Sappi North America, Inc., Presumpscot Hydro LLC; Notice of Application for Transfer of License and Lease of Project Lands Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 7723-7724 [2021-02059]
Download as PDF
Federal Register / Vol. 86, No. 19 / Monday, February 1, 2021 / Notices
via USPS, use the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
To mail via any other courier, use the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on February 11, 2021.
Dated: January 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–02060 Filed 1–29–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–47–000.
Applicants: R–WS Antelope Valley
Gen-Tie, LLC, Portal Ridge Solar A,
LLC, OMERS Administration
Corporation.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act of R–WS Antelope
Valley Gen-Tie, LLC, et al.
Filed Date: 1/25/21.
Accession Number: 20210125–5231.
Comments Due: 5 p.m. ET 2/16/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2633–039.
Applicants: Birchwood Power
Partners, L.P.
Description: Notice of Change in
Status of Birchwood Power Partners,
L.P.
Filed Date: 1/22/21.
Accession Number: 20210122–5128.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER10–2924–015.
Applicants: Kleen Energy Systems,
LLC.
Description: Notice of Non-Material
Change in Status of Kleen Energy
Systems, LLC.
Filed Date: 1/26/21.
Accession Number: 20210126–5111.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER19–2757–003.
Applicants: California Independent
System Operator Corporation.
Description: Compliance filing: 2021–
01–26 Petition for Limited Tariff
Waiver—Postpone Eff. Date to June 2021
to be effective N/A.
VerDate Sep<11>2014
16:57 Jan 29, 2021
Jkt 253001
Filed Date: 1/26/21.
Accession Number: 20210126–5104.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER21–639–000.
Applicants: Wapello Solar LLC.
Description: Supplement to December
14, 2020 Wapello Solar LLC tariff filing.
Filed Date: 1/21/21.
Accession Number: 20210121–5316.
Comments Due: 5 p.m. ET 2/5/21.
Docket Numbers: ER21–940–000.
Applicants: Hardin Solar Energy LLC.
Description: Baseline eTariff Filing:
Shared Facilities Agreement to be
effective 1/26/2021.
Filed Date: 1/25/21.
Accession Number: 20210125–5214.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER21–941–000.
Applicants: ISO New England Inc.,
New England Power Pool Participants
Committee.
Description: Compliance filing: ISO–
NE and NEPOOL; Revisions to Schedule
24 to Comply with Order No. 676–I to
be effective 12/31/9998.
Filed Date: 1/26/21.
Accession Number: 20210126–5034.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER21–942–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
Amended GIA Windpower Partner
1993, LLC Renwind Project SA No. 375
to be effective 1/27/2021.
Filed Date: 1/26/21.
Accession Number: 20210126–5061.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER21–943–000.
Applicants: ISO New England Inc.
Description: § 205(d) Rate Filing: ISO–
NE; Revisions to Obligations of Energy
Efficiency Resources Under PFP to be
effective 4/1/2021.
Filed Date: 1/26/21.
Accession Number: 20210126–5084.
Comments Due: 5 p.m. ET 2/16/21.
Docket Numbers: ER21–944–000.
Applicants: Southwestern Electric
Power Company.
Description: § 205(d) Rate Filing:
Bentonville PSA to be effective 3/28/
2021.
Filed Date: 1/26/21.
Accession Number: 20210126–5132.
Comments Due: 5 p.m. ET 2/16/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
7723
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 26, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021–02094 Filed 1–29–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. 2897–052, 2931–044, 2932–
051, 2941–047, 2942–054, and 2984–123]
Sappi North America, Inc.,
Presumpscot Hydro LLC; Notice of
Application for Transfer of License and
Lease of Project Lands Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Transfer of
License and Lease of Project Lands.
b. Project Nos.: 2897–052, 2931–044,
2932–051, 2941–047, 2942–054, and
2984–123.
c. Date Filed: October 20, 2020.
d. Applicants: Sappi North America,
Inc. (Transferor). Presumpscot Hydro
LLC (Transferee).
e. Name of Projects: Saccarappa,
Gambo, Mallison Falls, Little Falls,
Dundee, and Eel Weir.
f. Location: The Saccarappa, Gambo,
Mallison Falls, Little Falls, Dundee
projects are located on the Presumpscot
River, in the Towns of Gorham and
Windham and the City of Westbrook in
Cumberland County, Maine. The Eel
Weir Project is located on Sebago Lake
near the cities of Standish and
Windham in Cumberland County,
Maine.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contacts:
For Transferor: Ms. Briana O’Regan,
Sappi North America, Inc., 179 John
Roberts Road, South Portland, ME
04106, phone: (207) 854–7070, Email:
briana.oregan@sappi.com.
