Federal Register / Vol. 85, No. 234 / Friday, December 4, 2020 / Notices
two 8-foot-wide, 8-foot-high low-level
outlet gates (only one of which is
operational), that control flow into two
7-foot-diameter, 40-foot-long outlet
pipes; and (c) a 71-foot-long right
abutment section; (2) a 40-acre
impoundment with a normal surface
elevation of 106.37 feet NGVD 29; (3) a
40.5-foot-wide, 20-foot-high intake
structure with four 5-foot-wide, 10.5foot-high steel frame gates and a
trashrack with 2-inch bar spacing; (4) an
8.5-foot-diameter, 120-foot-long left,
steel penstock that bifurcates into a 5.3foot-diameter, 85-foot-long section and a
7.6-foot-diameter, 85-foot-long section;
(5) an 8.5-foot-diameter, 140-foot-long
right, steel penstock that bifurcates into
a 7-foot-diameter, 85-foot-long section
and a 7.6-foot-diameter, 85-foot-long
section; (6) a 46-foot-long, 30-foot-wide
concrete and brick powerhouse with
two 260-kilowatt (kW) F-type Francis
turbine-generator units and two 380-kW
F-type Francis turbine-generator units,
for a total installed capacity of 1.28 MW;
(7) a 55-foot-long, 30-foot-wide tailrace;
(8) a 260-foot-long underground
transmission line that delivers power to
a 4.16-kilovolt distribution line; and (9)
appurtenant facilities. The project
creates an approximately 250-foot-long
bypassed reach of the Salmon Falls
River.
The project operates as a run-of-river
(ROR) facility with no storage or flood
control capacity. The project
impoundment is maintained at a
flashboard crest elevation of 106.37 feet
NGVD. The current license requires the
project to maintain a continuous
minimum flow of 6.05 cubic feet per
second (cfs) or inflow, whichever is less,
to the bypassed reach for the purpose of
protecting and enhancing aquatic
resources in the Salmon Falls River. The
average annual generation production of
the project was 3,916,825 kilowatt-hours
from 2005 through 2018.
The applicant proposes to: (1)
Continue operating the project in a ROR
mode; (2) provide a minimum flow of 30
cfs or inflow, whichever is less, to the
bypassed reach; (3) install an eel ramp
for upstream eel passage at the project;
(4) implement targeted nighttime
turbine shutdowns to protect eels
during downstream passage; (5) install a
downstream fish passage structure for
eels and other fish species.
m. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents via the
internet through the Commission’s
Home Page (https://www.ferc.gov) using
the eLibrary link. Enter the docket
number excluding the last three digits in
VerDate Sep<11>2014
18:18 Dec 03, 2020
Jkt 253001
the docket number field to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TYY, (202)
502–8659.
n. You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process.
Commission staff will prepare either
an environmental assessment (EA) or an
Environmental Impact Statement (EIS)
that describes and evaluates the
probable effects, if any, of the licensee’s
proposed action and alternatives. The
EA or EIS will consider environmental
impacts and reasonable alternatives to
the proposed action. The Commission’s
scoping process will help determine the
required level of analysis and satisfy the
NEPA scoping requirements,
irrespective of whether the Commission
prepares an EA or an EIS. Due to
restrictions on mass gatherings related
to COVID–19, we do not intend to
conduct a public scoping meeting and
site visit in this case. Instead, we are
soliciting written comments and
suggestions on the preliminary list of
issues and alternatives to be addressed
in the NEPA document, as described in
scoping document 1 (SD1), issued
November 30, 2020.
Copies of the SD1 outlining the
subject areas to be addressed in the
NEPA document were distributed to the
parties on the Commission’s mailing list
and the applicant’s distribution list.
Copies of SD1 may be viewed on the
web at https://www.ferc.gov using the
eLibrary link. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
Dated: November 30, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26715 Filed 12–3–20; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–2446–002.
Applicants: Bitter Ridge Wind Farm,
LLC.
Description: Compliance filing:
Revised Rate Schedule FERC No. 1
Under Docket ER20–2446 to be effective
9/15/2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5045
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–136–000.
Applicants: Flat Ridge 3 Wind Energy,
LLC.
Description: Resubmittal of
Attachments [Asset Appendix and
Exhibit D] to October 16, 2020 Flat
Ridge 3 Wind Energy, LLC tariff filing.
Filed Date: 11/25/20.
