Transcontinental Gas Pipe Line Company, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 7379-7380 [2021-01872]

Download as PDF Federal Register / Vol. 86, No. 17 / Thursday, January 28, 2021 / Notices Accession Number: 20210121–5290. Comments Due: 5 p.m. ET 2/11/21. Docket Numbers: ER21–930–000. Applicants: American Transmission Systems, Incorporated, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: ATSI submits ECSAs, SA Nos. 5913, 5914, and 5915 to be effective 3/24/ 2021. Filed Date: 1/22/21. Accession Number: 20210122–5034. Comments Due: 5 p.m. ET 2/12/21. Docket Numbers: ER21–931–000. Applicants: NorthWestern Corporation. Description: § 205(d) Rate Filing: SA 905—Agreement to Provide Services with GCC Three Forks LLC to be effective 1/25/2021. Filed Date: 1/22/21. Accession Number: 20210122–5072. Comments Due: 5 p.m. ET 2/12/21. Docket Numbers: ER21–932–000. Applicants: Louisville Gas & Electric Company. Description: Notice of Termination of a Transmission Lease Agreement of Louisville Gas and Electric Company. Filed Date: 1/22/21. Accession Number: 20210122–5079. Comments Due: 5 p.m. ET 2/12/21. Docket Numbers: ER21–933–000. Applicants: Peetz Table Wind Energy, LLC. Description: Tariff Cancellation: Peetz Table Wind Energy, LLC Cancellation of MBR Tariff to be effective 1/23/2021. Filed Date: 1/22/21. Accession Number: 20210122–5119. Comments Due: 5 p.m. ET 2/12/21. Docket Numbers: ER21–934–000. Applicants: Northern Colorado Wind Energy, LLC. Description: Tariff Cancellation: Northern Colorado Wind Energy, LLC Cancellation of MBR Tariff to be effective 1/23/2021. Filed Date: 1/22/21. Accession Number: 20210122–5121. Comments Due: 5 p.m. ET 2/12/21. Docket Numbers: ER21–935–000. Applicants: Crowned Ridge Interconnection, LLC. Description: Tariff Cancellation: Crowned Ridge Interconnection, LLC, to be effective 1/23/2021. Filed Date: 1/22/21. Accession Number: 20210122–5126. Comments Due: 5 p.m. ET 2/12/21. Take notice that the Commission received the following public utility holding company filings: Docket Numbers: PH21–7–000. Applicants: BlackRock, Inc. Description: BlackRock, Inc. submits FERC–65–A Notice of Change in Fact to Exemption Notification. VerDate Sep<11>2014 17:16 Jan 27, 2021 Jkt 253001 Filed Date: 1/21/21. Accession Number: 20210121–5318. Comments Due: 5 p.m. ET 2/11/21. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/docs-filing/ efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–01870 Filed 1–27–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–27–000] Transcontinental Gas Pipe Line Company, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on January 12, 2021, Transcontinental Gas Pipe Line Company, LLC (Transco), Post Office Box 1396, Houston, Texas 77251–1396, filed in the above referenced docket, a prior notice request pursuant to sections 157.205 and 157.216 of the Commission’s regulations under the Natural Gas Act (NGA) and Transco’s blanket certificate issued in Docket No. CP82–426–000, for authorization to abandon approximately 6.57 miles of pipeline that consists of an 8-inchdiameter supply lateral and approximately 6.56 miles of pipeline that consists of three 16-inch-diameter supply laterals extending from Ship Shoal Block 233, Platform B to Ship Shoal Block 214, Platform C and appurtenant metering facilities (Supply Laterals), all in Federal offshore waters, offshore Louisiana, all as more fully set PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 7379 forth in the application which is on file with the Commission and open to public inspection. Transco states that the abandonment of the Supply Laterals will have no impact on the daily design capacity or operating conditions of Transco’s system, nor will the abandonment have any adverse impact on Transco’s existing customers. Additionally, Transco states that the Supply Laterals have not provided service to any customers for the last 12 months. The estimated cost of the abandonment is $3,182,902. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding this prior notice request should be directed to Jordan Kirwin, Director, Rates & Regulatory, Transcontinental Gas Pipe Line Company, LLC, P.O. Box 1396, Houston, Texas 77251 at (713) 215–3723 or by email at Jordan.Kirwin@ Williams.com. Public Participation There are three ways to become involved in the Commission’s review of this project: You can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on March 23, 2021. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the E:\FR\FM\28JAN1.SGM 28JAN1 7380 Federal Register / Vol. 86, No. 17 / Thursday, January 28, 2021 / Notices NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is March 23, 2021. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is March 23, 2021. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the 1 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 3 18 CFR 157.205(e). 4 18 CFR 385.214. 5 18 CFR 157.10. 2 Persons VerDate Sep<11>2014 17:16 Jan 27, 2021 Jkt 253001 time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before March 23, 2021. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP21–27–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 6 (2) You can file a paper copy of your submission by mailing it to the address below.7 Your submission must reference the Project docket number CP21–27– 000. Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. 6 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. 7 Hand-delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 Protests and motions to intervene must be served on the applicant either by mail at: P.O. Box 1396, Houston, Texas 77251 at (713) 215–3723 or email (with a link to the document) at: Jordan.Kirwin@Williams.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: January 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–01872 Filed 1–27–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–26–000] Transcontinental Gas Pipe Line Company, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on January 12, 2021, Transcontinental Gas Pipe Line Company, LLC (Transco), P.O. Box 1396, Houston, TX 77251, filed in the above referenced docket a prior notice pursuant to Section 157.205 and 157.216 of the Federal Energy Regulatory Commission’s regulations under the Natural Gas Act, requesting authorization to abandon an existing 6inch supply lateral extending from E:\FR\FM\28JAN1.SGM 28JAN1

