Spire Storage West, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Clear Creek Expansion Project, 73032-73034 [2020-25209]

Download as PDF jbell on DSKJLSW7X2PROD with NOTICES 73032 Federal Register / Vol. 85, No. 221 / Monday, November 16, 2020 / Notices ER10–1852–044; ER10–1905–019; ER10–1907–018; ER10–1918–019; ER10–1925–019; ER10–1927–019; ER10–1950–019; ER10–1951–026; ER10–1970–018; ER10–1972–018; ER10–2005–019; ER10–2006–019; ER10–2078–019; ER11–26–019; ER11– 4462–047; ER12–1660–018; ER13–2458– 013; ER13–2461–013; ER16–1872–009; ER16–2506–010; ER17–2270–010; ER17–838–022; ER18–1771–008; ER18– 2224–008; ER18–2246–007; ER19–1003– 006; ER19–1393–006; ER19–1394–006; ER19–2382–002; ER19–2398–003; ER19–2437–002; ER19–2461–002; ER19–987–006; ER20–122–002; ER20– 975–001. Applicants: Ashtabula Wind I, LLC, Ashtabula Wind II, LLC, Ashtabula Wind III, LLC, Butler Ridge Wind Energy Center, LLC, Crowned Ridge Interconnection, LLC, Crowned Ridge Wind, LLC, Crowned Ridge Wind II, LLC, Crystal Lake Wind Energy I, LLC, Crystal Lake Wind Energy II, LLC, Crystal Lake Wind III, LLC, EmmonsLogan Wind, LLC, Endeavor Wind I, LLC, Endeavor Wind II, LLC, Florida Power & Light Company, FPL Energy Mower County, LLC, FPL Energy North Dakota Wind, LLC, FPL Energy North Dakota Wind II, LLC, FPL Energy Oliver Wind I, LLC, FPL Energy Oliver Wind II, LLC, Garden Wind, LLC, Hancock County Wind, LLC, Hawkeye Power Partners, LLC, Heartland Divide Wind Project, LLC, Langdon Renewables, LLC, Marshall Solar, LLC, NextEra Energy Duane Arnold, LLC, NextEra Energy Point Beach, LLC, Oliver Wind III, LLC, Pegasus Wind, LLC, Pheasant Run Wind, LLC, Story County Wind, LLC, Stuttgart Solar, LLC, Tuscola Bay Wind, LLC, Tuscola Wind II, LLC, White Oak Energy LLC, NEPM II, LLC, NextEra Energy Services Massachusetts, LLC, NextEra Energy Marketing, LLC. Description: Notification of Change in Status of NextEra Resources Entities. Filed Date: 11/5/20. Accession Number: 20201105–5187. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–321–000. Applicants: RRE Power LLC, Bridge Solar LLC. Description: Petition of for Limited Waiver of RRE Power LLC, et al. Filed Date: 10/30/20. Accession Number: 20201030–5463. Comments Due: 5 p.m. ET 11/20/20. Docket Numbers: ER21–351–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2020–11–06_Surplus Interconnection Product Study Clarification Filing to be effective 1/6/2021. Filed Date: 11/6/20. VerDate Sep<11>2014 20:13 Nov 13, 2020 Jkt 253001 Accession Number: 20201106–5162. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–352–000. Applicants: Flat Ridge Interconnection LLC. Description: Baseline eTariff Filing: Filing of Common Facilities Agreement to be effective 12/1/2020. Filed Date: 11/6/20. Accession Number: 20201106–5163. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–353–000. Applicants: Oakland Power Company LLC. Description: § 205(d) Rate Filing: Notices of Succession and Revisions to Tariffs and Agreements (I) to be effective 10/30/2020. Filed Date: 11/6/20. Accession Number: 20201106–5166. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–354–000. Applicants: Moss Landing Power Company LLC. Description: § 205(d) Rate Filing: Notices of Succession and Revisions to Tariffs and Agreements (II) to be effective 10/30/2020. Filed Date: 11/6/20. Accession Number: 20201106–5170. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–355–000. Applicants: Pacific Gas and Electric Company. Description: § 205(d) Rate Filing: 1st Amendment to CDWR Hyatt-Thermalito LGIA (SA 273) to be effective 1/6/2021. Filed Date: 11/6/20. Accession Number: 20201106–5172. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–356–000. Applicants: Flat Ridge 2 Wind Energy LLC. Description: § 205(d) Rate Filing: Certificate of Concurrence to Common Facilities Agreement to be effective 12/ 1/2020. Filed Date: 11/6/20. Accession Number: 20201106–5182. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–357–000. Applicants: Public Service Company of New Mexico. Description: § 205(d) Rate Filing: Executed Engineering and Procurement Agreement between PNM and 201LC 8me LLC to be effective 10/20/2020. Filed Date: 11/6/20. Accession Number: 20201106–5183. Comments Due: 5 p.m. ET 11/27/20. Docket Numbers: ER21–358–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original ISA, Service Agreement No. 5823; Queue No. AC2–103 to be effective 10/12/2020. PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 Filed Date: 11/9/20. Accession Number: 20201109–5068. Comments Due: 5 p.m. ET 11/30/20. Docket Numbers: ER21–359–000. Applicants: Flat Ridge 3 Wind Energy, LLC. Description: § 205(d) Rate Filing: CFA, Common Facilities Agreement to be effective 12/1/2020. Filed Date: 11/9/20. Accession Number: 20201109–5067. Comments Due: 5 p.m. ET 11/30/20. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 9, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–25204 Filed 11–13–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–6–000] Spire Storage West, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Clear Creek Expansion Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document, that will discuss the environmental impacts of the Clear Creek Expansion Project involving construction and operation of facilities by Spire Storage West, LLC (Spire Storage) in Uinta County, Wyoming. The Commission will use this environmental document in its decision-making process to determine whether the project is in the public convenience and necessity. E:\FR\FM\16NON1.SGM 16NON1 jbell on DSKJLSW7X2PROD with NOTICES Federal Register / Vol. 85, No. 221 / Monday, November 16, 2020 / Notices This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies regarding the project. As part of the National Environmental Policy Act (NEPA) review process, the Commission takes into account concerns the public may have about proposals and the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. This gathering of public input is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the environmental document on the important environmental issues. Additional information about the Commission’s NEPA process is described below in the NEPA Process and Environmental Document section of this notice. By this notice, the Commission requests public comments on the scope of issues to address in the environmental document. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on December 9, 2020. Comments may be submitted in written form. Further details on how to submit comments are provided in the Public Participation section of this notice. