Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES 82470 Federal Register / Vol. 85, No. 244 / Friday, December 18, 2020 / Notices Docket Numbers: ER12–162–030; ER10–2984–050; ER11–2044–036 ER13– 1266–033; ER15–2211–030. Applicants: Bishop Hill Energy II LLC, CalEnergy, LLC, Merrill Lynch Commodities, Inc., MidAmerican Energy Company, MidAmerican Energy Services, LLC. Description: Central Region Triennial Market Power Analysis of Bishop Hill Energy II LLC, et al. Filed Date: 12/11/20. Accession Number: 20201211–5205. Comments Due: 5 p.m. ET 2/9/21. Docket Numbers: ER21–635–000. Applicants: Portland General Electric Company. Description: § 205(d) Rate Filing: PGE–BPA E&P Agreement to be effective 12/14/2020. Filed Date: 12/11/20. Accession Number: 20201211–5169. Comments Due: 5 p.m. ET 1/4/21. Docket Numbers: ER21–636–000. Applicants: American Electric Power Service Corporation, Ohio Power Company, AEP Ohio Transmission Company, Inc., PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: AEP submits Arlington FA re: ILDSA SA No. 1336 to be effective 2/10/2021. Filed Date: 12/11/20. Accession Number: 20201211–5178. Comments Due: 5 p.m. ET 1/4/21. Docket Numbers: ER21–637–000. Applicants: Foxglove Wind LLC, Moonlite Wind 2 LLC. Description: Request for Limited Waiver of Tariff Provisions, et al. of Foxglove Wind LLC, et al. Filed Date: 12/11/20. Accession Number: 20201211–5203. Comments Due: 5 p.m. ET 12/21/21. Docket Numbers: ER21–638–000. Applicants: RWE Renewables Americas, LLC. Description: Request for COVID–19 Related Waiver of Tariff Provisions, et al. of RWE Renewables Americas, LLC. Filed Date: 12/11/20. Accession Number: 20201211–5204. Comments Due: 5 p.m. ET 12/21/21. Docket Numbers: ER21–639–000. Applicants: Wapello Solar LLC. Description: Baseline eTariff Filing: Application for Market Based Rate Authority to be effective 12/17/2020. Filed Date: 12/14/20. Accession Number: 20201214–5056. Comments Due: 5 p.m. ET 1/4/21. Docket Numbers: ER21–640–000. Applicants: ISO New England Inc., New England Power Pool Participants Committee. Description: § 205(d) Rate Filing: ISO– NE & NEPOOL; Changes to Qualification VerDate Sep<11>2014 22:22 Dec 17, 2020 Jkt 253001 of Energy Eff. Resources in the FCM to be effective 2/12/2021. Filed Date: 12/14/20. Accession Number: 20201214–5107. Comments Due: 5 p.m. ET 1/4/21. DEPARTMENT OF ENERGY Docket Numbers: ER21–641–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of ISA, SA No. 4519, Queue No. AA2–159 re: Withdrawal to be effective 1/15/2021. Filed Date: 12/14/20. Accession Number: 20201214–5114. Comments Due: 5 p.m. ET 1/4/21. Marlow Hydro, LLC; Notice of Application Tendered for Filing With the Commission, Soliciting Additional Study Requests, Establishing Procedural Schedule for Relicensing, and Setting Deadline for Submission of Final Amendments Docket Numbers: ER21–643–000. Applicants: Louisville Gas and Electric Company. Description: § 205(d) Rate Filing: KYMEA Amended Wholesale Distribution Service Agreement No. 22 to be effective 12/15/2020. Filed Date: 12/14/20. Accession Number: 20201214–5133. Comments Due: 5 p.m. ET 1/4/21. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: December 14, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–27935 Filed 12–17–20; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission [Project No. 3309–021] Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 3309–021. c. Date filed: December 1, 2020. d. Applicant: Marlow Hydro, LLC (Marlow Hydro). e. Name of Project: Nash Mill Dam Project. f. Location: On the Ashuelot River, in the town of Marlow, Cheshire County, New Hampshire. The project does not occupy federal land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Anthony Rosario and Carole Rosario, 139 Henniker St., Hillsborough, New Hampshire 03244, (603) 494–1854, (603) 494–3897, or email at t-iem@tds.net or cprabr@tds.net. i. FERC Contact: Adam Peer at (202) 502–8449, or email adam.peer@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. E:\FR\FM\18DEN1.SGM 18DEN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 85, No. 244 / Friday, December 18, 2020 / Notices l. Deadline for filing additional study requests and requests for cooperating agency status: January 30, 2021. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–3309–021. m. The application is not ready for environmental analysis at this time. n. Marlow Hydro electronically filed the final license application cover letter and exhibit G drawings with the Commission on November 30, 2020 at 6:39 p.m. and the license application on December 1, 2020 at 10:03 a.m. Pursuant to 18 CFR 385.2001(a)(2), any document received after 5:00 p.m. eastern time is considered filed on the next regular business day. By this notice, the requirement under 18 CFR 16.20(c) to file the subsequent license application at least 24 months before the expiration of the current license (i.e., no later than November 30, 2020 at 5:00 p.m.) is waived. o. Project Description: The existing Nash Mill Dam Project utilizes water from the 2-acre impoundment and consists of: (1) A 249-foot-long dam consisting of: (i) A 57-foot-long, 9 foothigh concrete gravity spillway topped with 3-foot-high wooden flashboards, (ii) a 12-foot-long concrete intake section, and (iii) two, 12-foot-high earthen dam sections totaling 180 feet in length; (2) an intake structure with a 10foot-high, 10-foot-wide trash rack; (3) a 1,500 foot-long, 48-inch diameter steel penstock; (4) a 31-foot-long, 18-footwide powerhouse located on the north side of the Ashuelot River that contains two vertical-shaft, fixed propeller turbine-generator units and one horizontal-shaft turbine-generator unit for a total installed capacity of 225 kilowatts; (5) a 600-foot-long tailrace; (6) a 1,800-foot-long bypassed reach; (7) a 1,400 foot-long transmission line and a 12.5-kilovolt transformer; and (8) VerDate Sep<11>2014 22:22 Dec 17, 2020 Jkt 253001 appurtenant facilities. The average annual generation was 558,923 kilowatthours for the period from 2009 to 2018. Marlow Hydro currently operates the project in run-of-river mode and releases a minimum flow of 5 cubic feet per second (cfs) into the bypassed reach. Marlow Hydro proposes to continue to operate in run-of-river mode and to increase the minimum flow released into the bypassed reach to 12 cfs. p. In addition to publishing the full text of this notice in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this notice, as well as other documents in the proceeding (e.g., license application) via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–3309). At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19) issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. q. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary) February 2021 Request Additional Information February 2021 Issue Notice of Acceptance May 2021 Issue Scoping Document 1 for comments June 2021 Request Additional Information (if necessary) September 2021 Issue Scoping Document 2 September 2021 Issue Notice of Ready for Environmental Analysis September 2021 r. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 82471 Dated: December 14, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–27930 Filed 12–17–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER21–639–000] Wapello Solar LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced Wapello Solar LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is January 4, 2021. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all E:\FR\FM\18DEN1.SGM 18DEN1

