Green Mountain Power Corporation; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions, 78847-78849 [2020-26821]
Download as PDF
Federal Register / Vol. 85, No. 235 / Monday, December 7, 2020 / Notices
proposed to the ERO by a Regional
Entity.4 A Regional Entity is an entity
that has been approved by the
Commission to enforce Reliability
Standards under delegated authority
from the ERO.5 On March 17, 2011, the
Commission approved a regional
Reliability Standard submitted by the
ERO that was developed by the
ReliabilityFirst Corporation (RF).6
RF promotes bulk electric system
reliability in the Eastern
Interconnection. RF is the Regional
Entity responsible for compliance
monitoring and enforcement in the RF
region. In addition, RF provides an
environment for the development of
Commission’s compliance with section
215 of the Federal Power Act (FPA) (16
U.S.C. 824o), which enables the
Commission to strengthen the reliability
of the bulk-power system.1 The
Commission’s implementation of FPA
section 215 involves review and
approval of a system of mandatory
Reliability Standards that are
established and enforced by an Electric
Reliability Organization (ERO).2 The
Commission has certified the North
American Electric Reliability
Corporation (NERC) as the ERO.3
Reliability Standards that the ERO
proposes to the Commission may
include Reliability Standards that are
78847
Reliability Standards and the
coordination of the operating and
planning activities of its members as set
forth in the RF bylaws.
There is one regional Reliability
Standard in the RF region. The
Commission requests renewal of OMB
clearance for that regional Reliability
Standard, known as BAL–502–RF–03
(Planning Resource Adequacy Analysis,
Assessment and Documentation).
Type of Respondents: Planning
coordinators.
Estimate of Annual Burden 7: The
estimated burden and cost 8 are as
follows:
FERC–725HH, RF RELIABILITY STANDARDS
Entity
Number of
respondents 9
Annual
number of
responses
per
respondent
Annual
number of
responses
Average burden hours
and cost per response ($)
Total annual burden hours
and total annual cost ($)
Cost per
respondent ($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1) = (6)
Proposed Regional Reliability Standard BAL–502–RF–03
Planning Coordinators .........................
2
2
16 hrs.; $1,243.52 ............
32 hrs.; $2487.04 .............
$1,243.52
BILLING CODE 6717–01–P
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2879–012.
c. Date Filed: January 30, 2020.
d. Applicant: Green Mountain Power
Corporation (GMP).
e. Name of Project: Bolton Falls
Hydroelectric Project.
f. Location: The existing project is
located on the Winooski River in
Washington County, Vermont. The
project does not affect federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)—825(r).
h. Applicant Contact: Mr. John
Greenan, P.E., Engineer, Green
Mountain Power Corporation, 1252 Post
Road, Rutland, Vermont 05701; phone:
(802) 770–2195 or email at
John.Greenan@
greenmountainpower.com.
i. FERC Contact: Michael Tust at (202)
502–6522; or email at michael.tust@
ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
1 FPA section 251(a)(1) defines bulk-power
system as follows: (A) facilities and control systems
necessary for operating an interconnected electric
energy transmission network (or any portion
thereof); and (B) electric energy from generation
facilities needed to maintain transmission system
reliability. The term does not include facilities used
in the local distribution of electric energy.
2 FPA section 215(a)(2) defines ‘‘Electric
Reliability Organization’’ as ‘‘the organization
certified by the Commission under subsection (c)
the purpose of which is to establish and enforce
reliability standards for the bulk-power system,
subject to Commission review.’’
3 North American Electric Reliability Corp., 116
FERC 61,062 (ERO Certification Order), order on
reh’g & compliance, 117 FERC 61,126 (2006), aff’d
sub nom. Alcoa, Inc. v. FERC, 564 F.3d 1342 (DC
Cir. 2009).
4 16 U.S.C. 824o(e)(4).
5 16 U.S.C. 824o(a)(7) and (e)(4).