Accession Number: 20201125–5193.
Comments Due: 5 p.m. ET 12/7/20.
Docket Numbers: ER21–497–000.
Applicants: EDF Renewables
Development, Inc.
Description: Petition for Limited
Waiver, et al. of EDF Renewables
Development, Inc.
Filed Date: 11/25/20.
Accession Number: 20201125–5196.
Comments Due: 5 p.m. ET 12/7/20.
Docket Numbers: ER21–498–000.
Applicants: Otter Tail Power
Company.
Description: § 205(d) Rate Filing:
Filing of Revised Certificate of
Concurrence—NSP TCEA to be effective
1/4/2021.
Filed Date: 11/30/20.
Accession Number: 20201130–5051.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–499–000.
Applicants: New England Power Pool
Participants Committee.
Description: § 205(d) Rate Filing:
December 2020 Membership Filing to be
effective 11/1/2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5093.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–500–000.
Applicants: Exelon Generation
Company, LLC.
Description: Compliance filing:
Reactive Service Rate Schedule
Compliance Filing—Request for
Expedited Action to be effective 12/17/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5143.
E:\FR\FM\04DEN1.SGM
04DEN1
Federal Register / Vol. 85, No. 234 / Friday, December 4, 2020 / Notices
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–501–000.
Applicants: Arizona Public Service
Company.
Description: § 205(d) Rate Filing:
Service Agreement Nos. 383 and 384_
Sun Streams to be effective 11/1/2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5144.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–502–000.
Applicants: New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing: 205
filing re: 2021–2025 ICAP Demand
Curve Reset Proposal to be effective 1/
30/2021.
Filed Date: 11/30/20.
Accession Number: 20201130–5146.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–503–000.
Applicants: Alabama Power
Company.
Description: Initial rate filing: Cotton
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5175.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–504–000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Cotton
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5176.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–505–000.
Applicants: Mississippi Power
Company.
Description: Initial rate filing: Cotton
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5178.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–506–000.
Applicants: Alabama Power
Company.
Description: Initial rate filing: Wild
Azalea Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20..
Accession Number: 20201130–5179.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–507–000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Wild
Azalea Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5182.
VerDate Sep<11>2014
19:00 Dec 03, 2020
Jkt 253001
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–508–000.
Applicants: Mississippi Power
Company.
Description: Initial rate filing: Wild
Azalea Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5183.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–509–000.
Applicants: Alabama Power
Company.
Description: Initial rate filing: Flowers
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5185.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–510–000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Flowers
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5187.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–511–000.
Applicants: Safe Harbor Water Power
Corporation.
Description: § 205(d) Rate Filing:
Revised Reactive Service Tariff and
Requests for Waiver and Expedited
Action to be effective 1/1/2021.
Filed Date: 11/30/20.
Accession Number: 20201130–5190.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–512–000.
Applicants: Mississippi Power
Company.
Description: Initial rate filing: Flowers
Creek Affected System Upgrade
Agreement Filing to be effective 10/29/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130–5195.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–513–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing:
November 2020 Western WDT Service
Agreement Biannual Filing to be
effective 2/1/2021.
Filed Date: 11/30/20.
Accession Number: 20201130–5198.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21–514–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing:
November 2020 Western
Interconnection Agreement Biannual
Filing to be effective 2/1/2021.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
78321
Filed Date: 11/30/20.
Accession Number: 20201130–5201.
Comments Due: 5 p.m. ET 12/21/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 30, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26716 Filed 12–3–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–13–000]
Southern Natural Gas Company LLC;
Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on November 20,
2020, Southern Natural Gas Company,
LLC, 569 Brookwood Village, Suite 749,
Birmingham, Alabama 35209, filed in
the above referenced docket a prior
notice pursuant to Section 157.210 and
157.216 of the Federal Energy
Regulatory Commission’s regulations
under the Natural Gas Act, seeking
authorization to replace approximately
0.81 miles of 14-inch pipe on its
Chattanooga Branch Line with 20-inch
pipe, abandon in place approximately
0.81 miles of the 14″ Chattanooga
Branch Line being replaced with the
larger diameter pipeline, and perform
minor modifications at its Dalton #2
Meter Station in order to accommodate
increased deliveries of natural gas to
Dalton Utilities located in Whitfield
County, Georgia. Southern proposes to
abandon these facilities under
authorities granted by its blanket
certificate issued in Docket No. CP82–
E:\FR\FM\04DEN1.SGM
04DEN1
Agencies
[Federal Register Volume 85, Number 234 (Friday, December 4, 2020)]
[Notices]
[Pages 78320-78321]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-26716]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER20-2446-002.
