Golden Pass Pipeline LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Compression Relocation and Modification Project, 75313-75315 [2020-26077]
Download as PDF
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 228 / Wednesday, November 25, 2020 / Notices
Power, 241 Ralph McGill Blvd., NE, BIN
10151, Atlanta, Georgia 30308, (404)
506–2337, jcharles@southernco.com.
i. FERC Contact: Mark Carter, (678)
245–3083, mark.carter@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
December 21, 2020.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–2413–132. Comments
emailed to Commission staff are not
considered part of the Commission
record.
k. Description of Request: As required
by Article 410 of the June 28, 2020,
license, Georgia Power Company filed a
revised Recreation and Land Use Plan
for the project. In addition to the
provisions of the plan filed during
relicensing, the revised Recreation and
Land Use Plan includes the provisions
required by Article 410 (i.e., a ten-year
plan review process, incorporating U.S.
Forest Service 4(e) Condition 24,
consulting the Georgia Department of
Natural Resources on boating access,
documenting the number of parking
spaces at each boat ramp, and specifying
public access available on future
recreation lands).
l. Locations of the Application: In
addition to publishing the full text of
this document in the Federal Register,
the Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
Home Page (https://www.ferc.gov) using
the elibrary link. Enter the docket
number excluding the last three digits in
the document field to access the
VerDate Sep<11>2014
16:27 Nov 24, 2020
Jkt 253001
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3673 or TYY, (202)
502–8659. Agencies may obtain copies
of the application directly from the
applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title COMMENTS, PROTEST,
or MOTION TO INTERVENE as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person commenting,
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, motions to intervene, or
protests must set forth their evidentiary
basis. Any filing made by an intervenor
must be accompanied by proof of
service on all persons listed in the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 385.2010.
Dated: November 19, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26080 Filed 11–24–20; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
75313
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–1–000]
Golden Pass Pipeline LLC; Notice of
Scoping Period Requesting Comments
on Environmental Issues for the
Proposed Compression Relocation
and Modification Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Compression Relocation and
Modification Project involving
construction and operation of facilities
by Golden Pass Pipeline LLC (Golden
Pass) in Calcasieu Parish, Louisiana.
The Commission will use this
environmental document in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
amending a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on
December 19, 2020. Comments may be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
E:\FR\FM\25NON1.SGM
25NON1
75314
Federal Register / Vol. 85, No. 228 / Wednesday, November 25, 2020 / Notices
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on October 2,
2020 you will need to file those
comments in Docket No. CP21–1–000 to
ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law. The
Commission does not subsequently
grant, exercise, or oversee the exercise
of that eminent domain authority. The
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
Golden Pass provided landowners
with a fact sheet prepared by the FERC
entitled An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know? which addresses typically
asked questions, including the use of
eminent domain and how to participate
in the Commission’s proceedings. This
fact sheet along with other landowner
topics of interest are available for
viewing on the FERC website
(www.ferc.gov) under the Natural Gas
Questions or Landowner Topics link.
jbell on DSKJLSW7X2PROD with NOTICES
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
VerDate Sep<11>2014
16:27 Nov 24, 2020
Jkt 253001
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on eRegister. You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
Comment on a Filing; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP21–1–000) on
your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Summary of the Proposed Project
Specifically, Golden Pass seeks to
modify previously authorized facilities,
including:
• Relocate the approved compressor
Station at Milepost (MP) 66
approximately three miles, to MP 69,
and increase the amount of compression
at the relocated facility;
• Add a meter station near MP 69 to
support a new interconnection with a
proposed interstate pipeline to be
constructed an operated by Enable Gulf
Run Transmission, LLC;
• Remove any bi-directional piping
modification to the interconnect;
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
• Minor modifications to existing
interconnects at MP 66 and MP 68.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Land requirements for the proposed
modifications total approximately 44
acres, with construction and operation
of the MP 69 compressor station
requiring 35 acres.
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under the relevant
general resource areas:
• Geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called eLibrary. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room
due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus
Disease (COVID–19), issued by the President on
March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
E:\FR\FM\25NON1.SGM
25NON1
Federal Register / Vol. 85, No. 228 / Wednesday, November 25, 2020 / Notices
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on General Search and enter the
docket number in the Docket Number
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: November 19, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–26077 Filed 11–24–20; 8:45 am]
BILLING CODE 6717–01–P
jbell on DSKJLSW7X2PROD with NOTICES
2 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
16:27 Nov 24, 2020
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
75315
Docket Numbers: CP21–11–000.
Applicants: Transcontinental Gas
Pipe Line Company, LLC.
Description: Application for Partial
Abandonment of Service of
Transcontinental Gas Pipe Line
Company, LLC.
Filed Date: 11/16/20.
Accession Number: 20201116–5234.
