Lock 7 Hydro Partners, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 12680-12681 [2021-04466]
Download as PDF
jbell on DSKJLSW7X2PROD with NOTICES
12680
Federal Register / Vol. 86, No. 41 / Thursday, March 4, 2021 / Notices
Hydroland, Inc., 403 Madison Ave. N
#240, Bainbridge Island, WA 98110;
(844) 493–7612; email—tim@
hydrolandcorp.com.
i. FERC Contact: Jeremy Feinberg at
(202) 502–6893; or email at
jeremy.feinberg@ferc.gov.
j. Triton Power filed its request to use
the Traditional Licensing Process on
December 31, 2020. Triton Power
provided public notice of its request on
December 29, 2020. In a letter dated
February 26, 2021, the Director of the
Division of Hydropower Licensing
approved Triton Power’s request to use
the Traditional Licensing Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
New York State Historic Preservation
Officer, as required by section 106,
National Historic Preservation Act, and
the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Triton Power as the Commission’s nonfederal representative for carrying out
informal consultation pursuant to
section 7 of the Endangered Species Act
and consultation pursuant to section
106 of the National Historic
Preservation Act.
m. Triton Power filed a PreApplication Document (PAD; including
a proposed process plan and schedule)
with the Commission, pursuant to 18
CFR 5.6 of the Commission’s
regulations.
n. A copy of the PAD may be viewed
and/or printed on the Commission’s
website (https://www.ferc.gov), using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 5698.
VerDate Sep<11>2014
20:27 Mar 03, 2021
Jkt 253001
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by December 31, 2023.
p. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: February 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–04467 Filed 3–3–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. AD21–6–000; AD20–6–000]
RTO/ISO Credit Principles and
Practices; Credit Reforms in Organized
Wholesale Electric Markets;
Supplemental Notice of Technical
Conference
Correction
In notice document 2021–04261,
appearing on page 12187 in the issue of
Tuesday, March 2, 2021, make the
following correction:
On page 12187, in the first column, on
the twenty-seventh line from the bottom
of the page, the docket number is
corrected to read as set forth above.
[FR Doc. C1–2021–04261 Filed 3–3–21; 8:45 am]
BILLING CODE 1301–00–D
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 539–015]
Lock 7 Hydro Partners, LLC; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 539–015.
c. Date filed: April 30, 2020.
d. Applicant: Lock 7 Hydro Partners,
LLC (Lock 7 Partners).
PO 00000
Frm 00088
Fmt 4703
Sfmt 4703
e. Name of Project: Mother Ann Lee
Hydroelectric Station Water Power
Project (Mother Ann Lee Project).
f. Location: The project is located on
the Kentucky River in Mercer,
Jessamine, and Garrard Counties,
Kentucky. The project does not occupy
federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: David Brown
Kinloch, Lock 7 Hydro Partners, 414 S
Wenzel St., Louisville, Kentucky 40204;
(502) 589–0975, or kyhydropower@
gmail.com.
i. FERC Contact: Joshua Dub at (202)
502–8138, or joshua.dub@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
k. This application has been accepted
and is now ready for environmental
analysis.
The Council on Environmental
Quality (CEQ) issued a final rule on July
15, 2020, revising the regulations under
40 CFR parts 1500–1518 that federal
agencies use to implement NEPA (see
Update to the Regulations Implementing
the Procedural Provisions of the
National Environmental Policy Act, 85
FR 43,304). The Final Rule became
effective on and applies to any NEPA
process begun after September 14, 2020.
An agency may also apply the
regulations to ongoing activities and
environmental documents begun before
September 14, 2020, which includes the
proposed Mother Ann Lee Project.
Commission staff intends to conduct its
NEPA review in accordance with CEQ’s
new regulations.
l. The Mother Ann Lee Project
consists of the following existing
facilities: (1) A reservoir with a surface
area of 777 acres and a storage capacity
of 5,828 acre-feet at elevation 513.12
feet National Geodetic Vertical Datum of
1929; (2) a 250-foot-long, 15.3-foot-high,
E:\FR\FM\04MRN1.SGM
04MRN1
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 86, No. 41 / Thursday, March 4, 2021 / Notices
timber crib dam with a concrete cap and
an abandoned 62-foot-long lock
structure on the east side; (3) a 120-footlong, 100-foot-wide forebay; (4) a 24foot-tall, 84-foot-wide trashrack; (5) a
93-foot-long, 25-foot-wide, 16-foot-high
powerhouse integral with the dam
containing three turbine-generating
units with a total installed capacity of
2,210 kilowatts; (6) a 30-foot-long, 15.3foot-high concrete spillway section that
extends from the powerhouse to the
west shore; (7) an 85-foot-long
substation; and (8) a 34.5 kilovolt,
4,540-foot-long transmission line. The
project is estimated to generate an
average of 9,200 megawatt-hours
annually.
Lock 7 Partners proposes to continue
operating the project in a run-of-river
mode. In addition, the applicant
proposes to construct, operate, and
maintain a canoe portage, fishing access,
and parking area at the Mother Ann Lee
Project.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
VerDate Sep<11>2014
20:27 Mar 03, 2021
Jkt 253001
the schedule will be made as
appropriate.
