n. Project Description: The existing
Sandy Hollow Hydroelectric Project
consists of (1) a 20-acre reservoir at a
normal pool elevation of 419.1 feet
National Geodetic Vertical Datum of
1929; (2) a main 106-foot-long concrete
gravity dam with a maximum height of
25 feet that includes a 55-foot-long
spillway, and three 3- to 4-foot-high
concrete diversion spillway dams that
are 21 feet, 46 feet and 64 feet long,
respectively; (3) a 23-foot-long by 23foot-wide brick and concrete
powerhouse containing a 150-kilowatt
(kW), a 265-kW, and a 400-kW turbinegenerator unit; (4) two 12- to 15-footlong, 6-foot-diameter steel penstocks,
with one penstock that bifurcates before
joining the two turbine units; (5) two
trash racks; (6) a 400-foot-long tailrace
channel; (7) a 480-volt, 300-foot-long
transmission line connecting to a 480volt to 23-kilovolt step-up transformer at
a nearby substation; and (8) appurtenant
facilities. The average annual generation
was 933 megawatt-hours between 2012
and 2017.
The project is operated in a run-ofriver mode and discharges a minimum
flow of 35 cubic feet per second (cfs) or
inflow to the reservoir, whichever is
less, into the project’s bypassed reach
for the protection and enhancement of
aquatic resources.
As part of the license application,
Sandy Hollow Hydro filed a settlement
agreement entered into between itself,
the U.S. Fish and Wildlife Service, and
the New York State Department of
Environmental Conservation. As part of
the settlement agreement, Sandy Hollow
Hydro proposes to: (1) Continue to
operate the project in a run-of-river
mode; (2) provide a year-round
minimum flow in the bypassed reach of
35 cfs, or inflow, whichever is less; (3)
continue the existing stream flow and
water level monitoring; (4) maintain the
existing trash rack on turbine unit 3
with 1-inch clear spacing and, within 5
years of any license issued for the
project, install trash racks with either
1-inch clear spacing or the equivalent
(e.g., an overlay-type system) on turbine
units 1 and 2; (5) within 3 years of the
effective date of any license issued for
the project, install and maintain a yearround downstream fish passage
structure at one of the three diversion
spillway dams; (6) maintain the existing
portage trail; and (7) implement the
Invasive Species Management Plan filed
with the final license application.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
VerDate Sep<11>2014
16:52 Mar 15, 2021
Jkt 253001
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–5728).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Issue Deficiency Letter (if
necessary).
Request Additional Information.
Issue Acceptance Letter .......
Issue Scoping Document 1
for comments.
Request Additional Information (if necessary).
Issue Scoping Document 2 ..
Issue Notice of Ready for
Environmental Analysis.
April 2021
July 2021
August 2021
October 2021
[FR Doc. 2021–05389 Filed 3–15–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator Status
Frm 00022
Fmt 4703
EG21–52–000
EG21–53–000
EG21–54–000
EG21–55–000
EG21–57–000
EG21–58–000
EG21–59–000
EG21–60–000
EG21–61–000
EG21–62–000
EG21–63–000
Take notice that during the month of
February 2021, the status of the abovecaptioned entities as Exempt Wholesale
Generators became effective by
operation of the Commission’s
regulations. 18 CFR 366.7(a) (2020).
Dated: March 10, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–05388 Filed 3–15–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15060–000]
November
2021
November
2021
Dated: March 10, 2021.
Kimberly D. Bose,
Secretary.
PO 00000
EG21–50–000
EG21–51–000
April 2021
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Wolf Ridge Wind Energy,
LLC.
Blue Summit I Wind, LLC ...
Dickerson Power, LLC .........
Morgantown Power, LLC .....
Morgantown Station, LLC ....
Water Strider Solar, LLC .....
325MK 8ME LLC ..................
Chalk Point Power, LLC ......
Flat Ridge 2 Wind Energy
LLC.
Harry Allen Solar Energy
LLC.
Centerfield Cooper Solar,
LLC.
PGR Lessee O, LLC ..............
Dry Lake Solar Holdings
LLC.
HO Clarke II, LLC .................
Indiana Crossroads Wind
Farm LLC.
Wallingford Renewable Energy LLC.
Topaz II, LLC ........................
Braes Bayou Generating,
LLC.
KCE TX 23, LLC ...................
Midway-Sunset Cogeneration Company.
EG21–43–000
EG21–44–000
EG21–45–000
EG21–46–000
EG21–47–000
EG21–48–000
EG21–49–000
Sfmt 4703
Kinet, Inc.; Notice of Preliminary
Permit Application Accepted For Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On December 3, 2020, Kinet, Inc.,
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of a conventional
hydropower project located in
Jessamine, Woodford, and Mercer
Counties, Kentucky. The sole purpose of
a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed Kentucky River Lock
and Dam No. 6 Hydroelectric Project
would consist of the following: (1) An
existing 465-foot-long, 34-foot-high,
timber crib dam with concrete overlay
connected to a 280-foot-long, and 45foot-wide abandoned navigation lock,
which are owned by the Kentucky River
E:\FR\FM\16MRN1.SGM
16MRN1
Agencies
[Federal Register Volume 86, Number 49 (Tuesday, March 16, 2021)]
[Notices]
[Page 14424]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-05388]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Effectiveness of Exempt Wholesale Generator Status
Wolf Ridge Wind Energy, LLC.............. EG21-43-000
Blue Summit I Wind, LLC.................. EG21-44-000
Dickerson Power, LLC..................... EG21-45-000
Morgantown Power, LLC.................... EG21-46-000
Morgantown Station, LLC.................. EG21-47-000
Water Strider Solar, LLC................. EG21-48-000
325MK 8ME LLC............................ EG21-49-000
Chalk Point Power, LLC................... EG21-50-000
Flat Ridge 2 Wind Energy LLC............. EG21-51-000
Harry Allen Solar Energy LLC............. EG21-52-000
Centerfield Cooper Solar, LLC............ EG21-53-000
PGR Lessee O, LLC........................ EG21-54-000
Dry Lake Solar Holdings LLC.............. EG21-55-000
HO Clarke II, LLC........................ EG21-57-000
Indiana Crossroads Wind Farm LLC......... EG21-58-000
Wallingford Renewable Energy LLC......... EG21-59-000
Topaz II, LLC............................ EG21-60-000
Braes Bayou Generating, LLC.............. EG21-61-000
KCE TX 23, LLC........................... EG21-62-000
Midway-Sunset Cogeneration Company....... EG21-63-000
Take notice that during the month of February 2021, the status of
the above-captioned entities as Exempt Wholesale Generators became
effective by operation of the Commission's regulations. 18 CFR 366.7(a)
(2020).
Dated: March 10, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-05388 Filed 3-15-21; 8:45 am]
BILLING CODE 6717-01-P