6 Planning Resource Adequacy Assessment
Reliability Standard, Order No. 747, 134 FERC
61,212 (2011).
7 Burden is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a Federal agency. For further
explanation of what is included in the information
collection burden, refer to 5 CFR 1320.3.
8 For BAL–502–RF–03, the hourly cost (for salary
plus benefits) uses the figures from the Bureau of
Labor Statistics for three positions involved in the
reporting and recordkeeping requirements. These
figures include salary (https://www.bls.gov/oes/
current/oes_nat.htm) and benefits (https://
www.bls.gov/news.release/ecec.nr0.htm) and are:
• Manager (Occupation Code 11–0000): $94.84/
hour
• Engineer (Occupation Code 17–2071): $85.71/
hour
• File Clerk (Occupation Code 43–4071): $52.60/
hour
The hourly cost for the reporting requirements
($77.72) is an average of the cost of a manager, an
engineer, and a file clerk.
9 The number of respondents is derived from the
NERC Compliance Registry as of October 2, 2020 for
the burden associated with the proposed regional
Reliability Standard BAL–502–RF–03.
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: December 1, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26823 Filed 12–4–20; 8:45 am]
khammond on DSKJM1Z7X2PROD with NOTICES
1
VerDate Sep<11>2014
18:32 Dec 04, 2020
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2879–012]
Green Mountain Power Corporation;
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
E:\FR\FM\07DEN1.SGM
07DEN1
khammond on DSKJM1Z7X2PROD with NOTICES
78848
Federal Register / Vol. 85, No. 235 / Monday, December 7, 2020 / Notices
prescriptions: 60 days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
fishway prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
The Council on Environmental
Quality (CEQ) issued a final rule on July
15, 2020, revising the regulations under
40 CFR parts 1500–1518 that federal
agencies use to implement NEPA (see
Update to the Regulations Implementing
the Procedural Provisions of the
National Environmental Policy Act, 85
FR 43,304). The Final Rule became
effective on and applies to any NEPA
process begun after September 14, 2020.
An agency may also apply the
regulations to ongoing activities and
environmental documents begun before
September 14, 2020, which includes the
proposed Bolton Falls Project
relicensing. Commission staff intends to
conduct its NEPA review in accordance
with CEQ’s new regulations.
VerDate Sep<11>2014
18:32 Dec 04, 2020
Jkt 253001
l. The Bolton Falls Project consists of
the following constructed facilities: (1) A
92-foot-high, 275-foot-wide timber crib
dam with a 5-foot-high rubber dam atop
the timber crib construction with a
maximum crest elevation of 397 feet and
a 196-foot-long reinforced concrete
spillway cap at a crest elevation of 392
feet; (2) a 59-acre impoundment with a
total storage capacity of 300 acre-feet at
a normal operating elevation of 397 feet;
(3) a forebay with two concrete intakes,
each with a 3-inch-spaced trashrack; (4)
two 10-foot diameter, 120-foot-long steel
penstocks; (5) a 73-foot-long, 57-footwide powerhouse containing two
horizontal, 3,750-kilowatt Kaplan
turbines with a total installed capacity
of 7,500 kilowatts; (6) a 36-inch
diameter steel bypass pipe with an
invert elevation of 383 feet that
discharges near the left side of the
spillway base; (7) an approximately 130foot long, 5-kilovolt underground
transmission line connecting to an
adjacent switchyard; (8) a 600-foot-long,
34.5-kilovolt overhead transmission line
connecting to a second switchyard; and
(9) appurtenant facilities. GMP also
maintains day-use recreation facilities at
the project, including a picnic area,
trails, fishing access, and a canoe launch
and portage trail.