Applicants: Bitter Ridge Wind Farm, LLC.
Description: Compliance filing: Revised Rate Schedule FERC No. 1
Under Docket ER20-2446 to be effective 9/15/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5045
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-136-000.
Applicants: Flat Ridge 3 Wind Energy, LLC.
Description: Resubmittal of Attachments [Asset Appendix and Exhibit
D] to October 16, 2020 Flat Ridge 3 Wind Energy, LLC tariff filing.
Filed Date: 11/25/20.
Accession Number: 20201125-5193.
Comments Due: 5 p.m. ET 12/7/20.
Docket Numbers: ER21-497-000.
Applicants: EDF Renewables Development, Inc.
Description: Petition for Limited Waiver, et al. of EDF Renewables
Development, Inc.
Filed Date: 11/25/20.
Accession Number: 20201125-5196.
Comments Due: 5 p.m. ET 12/7/20.
Docket Numbers: ER21-498-000.
Applicants: Otter Tail Power Company.
Description: Sec. 205(d) Rate Filing: Filing of Revised
Certificate of Concurrence--NSP TCEA to be effective 1/4/2021.
Filed Date: 11/30/20.
Accession Number: 20201130-5051.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-499-000.
Applicants: New England Power Pool Participants Committee.
Description: Sec. 205(d) Rate Filing: December 2020 Membership
Filing to be effective 11/1/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5093.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-500-000.
Applicants: Exelon Generation Company, LLC.
Description: Compliance filing: Reactive Service Rate Schedule
Compliance Filing--Request for Expedited Action to be effective 12/17/
2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5143.
[[Page 78321]]
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-501-000.
Applicants: Arizona Public Service Company.
Description: Sec. 205(d) Rate Filing: Service Agreement Nos. 383
and 384_Sun Streams to be effective 11/1/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5144.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-502-000.
Applicants: New York Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 205 filing re: 2021-2025
ICAP Demand Curve Reset Proposal to be effective 1/30/2021.
Filed Date: 11/30/20.
Accession Number: 20201130-5146.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-503-000.
Applicants: Alabama Power Company.
Description: Initial rate filing: Cotton Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5175.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-504-000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Cotton Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5176.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-505-000.
Applicants: Mississippi Power Company.
Description: Initial rate filing: Cotton Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5178.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-506-000.
Applicants: Alabama Power Company.
Description: Initial rate filing: Wild Azalea Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20..
Accession Number: 20201130-5179.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-507-000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Wild Azalea Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5182.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-508-000.
Applicants: Mississippi Power Company.
Description: Initial rate filing: Wild Azalea Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5183.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-509-000.
Applicants: Alabama Power Company.
Description: Initial rate filing: Flowers Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5185.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-510-000.
Applicants: Georgia Power Company.
Description: Initial rate filing: Flowers Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5187.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-511-000.
Applicants: Safe Harbor Water Power Corporation.
Description: Sec. 205(d) Rate Filing: Revised Reactive Service
Tariff and Requests for Waiver and Expedited Action to be effective 1/
1/2021.
Filed Date: 11/30/20.
Accession Number: 20201130-5190.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-512-000.
Applicants: Mississippi Power Company.
Description: Initial rate filing: Flowers Creek Affected System
Upgrade Agreement Filing to be effective 10/29/2020.
Filed Date: 11/30/20.
Accession Number: 20201130-5195.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-513-000.
Applicants: Pacific Gas and Electric Company.
Description: Sec. 205(d) Rate Filing: November 2020 Western WDT
Service Agreement Biannual Filing to be effective 2/1/2021.
Filed Date: 11/30/20.
Accession Number: 20201130-5198.
Comments Due: 5 p.m. ET 12/21/20.
Docket Numbers: ER21-514-000.
Applicants: Pacific Gas and Electric Company.
Description: Sec. 205(d) Rate Filing: November 2020 Western
Interconnection Agreement Biannual Filing to be effective 2/1/2021.
Filed Date: 11/30/20.
Accession Number: 20201130-5201.
Comments Due: 5 p.m. ET 12/21/20.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: November 30, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-26716 Filed 12-3-20; 8:45 am]
BILLING CODE 6717-01-P