E:\FR\FM\01FEN1.SGM
01FEN1
7724
Federal Register / Vol. 86, No. 19 / Monday, February 1, 2021 / Notices
For Transferor and Transferee: Mr.
Matthew D. Manahan, Counsel for
Transferor and Transferee, Pierce
Atwood LLP, 254 Commercial St.,
Portland, ME 04101, phone: (207) 791–
1189, Email: mmanahan@
pierceatwood.com.
i. FERC Contact: Mrs. Anumzziatta
Purchiaroni, (202) 502–6191 or
Anumzziatta.purchiaroni@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
Within 30 days from the issuance date
of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–2897–052, P–2931–044, P–
2932–051, P–2941–047, P–2942–054,
and P–2984–123. Comments emailed to
Commission staff are not considered
part of the Commission record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a resource agency, it must also serve
a copy of the document on that resource
agency.
k. Description of Transfer and Lease
of Project Lands Request: The applicants
request that the Commission approve
the transfer of the following projects
from Sappi North America, Inc. (Sappi
or Transferor) to Presumpscot Hydro
LLC (Presumpscot or Transferee):
Saccarappa Project No. 2897, Gambo
Project No. 2931, Mallison Falls Project
No. 2932, Little Falls Project No. 2941,
Dundee Project No. 2942, and Eel Weir
VerDate Sep<11>2014
16:57 Jan 29, 2021
Jkt 253001
Project No. 2984–123. The applicants
propose the transfer because of an
internal corporate reorganization that
resulted in the formation of the Sappi
subsidiary, Presumpscot. As part of the
proposed transfers, the Transferor
would retain ownership of the
transmission line properties between
the Dundee Project and Transferor’s
Westbrook Mill. In addition, the
Transferor would retain ownership of
the transmission line properties
between the Mallison Falls Project and
Transferors’ Westbrook Mill (which
transmission line connects the Gambo,
Little Falls, and Mallison Falls projects
to the mill). The applicants request
Commission approval to lease the
transmission line property to the
Transferee. Furthermore, the Transferor
requests approval to lease to the
Transferee certain lands associated with
the Saccarappa Project, including
property associated with required fish
passage facilities. By an Order issued on
April 4, 2019, the Commission approved
a surrender of the Saccarappa Project
license and related license amendments
for the Mallison Falls, Little Falls,
Gambo, and Dundee Projects. The
license surrender would become
effective upon removal of the
Saccarappa Dam and other project
works, installation of fish passage
facilities, and the completion of other
requirements. The completed fish
passage facilities would become part of
the Mallison Falls Project. The
applicants also request Commission
approval to convey in fee the proposed
leased lands occupied by the fish
passage facilities to the Transferee once
the surrender becomes effective.
l. Locations of the Applications: The
Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
Agencies may obtain copies of the
application directly from the applicants.
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
toll free, (866) 208–3676 or TTY, (202)
502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: January 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–02059 Filed 1–29–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF HEALTH AND
HUMAN SERVICES
Centers for Disease Control and
Prevention
Notice of Closed Meeting
Pursuant to section 10(d) of the
Federal Advisory Committee Act, as
amended, notice is hereby given of the
following meeting.