GMP proposes to operate in
automated run-of-river mode as it does
under its current practice but instead of
providing a 300-cubic feet per second
(cfs) minimum flow into the Winooski
River through the powerhouse (when
generating) or via spill over the dam
(when not generating) as it does now,
GMP proposes to provide a seasonal
aesthetic spill flow of 75 cfs or inflow,
whichever is less, into the bypassed
reach via spillage over the dam during
daylight hours from April 1 through
December 15. At all other times,
bypassed reach flows would be reduced
to leakage except when inflow drops
below the minimum hydraulic capacity
(i.e., 365 cfs) or when inflow exceeds
the maximum hydraulic capacity (2,400
cfs) of the generating units in which
case additional flows would be released
to the bypassed reach via spill over the
dam. Under normal flow conditions
when aesthetic spillage is required,
GMP proposes to maintain the
impoundment at an elevation of 397.25
feet. When aesthetic spillage over the
dam is not required, GMP proposes to
maintain the reservoir at an elevation of
397 feet as it does now. GMP also
proposes to: (1) Relocate recreation
parking area out of the floodplain; (2)
implement measures to protect creeping
lovegrass at the day-use area; (3) add
two picnic tables and an information
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
kiosk to the day-use area; and (4)
improve the portage landing, trail, and
signage.
m. A copy of the application can
viewed on the Commission’s website at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support.
Register online at https://
ferconline.ferc.gov/FERCOnline.aspx to
be notified via email of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title PROTEST, MOTION TO
INTERVENE, COMMENTS, REPLY
COMMENTS, RECOMMENDATIONS,
PRELIMINARY TERMS AND
CONDITIONS, or PRELIMINARY
FISHWAY PRESCRIPTIONS; (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Final amendments to the
application must be filed with the
Commission no later than thirty (30)
days from the issuance date of this
notice.
E:\FR\FM\07DEN1.SGM
07DEN1
Federal Register / Vol. 85, No. 235 / Monday, December 7, 2020 / Notices
p. The applicant must file no later
than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification. Please note that the
certification request must be sent to the
certifying authority and to the
Commission concurrently.
q. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Target date
Deadline for Filing Comments, Recommendations,
and Agency Terms and
Conditions/Prescriptions.
Deadline for Filing Reply
Comments.
January 2021.
March 2021.
Dated: December 1, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26821 Filed 12–4–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–527–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Columbia Gulf Transmission, LLC;
Notice of Schedule for the Preparation
of an Environmental Assessment for
the East Lateral Xpress Project
On September 24, 2020, Columbia
Gulf Transmission, LLC (Columbia Gulf)
filed an application in Docket No.
CP20–527–000 requesting a Certificate
of Public Convenience and Necessity
pursuant to Section 7(c) of the Natural
Gas Act to construct and operate certain
natural gas pipeline facilities in
Louisiana. The proposed project is
known as the East Lateral XPress Project
(Project), and would provide a total of
725 million standard cubic feet per day
of firm transportation capacity, on
Columbia Gulf’s interstate natural gas
pipeline system, to supply feed gas for
Venture Global LNG’s Plaquemines LNG
facility in Plaquemines Parish,
Louisiana.
On October 8, 2020, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
VerDate Sep<11>2014
18:32 Dec 04, 2020
Jkt 253001
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s environmental
document for the Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1
Schedule for Environmental Review
Issuance of EA March 16, 2021
90-day Federal Authorization Decision
Deadline June 14, 2021
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The East Lateral XPress Project would
consist of the following facilities:
• 8.1 miles of 30-inch-diameter
pipeline lateral within Barataria Bay in
Jefferson and Plaquemines Parishes,
Louisiana;
• a new 23,470-horsepower
compressor station at an existing
Columbia Gulf abandoned compressor
station site in St. Mary Parish, Louisiana
(Centerville Compressor Station);
• a new 23,470-horsepower
compressor station adjacent to an
existing tie-in facility in Lafourche
Parish, Louisiana (Golden Meadow
Compressor Station);
• one new delivery meter station;
• one new tie-in facility in Barataria
Bay; and
• two new mainline valves.