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the environmental document. Commission staff will consider all written comments during the preparation of the environmental document. If you submitted comments on this project to the Commission before the opening of this docket on October 9, 2020, you will need to file those comments in Docket No. CP21–6–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would VerDate Sep<11>2014 20:13 Nov 13, 2020 Jkt 253001 seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, the Natural Gas Act conveys the right of eminent domain to the company. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. The Commission does not subsequently grant, exercise, or oversee the exercise of that eminent domain authority. The courts have exclusive authority to handle eminent domain cases; the Commission has no jurisdiction over these matters. Spire Storage provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ which addresses typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. This fact sheet along with other landowner topics of interest are available for viewing on the FERC website (www.ferc.gov) under the Natural Gas Questions or Landowner Topics link. Public Participation There are three methods you can use to submit your comments to the Commission. Please carefully follow these instructions so that your comments are properly recorded. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to FERC Online. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; a comment on a particular project is considered a ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 73033 Commission. Be sure to reference the project docket number (CP21–6–000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Additionally, the Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. Summary of the Proposed Project Spire Storage proposes to expand its natural gas storage facilities at its existing Clear Creek Storage Field in Uinta County, Wyoming in order to increase the certificated gas capacities from 4.0 billion cubic feet (Bcf) to 20 Bcf, and increase the maximum daily injection and withdrawal capacities from 35 million cubic feet (MMcf) and 50 MMcf per day, to 350 MMcf and 500 MMcf per day, respectively. Spire Storage further proposes to construct pipeline connections north to the Canyon Creek Plant, south to the Kern River Gas Transmission mainline, and reconnect with the Questar Pipeline at the Clear Creek Plant. According to Spire Storage, the purpose of this project is to increase storage capacity and enhance operational capabilities to satisfy market demand for natural gas services in the Western United States. The Clear Creek Expansion Project would consist of the following facilities: • Four compressor units at the Clear Creek Plant; • a tank storage and natural gas liquids fueling equipment facility on an existing pad; • 11 new injection/withdrawal wells, one new water disposal well, and associated lines; • approximately 10.6 miles of 20inch-diameter pipeline; • approximately 3.5 miles of 4,160volt powerline; and • other related appurtenances. E:\FR\FM\16NON1.SGM 16NON1 73034 Federal Register / Vol. 85, No. 221 / Monday, November 16, 2020 / Notices The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb about 249.0 acres of land for the aboveground facilities and the pipeline. Following construction, Spire Storage would maintain about 128.1 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. jbell on DSKJLSW7X2PROD with NOTICES NEPA Process and the Environmental Document Any environmental document issued by the Commission will discuss impacts that could occur as a result of the construction and operation of the proposed project under the relevant general resource areas: • Geology and soils; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • land use; • air quality and noise; and • reliability and safety. Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project and make recommendations on how to lessen or avoid impacts on the various resource areas. Your comments will help Commission staff identify and focus on the issues that might have an effect on the human environment and potentially eliminate others from further study and discussion in the environmental document. Following this scoping period, Commission staff will determine whether to prepare an Environmental Assessment (EA) or an Environmental Impact Statement (EIS). The EA or the EIS will present Commission staff’s independent analysis of the issues. If Commission staff prepares an EA, a Notice of Schedule for the Preparation of an Environmental Assessment will be issued. The EA may be issued for an allotted public comment period. The Commission would consider timely comments on the EA before making its decision regarding the proposed project. 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’. For instructions on connecting to eLibrary, refer to the last page of this notice. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll free, (886) 208–3676 or TTY (202) 502–8659. VerDate Sep<11>2014 20:13 Nov 13, 2020 Jkt 253001 If Commission staff prepares an EIS, a Notice of Intent to Prepare an EIS/ Notice of Schedule will be issued, which will open up an additional comment period. Staff will then prepare a draft EIS which will be issued for public comment. Commission staff will consider all timely comments received during the comment period on the draft EIS and revise the document, as necessary, before issuing a final EIS. Any EA or draft and final EIS will be available in electronic format in the public record through eLibrary 2 and the Commission’s natural gas environmental documents web page (https://www.ferc.gov/industries-data/ natural-gas/environment/ environmental-documents). If eSubscribed, you will receive instant email notification when the environmental document is issued. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the environmental document.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Currently, the Bureau of Land Management has expressed its intention to participate as a cooperating agency in the preparation of the environmental document to satisfy its NEPA responsibilities related to this project. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 The environmental document for this project will document findings on the impacts on historic properties and 2 For instructions on connecting to eLibrary, refer to the last page of this notice. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Section 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00018 Fmt 4703 Sfmt 9990 summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project and includes a mailing address with their comments. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached ‘‘Mailing List Update Form’’ (appendix 2). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at https://w.ferc.gov/newsevents/events along with other related information. Dated: November 9, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–25209 Filed 11–13–20; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\16NON1.SGM 16NON1