The meeting will be closed to the
public in accordance with the
provisions set forth in sections
552b(c)(4) and 552b(c)(6), Title 5 U.S.C.,
as amended, and the Determination of
E:\FR\FM\01FEN1.SGM
01FEN1
Agencies
[Federal Register Volume 86, Number 19 (Monday, February 1, 2021)]
[Notices]
[Pages 7723-7724]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-02059]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. 2897-052, 2931-044, 2932-051, 2941-047, 2942-054, and
2984-123]
Sappi North America, Inc., Presumpscot Hydro LLC; Notice of
Application for Transfer of License and Lease of Project Lands Accepted
for Filing and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Transfer of License and Lease of Project
Lands.
b. Project Nos.: 2897-052, 2931-044, 2932-051, 2941-047, 2942-054,
and 2984-123.
c. Date Filed: October 20, 2020.
d. Applicants: Sappi North America, Inc. (Transferor). Presumpscot
Hydro LLC (Transferee).
e. Name of Projects: Saccarappa, Gambo, Mallison Falls, Little
Falls, Dundee, and Eel Weir.
f. Location: The Saccarappa, Gambo, Mallison Falls, Little Falls,
Dundee projects are located on the Presumpscot River, in the Towns of
Gorham and Windham and the City of Westbrook in Cumberland County,
Maine. The Eel Weir Project is located on Sebago Lake near the cities
of Standish and Windham in Cumberland County, Maine.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contacts:
For Transferor: Ms. Briana O'Regan, Sappi North America, Inc., 179
John Roberts Road, South Portland, ME 04106, phone: (207) 854-7070,
Email: [email protected].
[[Page 7724]]
For Transferor and Transferee: Mr. Matthew D. Manahan, Counsel for
Transferor and Transferee, Pierce Atwood LLP, 254 Commercial St.,
Portland, ME 04101, phone: (207) 791-1189, Email:
[email protected].
i. FERC Contact: Mrs. Anumzziatta Purchiaroni, (202) 502-6191 or
[email protected].
j. Deadline for filing comments, motions to intervene, and
protests: Within 30 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please
send a paper copy to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any
filing should include docket number P-2897-052, P-2931-044, P-2932-051,
P-2941-047, P-2942-054, and P-2984-123. Comments emailed to Commission
staff are not considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a resource agency, it must also serve a copy of the
document on that resource agency.
k. Description of Transfer and Lease of Project Lands Request: The
applicants request that the Commission approve the transfer of the
following projects from Sappi North America, Inc. (Sappi or Transferor)
to Presumpscot Hydro LLC (Presumpscot or Transferee): Saccarappa
Project No. 2897, Gambo Project No. 2931, Mallison Falls Project No.
2932, Little Falls Project No. 2941, Dundee Project No. 2942, and Eel
Weir Project No. 2984-123. The applicants propose the transfer because
of an internal corporate reorganization that resulted in the formation
of the Sappi subsidiary, Presumpscot. As part of the proposed
transfers, the Transferor would retain ownership of the transmission
line properties between the Dundee Project and Transferor's Westbrook
Mill. In addition, the Transferor would retain ownership of the
transmission line properties between the Mallison Falls Project and
Transferors' Westbrook Mill (which transmission line connects the
Gambo, Little Falls, and Mallison Falls projects to the mill). The
applicants request Commission approval to lease the transmission line
property to the Transferee. Furthermore, the Transferor requests
approval to lease to the Transferee certain lands associated with the
Saccarappa Project, including property associated with required fish
passage facilities. By an Order issued on April 4, 2019, the Commission
approved a surrender of the Saccarappa Project license and related
license amendments for the Mallison Falls, Little Falls, Gambo, and
Dundee Projects. The license surrender would become effective upon
removal of the Saccarappa Dam and other project works, installation of
fish passage facilities, and the completion of other requirements. The
completed fish passage facilities would become part of the Mallison
Falls Project. The applicants also request Commission approval to
convey in fee the proposed leased lands occupied by the fish passage
facilities to the Transferee once the surrender becomes effective.
l. Locations of the Applications: The Commission provides all
interested persons an opportunity to view and/or print the contents of
this document via the internet through the Commission's website at
https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number
excluding the last three digits in the docket number field to access
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and
issuances related to this or other pending projects. Agencies may
obtain copies of the application directly from the applicants. At this
time, the Commission has suspended access to the Commission's Public
Reference Room due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
[email protected] or call toll free, (866) 208-3676 or TTY,
(202) 502-8659.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. Any filing made by an intervenor must be accompanied
by proof of service on all persons listed in the service list prepared
by the Commission in this proceeding, in accordance with 18 CFR
385.2010.
Dated: January 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-02059 Filed 1-29-21; 8:45 am]