Background
On October 21, 2020, the Commission
issued a Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Proposed
East Lateral XPress Project (Notice of
Scoping). The Notice of Scoping was
sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the Notice of Scoping, the Commission
received comments from the National
Oceanic and Atmospheric
Administration National Marine
Fisheries Service, the U.S.
Environmental Protection Agency, and
the Teamsters National Pipeline Labor
Management Cooperation Trust. The
primary issues raised by the
1 40
PO 00000
CFR 1501.10 (2020)
Frm 00029
Fmt 4703
Sfmt 4703
78849
commenters are essential fish habitat;
air quality; environmental justice
populations; and tribal impacts. All
substantive comments will be addressed
in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Additional information about the
Project is available from the
Commission’s
Office of External Affairs at (866) 208–
FERC or on the FERC website
(www.ferc.gov). Using the eLibrary link,
select General Search from the eLibrary
menu, enter the selected date range and
Docket Number (i.e., CP20–527), and
follow the instructions. For assistance
with access to eLibrary, the helpline can
be reached at (866) 208–3676, TTY (202)
502–8659, or at FERCOnlineSupport@
ferc.gov. The eLibrary link on the FERC
website also provides access to the texts
of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
Dated: December 1, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26825 Filed 12–4–20; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPP–2017–0750; FRL–10017–13]
Pesticide Registration Review;
Proposed Interim Decision for
Chlorpyrifos; Notice of Availability
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
This notice announces the
availability of EPA’s proposed interim
registration review decision for
chlorpyrifos and opens a 60-day public
comment period on the proposed
interim decision, revised draft human
health risk assessment and ecological
risk assessment for chlorpyrifos.
DATES: Comments must be received on
or before February 5, 2021.
ADDRESSES: Submit your comments,
identified by the docket identification
SUMMARY:
E:\FR\FM\07DEN1.SGM
07DEN1
Agencies
[Federal Register Volume 85, Number 235 (Monday, December 7, 2020)]
[Notices]
[Pages 78847-78849]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-26821]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2879-012]
Green Mountain Power Corporation; Notice of Application Accepted
for Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations,
Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2879-012.
c. Date Filed: January 30, 2020.
d. Applicant: Green Mountain Power Corporation (GMP).
e. Name of Project: Bolton Falls Hydroelectric Project.
f. Location: The existing project is located on the Winooski River
in Washington County, Vermont. The project does not affect federal
lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)--825(r).
h. Applicant Contact: Mr. John Greenan, P.E., Engineer, Green
Mountain Power Corporation, 1252 Post Road, Rutland, Vermont 05701;
phone: (802) 770-2195 or email at [email protected].
i. FERC Contact: Michael Tust at (202) 502-6522; or email at
[email protected].
j. Deadline for filing motions to intervene and protests, comments,
recommendations, preliminary terms and conditions, and preliminary
[[Page 78848]]
prescriptions: 60 days from the issuance date of this notice; reply
comments are due 105 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene, protests, comments, recommendations, preliminary
terms and conditions, and preliminary fishway prescriptions using the
Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://ferconline.ferc.gov/QuickComment.aspx. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
The Council on Environmental Quality (CEQ) issued a final rule on
July 15, 2020, revising the regulations under 40 CFR parts 1500-1518
that federal agencies use to implement NEPA (see Update to the
Regulations Implementing the Procedural Provisions of the National
Environmental Policy Act, 85 FR 43,304). The Final Rule became
effective on and applies to any NEPA process begun after September 14,
2020. An agency may also apply the regulations to ongoing activities
and environmental documents begun before September 14, 2020, which
includes the proposed Bolton Falls Project relicensing. Commission
staff intends to conduct its NEPA review in accordance with CEQ's new
regulations.