Agencies

[Federal Register Volume 85, Number 221 (Monday, November 16, 2020)]
[Notices]
[Pages 73032-73034]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-25209]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP21-6-000]


Spire Storage West, LLC; Notice of Scoping Period Requesting 
Comments on Environmental Issues for the Proposed Clear Creek Expansion 
Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental document, that will discuss 
the environmental impacts of the Clear Creek Expansion Project 
involving construction and operation of facilities by Spire Storage 
West, LLC (Spire Storage) in Uinta County, Wyoming. The Commission will 
use this environmental document in its decision-making process to 
determine whether the project is in the public convenience and 
necessity.

[[Page 73033]]

    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies regarding the project. As part of the National Environmental 
Policy Act (NEPA) review process, the Commission takes into account 
concerns the public may have about proposals and the environmental 
impacts that could result from its action whenever it considers the 
issuance of a Certificate of Public Convenience and Necessity. This 
gathering of public input is referred to as ``scoping.'' The main goal 
of the scoping process is to focus the analysis in the environmental 
document on the important environmental issues. Additional information 
about the Commission's NEPA process is described below in the NEPA 
Process and Environmental Document section of this notice.
    By this notice, the Commission requests public comments on the 
scope of issues to address in the environmental document. To ensure 
that your comments are timely and properly recorded, please submit your 
comments so that the Commission receives them in Washington, DC on or 
before 5:00 p.m. Eastern Time on December 9, 2020. Comments may be 
submitted in written form. Further details on how to submit comments 
are provided in the Public Participation section of this notice.
    Your comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the environmental document. Commission 
staff will consider all written comments during the preparation of the 
environmental document.
    If you submitted comments on this project to the Commission before 
the opening of this docket on October 9, 2020, you will need to file 
those comments in Docket No. CP21-6-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, the Natural Gas Act conveys the right of eminent 
domain to the company. Therefore, if you and the company do not reach 
an easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law. The Commission does 
not subsequently grant, exercise, or oversee the exercise of that 
eminent domain authority. The courts have exclusive authority to handle 
eminent domain cases; the Commission has no jurisdiction over these 
matters.
    Spire Storage provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' which addresses typically asked questions, including 
the use of eminent domain and how to participate in the Commission's 
proceedings. This fact sheet along with other landowner topics of 
interest are available for viewing on the FERC website (www.ferc.gov) 
under the Natural Gas Questions or Landowner Topics link.