Milestone
Target date
Deadline for Filing Comments, Recommendations, and Agency
Terms and Conditions/
Prescriptions.
Deadline for Filing Reply
Comments.
April 2021.
June 2021.
Dated: February 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–04466 Filed 3–3–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4026–054]
Androscoggin Reservoir Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Non-Capacity
Amendment of License.
b. Project No.: 4026–054.
c. Date Filed: December 31, 2020, and
supplemented on February 11, 2021.
d. Applicant: Androscoggin Reservoir
Company.
e. Name of Project: Aziscohos
Hydroelectric Project.
f. Location: The project is located on
the Magalloway River in Oxford County,
Maine.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Randall
Dorman, Licensing Manager, Brookfield
Renewable, 150 Main Street, Lewiston,
ME 04240; telephone (207) 755–5605
and email randy.dorman@
brookfieldrenewable.com.
i. FERC Contact: Linda Stewart, (202)
502–8184, linda.stewart@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance date of this
notice by the Commission.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
PO 00000
Frm 00089
Fmt 4703
Sfmt 4703
12681
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–4026–054. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, it must also
serve a copy of the document on that
resource agency.
k. Description of Request: The
Androscoggin Reservoir Company
(licensee) proposes to administratively
remove from the project license the
existing 23.5-mile-long, 34.5-kilovolt
transmission line. The licensee specifies
that the transmission line, which is
owned by Central Maine Power
Company, should no longer be included
in the license as a primary line because
the line does not solely transmit power
from the project to the interconnected
grid, but also transmits power from the
grid to the customers of the utility.
Further, the licensee states that the
point of interconnection of project
power with the transmission grid occurs
at the existing substation located
adjacent to the powerhouse.
l. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
E:\FR\FM\04MRN1.SGM
04MRN1
Agencies
[Federal Register Volume 86, Number 41 (Thursday, March 4, 2021)]
[Notices]
[Pages 12680-12681]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-04466]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 539-015]
Lock 7 Hydro Partners, LLC; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 539-015.
c. Date filed: April 30, 2020.
d. Applicant: Lock 7 Hydro Partners, LLC (Lock 7 Partners).
e. Name of Project: Mother Ann Lee Hydroelectric Station Water
Power Project (Mother Ann Lee Project).
f. Location: The project is located on the Kentucky River in
Mercer, Jessamine, and Garrard Counties, Kentucky. The project does not
occupy federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: David Brown Kinloch, Lock 7 Hydro Partners,
414 S Wenzel St., Louisville, Kentucky 40204; (502) 589-0975, or
[email protected].
i. FERC Contact: Joshua Dub at (202) 502-8138, or
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://ferconline.ferc.gov/QuickComment.aspx. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY).
k. This application has been accepted and is now ready for
environmental analysis.
The Council on Environmental Quality (CEQ) issued a final rule on
July 15, 2020, revising the regulations under 40 CFR parts 1500-1518
that federal agencies use to implement NEPA (see Update to the
Regulations Implementing the Procedural Provisions of the National
Environmental Policy Act, 85 FR 43,304). The Final Rule became
effective on and applies to any NEPA process begun after September 14,
2020. An agency may also apply the regulations to ongoing activities
and environmental documents begun before September 14, 2020, which
includes the proposed Mother Ann Lee Project. Commission staff intends
to conduct its NEPA review in accordance with CEQ's new regulations.
l. The Mother Ann Lee Project consists of the following existing
facilities: (1) A reservoir with a surface area of 777 acres and a
storage capacity of 5,828 acre-feet at elevation 513.12 feet National
Geodetic Vertical Datum of 1929; (2) a 250-foot-long, 15.3-foot-high,
[[Page 12681]]
timber crib dam with a concrete cap and an abandoned 62-foot-long lock
structure on the east side; (3) a 120-foot-long, 100-foot-wide forebay;
(4) a 24-foot-tall, 84-foot-wide trashrack; (5) a 93-foot-long, 25-
foot-wide, 16-foot-high powerhouse integral with the dam containing
three turbine-generating units with a total installed capacity of 2,210
kilowatts; (6) a 30-foot-long, 15.3-foot-high concrete spillway section
that extends from the powerhouse to the west shore; (7) an 85-foot-long
substation; and (8) a 34.5 kilovolt, 4,540-foot-long transmission line.
The project is estimated to generate an average of 9,200 megawatt-hours
annually.
Lock 7 Partners proposes to continue operating the project in a
run-of-river mode. In addition, the applicant proposes to construct,
operate, and maintain a canoe portage, fishing access, and parking area
at the Mother Ann Lee Project.
m. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support.
All filings must (1) bear in all capital letters the title
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Deadline for Filing Comments, April 2021.
Recommendations, and Agency Terms and
Conditions/Prescriptions.
Deadline for Filing Reply Comments........ June 2021.
------------------------------------------------------------------------
Dated: February 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-04466 Filed 3-3-21; 8:45 am]