o. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Commission issues letters identifying application deficiencies and requesting additional information ...........................................
Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..............................................................
Reply Comments due .......................................................................................................................................................................
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: December 16, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–28247 Filed 12–21–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER21–653–000]
jbell on DSKJLSW7X2PROD with NOTICES
Centerfield Cooper Solar, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of
Centerfield Cooper Solar, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is January 5,
2021.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
VerDate Sep<11>2014
17:30 Dec 21, 2020
Jkt 253001
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
may mail similar pleadings to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426. Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Dated: December 16, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–28241 Filed 12–21–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Number: CP21–16–000.
PO 00000
Frm 00036
Fmt 4703
83545
Sfmt 4703
January 2021.
May 2021.
July 2021.
August 2021.
Applicants: Midcontinent Express
Pipeline LLC.
Description: Joint Abbreviated
Application of Midcontinent Express
Pipeline LLC et al for Partial Lease
Capacity Abandonment Authorization.
Filed Date: 12/10/20.
Accession Number: 202012105111.
Comments Due: 5 p.m. ET 1/4/21.
Docket Number: PR21–8–000.
Applicants: Interstate Power and
Light Company.
Description: § 284.123 Rate Filing:
2020 Fuel Reimbursement Mechansim
Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155048.
Comments Due: 5 p.m. ET 1/5/21.
Docket Number: PR21–9–000.
Applicants: Jefferson Island Storage &
Hub, L.L.C.
Description: § 284.123 Rate Filing:
2020 Fuel Reimbursement Mechansim
Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155063.
Comments Due: 5 p.m. ET 1/5/21.
Docket Number: PR21–10–000.
Applicants: Valley Crossing Pipeline,
LLC.
Description: § 284.123 Rate Filing:
2020 Fuel Reimbursement Mechansim
Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155075.
Comments Due: 5 p.m. ET 1/5/21.
Docket Numbers: RP21–232–001.
Applicants: Cheniere Corpus Christi
Pipeline, LP.
Description: Compliance filing CCPL
Stage 3 Supplemental Compliance
Filing CP18–513 to be effective 2/1/
2021.
Filed Date: 12/15/20.
Accession Number: 20201215–5078.
Comments Due: 5 p.m. ET 12/28/20.
Docket Numbers: RP21–309–000.
Applicants: Portland Natural Gas
Transmission System.
Description: Compliance filing 2020
Fuel Reimbursement Mechansim Report
to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 20201215–5035.
Comments Due: 5 p.m. ET 12/28/20.
The filings are accessible in the
Commission’s eLibrary system (https://
E:\FR\FM\22DEN1.SGM
22DEN1
83546
Federal Register / Vol. 85, No. 246 / Tuesday, December 22, 2020 / Notices
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 16, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–28236 Filed 12–21–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1904–078]
jbell on DSKJLSW7X2PROD with NOTICES
Great River Hydro, LLC; Notice
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
amended hydroelectric application has
been filed with the Commission and is
available for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 1904–078.
c. Date Material Amendments Filed:
December 7, 2020.
d. Applicant: Great River Hydro, LLC
(Great River Hydro).
e. Name of Project: Vernon
Hydroelectric Project.
f. Location: The existing project is
located on the Connecticut River in
Windham County, Vermont, and
Cheshire County, New Hampshire.
There are no federal lands within the
project boundary.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: John Ragonese,
FERC License Manager, Great River
Hydro, LLC, 40 Pleasant Street, Suite
202, Portsmouth, NH 03801; (603) 498–
2851 or jragonese@greatriverhydro.com.
i. FERC Contact: Steve Kartalia, (202)
502–6131 or stephen.kartalia@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Great River Hydro filed an
application for a new license for the
Vernon Hydroelectric Project No. 1904
on May 1, 2017. In the license
application, Great River Hydro stated
that it could not develop a complete
licensing proposal for the project since
many of the required environmental
studies were not complete as of May 1,
2017. Great River Hydro indicated that
it would amend the license application
after completing additional field work,
consultation, and analyses on the
required studies. Great River Hydro
filed material amendments to the final
license application on December 7,
2020.
