Transcontinental Gas Pipe Line Company, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 7379-7380 [2021-01872]
Download as PDF
Federal Register / Vol. 86, No. 17 / Thursday, January 28, 2021 / Notices
Accession Number: 20210121–5290.
Comments Due: 5 p.m. ET 2/11/21.
Docket Numbers: ER21–930–000.
Applicants: American Transmission
Systems, Incorporated, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
ATSI submits ECSAs, SA Nos. 5913,
5914, and 5915 to be effective 3/24/
2021.
Filed Date: 1/22/21.
Accession Number: 20210122–5034.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER21–931–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing: SA
905—Agreement to Provide Services
with GCC Three Forks LLC to be
effective 1/25/2021.
Filed Date: 1/22/21.
Accession Number: 20210122–5072.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER21–932–000.
Applicants: Louisville Gas & Electric
Company.
Description: Notice of Termination of
a Transmission Lease Agreement of
Louisville Gas and Electric Company.
Filed Date: 1/22/21.
Accession Number: 20210122–5079.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER21–933–000.
Applicants: Peetz Table Wind Energy,
LLC.
Description: Tariff Cancellation: Peetz
Table Wind Energy, LLC Cancellation of
MBR Tariff to be effective 1/23/2021.
Filed Date: 1/22/21.
Accession Number: 20210122–5119.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER21–934–000.
Applicants: Northern Colorado Wind
Energy, LLC.
Description: Tariff Cancellation:
Northern Colorado Wind Energy, LLC
Cancellation of MBR Tariff to be
effective 1/23/2021.
Filed Date: 1/22/21.
Accession Number: 20210122–5121.
Comments Due: 5 p.m. ET 2/12/21.
Docket Numbers: ER21–935–000.
Applicants: Crowned Ridge
Interconnection, LLC.
Description: Tariff Cancellation:
Crowned Ridge Interconnection, LLC, to
be effective 1/23/2021.
Filed Date: 1/22/21.
Accession Number: 20210122–5126.
Comments Due: 5 p.m. ET 2/12/21.
Take notice that the Commission
received the following public utility
holding company filings:
Docket Numbers: PH21–7–000.
Applicants: BlackRock, Inc.
Description: BlackRock, Inc. submits
FERC–65–A Notice of Change in Fact to
Exemption Notification.
VerDate Sep<11>2014
17:16 Jan 27, 2021
Jkt 253001
Filed Date: 1/21/21.
Accession Number: 20210121–5318.
Comments Due: 5 p.m. ET 2/11/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at:
https://www.ferc.gov/docs-filing/
efiling/filing-req.pdf. For other
information, call (866) 208–3676 (toll
free). For TTY, call (202) 502–8659.
Dated: January 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–01870 Filed 1–27–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–27–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Request
Under Blanket Authorization and
Establishing Intervention and Protest
Deadline
Take notice that on January 12, 2021,
Transcontinental Gas Pipe Line
Company, LLC (Transco), Post Office
Box 1396, Houston, Texas 77251–1396,
filed in the above referenced docket, a
prior notice request pursuant to sections
157.205 and 157.216 of the
Commission’s regulations under the
Natural Gas Act (NGA) and Transco’s
blanket certificate issued in Docket No.
CP82–426–000, for authorization to
abandon approximately 6.57 miles of
pipeline that consists of an 8-inchdiameter supply lateral and
approximately 6.56 miles of pipeline
that consists of three 16-inch-diameter
supply laterals extending from Ship
Shoal Block 233, Platform B to Ship
Shoal Block 214, Platform C and
appurtenant metering facilities (Supply
Laterals), all in Federal offshore waters,
offshore Louisiana, all as more fully set
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
7379
forth in the application which is on file
with the Commission and open to
public inspection.
Transco states that the abandonment
of the Supply Laterals will have no
impact on the daily design capacity or
operating conditions of Transco’s
system, nor will the abandonment have
any adverse impact on Transco’s
existing customers. Additionally,
Transco states that the Supply Laterals
have not provided service to any
customers for the last 12 months. The
estimated cost of the abandonment is
$3,182,902.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this prior
notice request should be directed to
Jordan Kirwin, Director, Rates &
Regulatory, Transcontinental Gas Pipe
Line Company, LLC, P.O. Box 1396,
Houston, Texas 77251 at (713) 215–3723
or by email at Jordan.Kirwin@
Williams.com.
Public Participation
There are three ways to become
involved in the Commission’s review of
this project: You can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5:00 p.m.
Eastern Time on March 23, 2021. How
to file protests, motions to intervene,
and comments is explained below.
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
E:\FR\FM\28JAN1.SGM
28JAN1
7380
Federal Register / Vol. 86, No. 17 / Thursday, January 28, 2021 / Notices
NGA,1 any person 2 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,3 and must be submitted by
the protest deadline, which is March 23,
2021. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 4 and the regulations under
the NGA 5 by the intervention deadline
for the project, which is March 23, 2021.