Agencies

[Federal Register Volume 86, Number 17 (Thursday, January 28, 2021)]
[Notices]
[Pages 7379-7380]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-01872]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP21-27-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Request 
Under Blanket Authorization and Establishing Intervention and Protest 
Deadline

    Take notice that on January 12, 2021, Transcontinental Gas Pipe 
Line Company, LLC (Transco), Post Office Box 1396, Houston, Texas 
77251-1396, filed in the above referenced docket, a prior notice 
request pursuant to sections 157.205 and 157.216 of the Commission's 
regulations under the Natural Gas Act (NGA) and Transco's blanket 
certificate issued in Docket No. CP82-426-000, for authorization to 
abandon approximately 6.57 miles of pipeline that consists of an 8-
inch-diameter supply lateral and approximately 6.56 miles of pipeline 
that consists of three 16-inch-diameter supply laterals extending from 
Ship Shoal Block 233, Platform B to Ship Shoal Block 214, Platform C 
and appurtenant metering facilities (Supply Laterals), all in Federal 
offshore waters, offshore Louisiana, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection.
    Transco states that the abandonment of the Supply Laterals will 
have no impact on the daily design capacity or operating conditions of 
Transco's system, nor will the abandonment have any adverse impact on 
Transco's existing customers. Additionally, Transco states that the 
Supply Laterals have not provided service to any customers for the last 
12 months. The estimated cost of the abandonment is $3,182,902.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this prior notice request should be 
directed to Jordan Kirwin, Director, Rates & Regulatory, 
Transcontinental Gas Pipe Line Company, LLC, P.O. Box 1396, Houston, 
Texas 77251 at (713) 215-3723 or by email at 
[email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: You can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on March 23, 2021. 
How to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the

[[Page 7380]]

NGA,\1\ any person \2\ or the Commission's staff may file a protest to 
the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is March 23, 2021. A protest may also serve 
as a motion to intervene so long as the protestor states it also seeks 
to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is March 23, 2021. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before March 23, 2021. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP21-27-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below.\7\ Your submission must reference the Project docket 
number CP21-27-000.
---------------------------------------------------------------------------

    \7\ Hand-delivered submissions in docketed proceedings should be 
delivered to Health and Human Services, 12225 Wilkins Avenue, 
Rockville, Maryland 20852.

Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426

    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected]
    Protests and motions to intervene must be served on the applicant 
either by mail at: P.O. Box 1396, Houston, Texas 77251 at (713) 215-
3723 or email (with a link to the document) at: 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: January 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-01872 Filed 1-27-21; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.