Agencies

[Federal Register Volume 85, Number 244 (Friday, December 18, 2020)]
[Notices]
[Pages 82470-82471]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-27930]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3309-021]


Marlow Hydro, LLC; Notice of Application Tendered for Filing With 
the Commission, Soliciting Additional Study Requests, Establishing 
Procedural Schedule for Relicensing, and Setting Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 3309-021.
    c. Date filed: December 1, 2020.
    d. Applicant: Marlow Hydro, LLC (Marlow Hydro).
    e. Name of Project: Nash Mill Dam Project.
    f. Location: On the Ashuelot River, in the town of Marlow, Cheshire 
County, New Hampshire. The project does not occupy federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Anthony Rosario and Carole Rosario, 139 
Henniker St., Hillsborough, New Hampshire 03244, (603) 494-1854, (603) 
494-3897, or email at [email protected] or [email protected].
    i. FERC Contact: Adam Peer at (202) 502-8449, or email 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.

[[Page 82471]]

    l. Deadline for filing additional study requests and requests for 
cooperating agency status: January 30, 2021.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. The first page of any filing should include docket 
number P-3309-021.
    m. The application is not ready for environmental analysis at this 
time.
    n. Marlow Hydro electronically filed the final license application 
cover letter and exhibit G drawings with the Commission on November 30, 
2020 at 6:39 p.m. and the license application on December 1, 2020 at 
10:03 a.m. Pursuant to 18 CFR 385.2001(a)(2), any document received 
after 5:00 p.m. eastern time is considered filed on the next regular 
business day. By this notice, the requirement under 18 CFR 16.20(c) to 
file the subsequent license application at least 24 months before the 
expiration of the current license (i.e., no later than November 30, 
2020 at 5:00 p.m.) is waived.
    o. Project Description: The existing Nash Mill Dam Project utilizes 
water from the 2-acre impoundment and consists of: (1) A 249-foot-long 
dam consisting of: (i) A 57-foot-long, 9 foot-high concrete gravity 
spillway topped with 3-foot-high wooden flashboards, (ii) a 12-foot-
long concrete intake section, and (iii) two, 12-foot-high earthen dam 
sections totaling 180 feet in length; (2) an intake structure with a 
10-foot-high, 10-foot-wide trash rack; (3) a 1,500 foot-long, 48-inch 
diameter steel penstock; (4) a 31-foot-long, 18-foot-wide powerhouse 
located on the north side of the Ashuelot River that contains two 
vertical-shaft, fixed propeller turbine-generator units and one 
horizontal-shaft turbine-generator unit for a total installed capacity 
of 225 kilowatts; (5) a 600-foot-long tailrace; (6) a 1,800-foot-long 
bypassed reach; (7) a 1,400 foot-long transmission line and a 12.5-
kilovolt transformer; and (8) appurtenant facilities. The average 
annual generation was 558,923 kilowatt-hours for the period from 2009 
to 2018.
    Marlow Hydro currently operates the project in run-of-river mode 
and releases a minimum flow of 5 cubic feet per second (cfs) into the 
bypassed reach.
    Marlow Hydro proposes to continue to operate in run-of-river mode 
and to increase the minimum flow released into the bypassed reach to 12 
cfs.
    p. In addition to publishing the full text of this notice in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this notice, as well 
as other documents in the proceeding (e.g., license application) via 
the internet through the Commission's Home Page (https://www.ferc.gov) 
using the eLibrary link. Enter the docket number excluding the last 
three digits in the docket number field to access the document (P-
3309). At this time, the Commission has suspended access to the 
Commission's Public Reference Room due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19) 
issued by the President on March 13, 2020. For assistance, contact FERC 
at [email protected] or call toll-free, (866) 208-3676 or 
(202) 502-8659 (TTY).
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    q. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

Issue Deficiency Letter (if necessary) February 2021
Request Additional Information February 2021
Issue Notice of Acceptance May 2021
Issue Scoping Document 1 for comments June 2021
Request Additional Information (if necessary) September 2021
Issue Scoping Document 2 September 2021
Issue Notice of Ready for Environmental Analysis September 2021

    r. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: December 14, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-27930 Filed 12-17-20; 8:45 am]
BILLING CODE 6717-01-P