As described further in Rule 214, your
motion to intervene must state, to the
extent known, your position regarding
the proceeding, as well as your interest
in the proceeding. For an individual,
this could include your status as a
landowner, ratepayer, resident of an
impacted community, or recreationist.
You do not need to have property
directly impacted by the project in order
to intervene. For more information
about motions to intervene, refer to the
FERC website at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
1 18
CFR 157.205.
include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
3 18 CFR 157.205(e).
4 18 CFR 385.214.
5 18 CFR 157.10.
2 Persons
VerDate Sep<11>2014
17:16 Jan 27, 2021
Jkt 253001
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before March 23,
2021. The filing of a comment alone will
not serve to make the filer a party to the
proceeding. To become a party, you
must intervene in the proceeding.
How To File Protests, Interventions, and
Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP21–27–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing’’; or 6
(2) You can file a paper copy of your
submission by mailing it to the address
below.7 Your submission must reference
the Project docket number CP21–27–
000.
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC
20426
The Commission encourages
electronic filing of submissions (option
1 above) and has eFiling staff available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
6 Additionally, you may file your comments
electronically by using the eComment feature,
which is located on the Commission’s website at
www.ferc.gov under the link to Documents and
Filings. Using eComment is an easy method for
interested persons to submit brief, text-only
comments on a project.
7 Hand-delivered submissions in docketed
proceedings should be delivered to Health and
Human Services, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
Protests and motions to intervene
must be served on the applicant either
by mail at: P.O. Box 1396, Houston,
Texas 77251 at (713) 215–3723 or email
(with a link to the document) at:
Jordan.Kirwin@Williams.com. Any
subsequent submissions by an
intervenor must be served on the
applicant and all other parties to the
proceeding. Contact information for
parties can be downloaded from the
service list at the eService link on FERC
Online.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Dated: January 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–01872 Filed 1–27–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–26–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Request
Under Blanket Authorization and
Establishing Intervention and Protest
Deadline
Take notice that on January 12, 2021,
Transcontinental Gas Pipe Line
Company, LLC (Transco), P.O. Box
1396, Houston, TX 77251, filed in the
above referenced docket a prior notice
pursuant to Section 157.205 and
157.216 of the Federal Energy
Regulatory Commission’s regulations
under the Natural Gas Act, requesting
authorization to abandon an existing 6inch supply lateral extending from
E:\FR\FM\28JAN1.SGM
28JAN1
Agencies
[Federal Register Volume 86, Number 17 (Thursday, January 28, 2021)]
[Notices]
[Pages 7379-7380]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-01872]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-27-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Request
Under Blanket Authorization and Establishing Intervention and Protest
Deadline
Take notice that on January 12, 2021, Transcontinental Gas Pipe
Line Company, LLC (Transco), Post Office Box 1396, Houston, Texas
77251-1396, filed in the above referenced docket, a prior notice
request pursuant to sections 157.205 and 157.216 of the Commission's
regulations under the Natural Gas Act (NGA) and Transco's blanket
certificate issued in Docket No. CP82-426-000, for authorization to
abandon approximately 6.57 miles of pipeline that consists of an 8-
inch-diameter supply lateral and approximately 6.56 miles of pipeline
that consists of three 16-inch-diameter supply laterals extending from
Ship Shoal Block 233, Platform B to Ship Shoal Block 214, Platform C
and appurtenant metering facilities (Supply Laterals), all in Federal
offshore waters, offshore Louisiana, all as more fully set forth in the
application which is on file with the Commission and open to public
inspection.
Transco states that the abandonment of the Supply Laterals will
have no impact on the daily design capacity or operating conditions of
Transco's system, nor will the abandonment have any adverse impact on
Transco's existing customers. Additionally, Transco states that the
Supply Laterals have not provided service to any customers for the last
12 months. The estimated cost of the abandonment is $3,182,902.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions regarding this prior notice request should be
directed to Jordan Kirwin, Director, Rates & Regulatory,
Transcontinental Gas Pipe Line Company, LLC, P.O. Box 1396, Houston,
Texas 77251 at (713) 215-3723 or by email at
[email protected].
Public Participation
There are three ways to become involved in the Commission's review
of this project: You can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on March 23, 2021.
How to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the
[[Page 7380]]
NGA,\1\ any person \2\ or the Commission's staff may file a protest to
the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\1\ 18 CFR 157.205.
\2\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\3\ and must be submitted by
the protest deadline, which is March 23, 2021. A protest may also serve
as a motion to intervene so long as the protestor states it also seeks
to be an intervenor.
---------------------------------------------------------------------------
\3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is March 23, 2021. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before March 23, 2021. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP21-27-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (www.ferc.gov) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------
\6\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at www.ferc.gov under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below.\7\ Your submission must reference the Project docket
number CP21-27-000.
---------------------------------------------------------------------------
\7\ Hand-delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected]
Protests and motions to intervene must be served on the applicant
either by mail at: P.O. Box 1396, Houston, Texas 77251 at (713) 215-
3723 or email (with a link to the document) at:
[email protected]. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: January 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-01872 Filed 1-27-21; 8:45 am]
BILLING CODE 6717-01-P