l. Project Description: The existing
Vernon Project consists of: (1) A 956foot-long, 58-foot-high concrete dam
that includes: (a) 356-foot-long section
integral to the powerhouse; and (b) a
600-foot-long overflow spillway section
that includes: (i) A 9-foot-high, 6-footwide downstream fishway sluice; (ii) a
13-foot-high, 13-foot-wide trash/ice
sluice; (iii) two 20-foot-high, 50-footwide tainter gates; (iv) four 10-foot-high,
50-foot-wide tainter gates; (v) two 10foot-high, 50-foot-wide hydraulic panel
bays; (vi) two 10-foot-high, 50-foot-wide
stanchion bays; (vii) a 10-foot-high,
42.5-foot-wide stanchion bay; and (viii)
eight 7-foot-high, 9-foot-wide hydraulic
flood gates; (2) a 26-mile-long, 2,550acre impoundment with a useable
storage volume of 18,300 acre-feet
between elevations 212.13 and 220.13
feet National Geodetic Vertical Datum of
1929 (NGVD 29); (3) eight
approximately 30-foot-high trashracks
with 1.75-inch clear bar spacing and
two approximately 30-foot-high
trashracks with 3.625-inch clear bar
spacing; (4) a 356-foot-long, 55-footwide, 45-foot-high reinforced concrete,
steel, and brick powerhouse containing
four 2-megawatt (MW) vertical Francis
turbine-generator units, four 4–MW
vertical Kaplan turbine-generator units,
and two 4.2–MW vertical Francis
turbine-generator units, for a total
project capacity of 32.4 MW; (5) ten
concrete draft tubes ranging from 16 to
27 feet in diameter; (6) a 500-foot-long,
13.8-kilovolt underground generator
lead that connects the turbine-generator
units to two step-up transformers; (7) a
984-foot-long, 15-foot-wide upstream
fishway; and (8) appurtenant facilities.
Great River Hydro operates the project
in coordination with its upstream
Wilder Project No. 1892 and Bellows
Falls Project No. 1855 and in a peaking
mode. Average annual generation is
approximately 158,028 MW-hours.
Great River Hydro is proposing changes
to project operation that would reduce
impoundment fluctuations and increase
the stability of downstream flow
releases relative to current project
operation, including targeted water
surface elevation levels and flow
ramping rates. Great River Hydro
proposes several protection, mitigation,
and enhancement measures for aquatic,
terrestrial, cultural, and recreation
resources, and threatened and
endangered species. The specific
proposed changes are described in the
amended application.
m. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–1904).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
n. You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Commission issues letter identifying application deficiencies and requesting additional information .............................................
Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..............................................................
VerDate Sep<11>2014
17:30 Dec 21, 2020
Jkt 253001
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
E:\FR\FM\22DEN1.SGM
22DEN1
January 2021.
May 2021.
July 2021.
Agencies
[Federal Register Volume 85, Number 246 (Tuesday, December 22, 2020)]
[Notices]
[Pages 83545-83546]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-28236]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Docket Number: CP21-16-000.
Applicants: Midcontinent Express Pipeline LLC.
Description: Joint Abbreviated Application of Midcontinent Express
Pipeline LLC et al for Partial Lease Capacity Abandonment
Authorization.
Filed Date: 12/10/20.
Accession Number: 202012105111.
Comments Due: 5 p.m. ET 1/4/21.
Docket Number: PR21-8-000.
Applicants: Interstate Power and Light Company.
Description: Sec. 284.123 Rate Filing: 2020 Fuel Reimbursement
Mechansim Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155048.
Comments Due: 5 p.m. ET 1/5/21.
Docket Number: PR21-9-000.
Applicants: Jefferson Island Storage & Hub, L.L.C.
Description: Sec. 284.123 Rate Filing: 2020 Fuel Reimbursement
Mechansim Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155063.
Comments Due: 5 p.m. ET 1/5/21.
Docket Number: PR21-10-000.
Applicants: Valley Crossing Pipeline, LLC.
Description: Sec. 284.123 Rate Filing: 2020 Fuel Reimbursement
Mechansim Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 202012155075.
Comments Due: 5 p.m. ET 1/5/21.
Docket Numbers: RP21-232-001.
Applicants: Cheniere Corpus Christi Pipeline, LP.
Description: Compliance filing CCPL Stage 3 Supplemental Compliance
Filing CP18-513 to be effective 2/1/2021.
Filed Date: 12/15/20.
Accession Number: 20201215-5078.
Comments Due: 5 p.m. ET 12/28/20.
Docket Numbers: RP21-309-000.
Applicants: Portland Natural Gas Transmission System.
Description: Compliance filing 2020 Fuel Reimbursement Mechansim
Report to be effective N/A.
Filed Date: 12/15/20.
Accession Number: 20201215-5035.
Comments Due: 5 p.m. ET 12/28/20.
The filings are accessible in the Commission's eLibrary system
(https://
[[Page 83546]]
elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: December 16, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-28236 Filed 12-21-20; 8:45 am]
BILLING CODE 6717-01-P