Comments Due: 5 p.m. ET 12/7/20.
Docket Numbers: RP21–223–000.
Applicants: Tres Palacios Gas Storage
LLC.
Description: § 4(d) Rate Filing: Tres
Palacios Gas Storage LLC—Filing of
Tariff Modifications to be effective
12/19/2020.
Filed Date: 11/18/20.
Accession Number: 20201118–5009.
Comments Due: 5 p.m. ET 11/30/20.
Docket Numbers: RP21–224–000.
Applicants: Trunkline Gas Company,
LLC.
Description: § 4(d) Rate Filing: Quality
Provision for Renewable Gas to be
effective 12/19/2020.
Filed Date: 11/18/20.
Accession Number: 20201118–5025.
Comments Due: 5 p.m. ET 11/30/20.
Docket Numbers: RP21–225–000.
Applicants: Central Kentucky
Transmission Company.
Description: Tariff Cancellation: CKY
Request for Cancellation of its Tariff to
be effective 12/1/2020.
Filed Date: 11/18/20.
Accession Number: 20201118–5042.
Comments Due: 5 p.m. ET 11/30/20.
Docket Numbers: RP21–226–000.
Applicants: Dominion Energy
Overthrust Pipeline, LLC.
Description: § 4(d) Rate Filing: Nonconforming TSAs, Citadel K5613
Amendment No. 37 to be effective 11/
14/2020.
Filed Date: 11/18/20.
Accession Number: 20201118–5068.
Comments Due: 5 p.m. ET 11/30/20.
Docket Numbers: RP21–227–000.
Applicants: Algonquin Gas
Transmission, LLC.
Description: § 4(d) Rate Filing:
Negotiated Rate—Yankee Gas 510802
Release eff 11–19–2020 to be effective
11/19/2020.
Filed Date: 11/18/20.
Accession Number: 20201118–5069.
Comments Due: 5 p.m. ET 11/30/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
E:\FR\FM\25NON1.SGM
25NON1
Agencies
[Federal Register Volume 85, Number 228 (Wednesday, November 25, 2020)]
[Notices]
[Pages 75313-75315]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-26077]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-1-000]
Golden Pass Pipeline LLC; Notice of Scoping Period Requesting
Comments on Environmental Issues for the Proposed Compression
Relocation and Modification Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Compression Relocation and
Modification Project involving construction and operation of facilities
by Golden Pass Pipeline LLC (Golden Pass) in Calcasieu Parish,
Louisiana. The Commission will use this environmental document in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers
amending a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on December 19, 2020. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission
[[Page 75314]]
staff determine what issues they need to evaluate in the environmental
document. Commission staff will consider all written comments during
the preparation of the environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on October 2, 2020 you will need to file
those comments in Docket No. CP21-1-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The courts have exclusive authority to handle
eminent domain cases; the Commission has no jurisdiction over these
matters.
Golden Pass provided landowners with a fact sheet prepared by the
FERC entitled An Interstate Natural Gas Facility On My Land? What Do I
Need To Know? which addresses typically asked questions, including the
use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas Questions or Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on eRegister. You will be asked to select the type of filing you are
making; a comment on a particular project is considered a Comment on a
Filing; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP21-1-
000) on your letter. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Proposed Project
Specifically, Golden Pass seeks to modify previously authorized
facilities, including:
Relocate the approved compressor Station at Milepost (MP)
66 approximately three miles, to MP 69, and increase the amount of
compression at the relocated facility;
Add a meter station near MP 69 to support a new
interconnection with a proposed interstate pipeline to be constructed
an operated by Enable Gulf Run Transmission, LLC;
Remove any bi-directional piping modification to the
interconnect;
Minor modifications to existing interconnects at MP 66 and
MP 68.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called eLibrary. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact
FERC at [email protected] or call toll free, (886) 208-3676
or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Land requirements for the proposed modifications total
approximately 44 acres, with construction and operation of the MP 69
compressor station requiring 35 acres.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
Geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/
[[Page 75315]]
Notice of Schedule will be issued, which will open up an additional
comment period. Staff will then prepare a draft EIS which will be
issued for public comment. Commission staff will consider all timely
comments received during the comment period on the draft EIS and revise
the document, as necessary, before issuing a final EIS. Any EA or draft
and final EIS will be available in electronic format in the public
record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please return the
attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on General Search and enter the docket number in
the Docket Number field. Be sure you have selected an appropriate date
range. For assistance, please contact FERC Online Support at
[email protected] or (866) 208-3676, or for TTY, contact (202)
502-8659. The eLibrary link also provides access to the texts of all
formal documents issued by the Commission, such as orders, notices, and
rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: November 19, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-26077 Filed 11-24-20; 8:45 am]
BILLING CODE 6717-01-P