l. The Bolton Falls Project consists of the following constructed
facilities: (1) A 92-foot-high, 275-foot-wide timber crib dam with a 5-
foot-high rubber dam atop the timber crib construction with a maximum
crest elevation of 397 feet and a 196-foot-long reinforced concrete
spillway cap at a crest elevation of 392 feet; (2) a 59-acre
impoundment with a total storage capacity of 300 acre-feet at a normal
operating elevation of 397 feet; (3) a forebay with two concrete
intakes, each with a 3-inch-spaced trashrack; (4) two 10-foot diameter,
120-foot-long steel penstocks; (5) a 73-foot-long, 57-foot-wide
powerhouse containing two horizontal, 3,750-kilowatt Kaplan turbines
with a total installed capacity of 7,500 kilowatts; (6) a 36-inch
diameter steel bypass pipe with an invert elevation of 383 feet that
discharges near the left side of the spillway base; (7) an
approximately 130-foot long, 5-kilovolt underground transmission line
connecting to an adjacent switchyard; (8) a 600-foot-long, 34.5-
kilovolt overhead transmission line connecting to a second switchyard;
and (9) appurtenant facilities. GMP also maintains day-use recreation
facilities at the project, including a picnic area, trails, fishing
access, and a canoe launch and portage trail.
GMP proposes to operate in automated run-of-river mode as it does
under its current practice but instead of providing a 300-cubic feet
per second (cfs) minimum flow into the Winooski River through the
powerhouse (when generating) or via spill over the dam (when not
generating) as it does now, GMP proposes to provide a seasonal
aesthetic spill flow of 75 cfs or inflow, whichever is less, into the
bypassed reach via spillage over the dam during daylight hours from
April 1 through December 15. At all other times, bypassed reach flows
would be reduced to leakage except when inflow drops below the minimum
hydraulic capacity (i.e., 365 cfs) or when inflow exceeds the maximum
hydraulic capacity (2,400 cfs) of the generating units in which case
additional flows would be released to the bypassed reach via spill over
the dam. Under normal flow conditions when aesthetic spillage is
required, GMP proposes to maintain the impoundment at an elevation of
397.25 feet. When aesthetic spillage over the dam is not required, GMP
proposes to maintain the reservoir at an elevation of 397 feet as it
does now. GMP also proposes to: (1) Relocate recreation parking area
out of the floodplain; (2) implement measures to protect creeping
lovegrass at the day-use area; (3) add two picnic tables and an
information kiosk to the day-use area; and (4) improve the portage
landing, trail, and signage.
m. A copy of the application can viewed on the Commission's website
at https://www.ferc.gov using the eLibrary link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC Online Support.
Register online at https://ferconline.ferc.gov/FERCOnline.aspx to
be notified via email of new filings and issuances related to this or
other pending projects. For assistance, contact FERC Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title PROTEST,
MOTION TO INTERVENE, COMMENTS, REPLY COMMENTS, RECOMMENDATIONS,
PRELIMINARY TERMS AND CONDITIONS, or PRELIMINARY FISHWAY PRESCRIPTIONS;
(2) set forth in the heading the name of the applicant and the project
number of the application to which the filing responds; (3) furnish the
name, address, and telephone number of the person protesting or
intervening; and (4) otherwise comply with the requirements of 18 CFR
385.2001 through 385.2005. All comments, recommendations, terms and
conditions or prescriptions must set forth their evidentiary basis and
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may
obtain copies of the application directly from the applicant. A copy of
any protest or motion to intervene must be served upon each
representative of the applicant specified in the particular
application. A copy of all other filings in reference to this
application must be accompanied by proof of service on all persons
listed in the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
o. Final amendments to the application must be filed with the
Commission no later than thirty (30) days from the issuance date of
this notice.
[[Page 78849]]
p. The applicant must file no later than 60 days following the date
of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification. Please note
that the certification request must be sent to the certifying authority
and to the Commission concurrently.
q. Procedural schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Deadline for Filing Comments, January 2021.
Recommendations, and Agency Terms and
Conditions/Prescriptions.
Deadline for Filing Reply Comments...... March 2021.
------------------------------------------------------------------------
Dated: December 1, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-26821 Filed 12-4-20; 8:45 am]
BILLING CODE 6717-01-P