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. Please carefully follow these instructions so that your 
comments are properly recorded. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (CP21-6-
000) on your letter. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.

Additionally, the Commission offers a free service called eSubscription 
which makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.

Summary of the Proposed Project

    Spire Storage proposes to expand its natural gas storage facilities 
at its existing Clear Creek Storage Field in Uinta County, Wyoming in 
order to increase the certificated gas capacities from 4.0 billion 
cubic feet (Bcf) to 20 Bcf, and increase the maximum daily injection 
and withdrawal capacities from 35 million cubic feet (MMcf) and 50 MMcf 
per day, to 350 MMcf and 500 MMcf per day, respectively. Spire Storage 
further proposes to construct pipeline connections north to the Canyon 
Creek Plant, south to the Kern River Gas Transmission mainline, and 
reconnect with the Questar Pipeline at the Clear Creek Plant. According 
to Spire Storage, the purpose of this project is to increase storage 
capacity and enhance operational capabilities to satisfy market demand 
for natural gas services in the Western United States.
    The Clear Creek Expansion Project would consist of the following 
facilities:
     Four compressor units at the Clear Creek Plant;
     a tank storage and natural gas liquids fueling equipment 
facility on an existing pad;
     11 new injection/withdrawal wells, one new water disposal 
well, and associated lines;
     approximately 10.6 miles of 20-inch-diameter pipeline;
     approximately 3.5 miles of 4,160-volt powerline; and
     other related appurtenances.

[[Page 73034]]

    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary''. For instructions on 
connecting to eLibrary, refer to the last page of this notice. At 
this time, the Commission has suspended access to the Commission's 
Public Reference Room due to the proclamation declaring a National 
Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact 
FERC at [email protected] or call toll free, (886) 208-3676 
or TTY (202) 502-8659.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 249.0 
acres of land for the aboveground facilities and the pipeline. 
Following construction, Spire Storage would maintain about 128.1 acres 
for permanent operation of the project's facilities; the remaining 
acreage would be restored and revert to former uses.

NEPA Process and the Environmental Document

    Any environmental document issued by the Commission will discuss 
impacts that could occur as a result of the construction and operation 
of the proposed project under the relevant general resource areas:
     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise; and
     reliability and safety.
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project and make recommendations on 
how to lessen or avoid impacts on the various resource areas. Your 
comments will help Commission staff identify and focus on the issues 
that might have an effect on the human environment and potentially 
eliminate others from further study and discussion in the environmental 
document.
    Following this scoping period, Commission staff will determine 
whether to prepare an Environmental Assessment (EA) or an Environmental 
Impact Statement (EIS). The EA or the EIS will present Commission 
staff's independent analysis of the issues. If Commission staff 
prepares an EA, a Notice of Schedule for the Preparation of an 
Environmental Assessment will be issued. The EA may be issued for an 
allotted public comment period. The Commission would consider timely 
comments on the EA before making its decision regarding the proposed 
project. If Commission staff prepares an EIS, a Notice of Intent to 
Prepare an EIS/Notice of Schedule will be issued, which will open up an 
additional comment period. Staff will then prepare a draft EIS which 
will be issued for public comment. Commission staff will consider all 
timely comments received during the comment period on the draft EIS and 
revise the document, as necessary, before issuing a final EIS. Any EA 
or draft and final EIS will be available in electronic format in the 
public record through eLibrary \2\ and the Commission's natural gas 
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you 
will receive instant email notification when the environmental document 
is issued.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the environmental document.\3\ Agencies that would like 
to request cooperating agency status should follow the instructions for 
filing comments provided under the Public Participation section of this 
notice. Currently, the Bureau of Land Management has expressed its 
intention to participate as a cooperating agency in the preparation of 
the environmental document to satisfy its NEPA responsibilities related 
to this project.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Section 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office(s), 
and to solicit their views and those of other government agencies, 
interested Indian tribes, and the public on the project's potential 
effects on historic properties.\4\ The environmental document for this 
project will document findings on the impacts on historic properties 
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project and includes a mailing address with their 
comments. Commission staff will update the environmental mailing list 
as the analysis proceeds to ensure that Commission notices related to 
this environmental review are sent to all individuals, organizations, 
and government entities interested in and/or potentially affected by 
the proposed project.
    If you need to make changes to your name/address, or if you would 
like to remove your name from the mailing list, please return the 
attached ``Mailing List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
in the ``Docket Number'' field. Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at [email protected] or (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of all formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at https://w.ferc.gov/news-events/events along with 
other related information.

    Dated: November 9, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-25209 Filed 11-13-20; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.