-P