Notice of Final Federal Agency Actions on I-5 Rose Quarter Improvement Project in City of Portland, Multnomah County, Oregon, 71136 [2020-24596]
Download as PDF
71136
Federal Register / Vol. 85, No. 216 / Friday, November 6, 2020 / Notices
guidance that is advisory and may
include recommended actions or
inspections with a request for voluntary
reporting of inspection results.
Respondents: Respondents may
include mechanics, type clubs, owners
and operators of aircraft.
Frequency: Information is collected as
needed to acquire additional
information on a specific condition.
Estimated Average Burden per
Response: 5 minutes.
Estimated Total Annual Burden: 447
hours.
Notice is
hereby given that FHWA has taken final
agency action subject to 23 U.S.C.
139(l)(1) by issuing approvals for the
following highway project in the State
of Oregon. The I–5 Rose Quarter
Improvement Project proposed to
construct auxiliary lanes on Interstate 5
for 1.5 miles in Portland, Oregon, along
with associated surface street
improvements. The purpose of the
Project is to improve the safety and
operations on Interstate 5 (I–5) between
Interstate 405 (I–405) and Interstate 84
Issued in Washington, DC.
(I–84), of the Broadway/Weidler
interchange, and on adjacent surface
Joy Wolf,
streets in the vicinity of the Broadway/
Management & Program Analyst for
Weidler interchange, and to enhance
Regulatory and Guidance Processing.
multimodal facilities in the Project Area
[FR Doc. 2020–24716 Filed 11–5–20; 8:45 am]
[Federal ID No. S001(483)]. The actions
BILLING CODE 4910–13–P
by the agencies, and the laws under
which such actions were taken, are
DEPARTMENT OF TRANSPORTATION described in the Environmental
Assessment (EA) and Revised
Federal Highway Administration
Environmental Assessment (REA) and
Finding of No Significant Impact
Notice of Final Federal Agency Actions (FONSI) for the project, approved on
on I–5 Rose Quarter Improvement
October 30, 2020. The I–5 Rose Quarter
Project in City of Portland, Multnomah
Improvement Project REA/FONSI and
County, Oregon
other project records are available by
contacting FHWA or Oregon DOT at the
AGENCY: Federal Highway
addresses provided above. The REA/
Administration (FHWA), DOT.
FONSI can be viewed and downloaded
ACTION: Notice of Limitation on Claims
from the project website at https://
for Judicial Review of Actions by
www.i5rosequarter.org/ or obtained
FHWA.
from any contact listed above. This
SUMMARY: This notice announces actions notice applies to all Federal agency
taken by the FHWA that are final. The
decisions that are final as of the
actions relate to a proposed highway
issuance date of this notice and all laws
project, I–5 Rose Quarter Improvement
under which such actions were taken,
Project, in the City of Portland,
including but not limited to:
Multnomah County, Oregon. Those
1. General: National Environmental
actions grant approvals for the project.
Policy Act (NEPA) [42 U.S.C. 4321–
DATES: By this notice, FHWA is advising 4351]; Federal-Aid Highway Act [23
U.S.C. 109 and 23 U.S.C. 128].
the public of final agency actions
2. Air: Clean Air Act [42 U.S.C. 7401–
subject to 23 U.S.C. 139(l)(1). A claim
7671q].
seeking judicial review of the Federal
agency actions on the highway project
3. Land: Section 4(f) of the
will be barred unless the claim is filed
Department of Transportation Act of
on or before April 5, 2021. If the Federal 1966 [49 U.S.C. 303; 23 U.S.C. 138];
law that authorizes judicial review of a
Landscaping and Scenic Enhancement
claim provides a time period of less
(Wildflowers) [23 U.S.C. 319].
than 150 days for filing such claim, then
4. Wildlife: Endangered Species Act
that shorter time period still applies.
[16 U.S.C. 1531–1544 and Section
1536]; Marine Mammal Protection Act
FOR FURTHER INFORMATION CONTACT:
[16 U.S.C. 1361–1423h]; Fish and
Emily Cline, Environmental Program
Wildlife Coordination Act [16 U.S.C.
Manager, FHWA Oregon Division
661–667d]; Migratory Bird Treaty Act
Office, 530 Center St. NE, Salem, OR
[16 U.S.C. 703–712].
97301, Office Hours: 7:30 a.m. to 4:00
5. Historic and Cultural Resources:
p.m., Office Phone: 503–316–2547,
Section 106 of the National Historic
Email: Emily.cline@dot.gov. You may
Preservation Act of 1966, as amended
also contact Megan Channell, Rose
[54 U.S.C. 306108]; Archeological
Quarter Project Director, ODOT Region
Resources Protection Act of 1977 [54
1, 123 NW Flanders St., Portland, OR
U.S.C. 312501–312508]; Native
97209, Office Phone: (971) 233–6510,
American Grave Protection and
Office Hours: 8:00 a.m.–5:00 p.m.,
Repatriation Act (NAGPRA) [25 U.S.C.
Email: Megan.CHANNELL@
3001–3013].
odot.state.or.us.
VerDate Sep<11>2014
19:00 Nov 05, 2020
Jkt 253001
SUPPLEMENTARY INFORMATION:
PO 00000
Frm 00090
Fmt 4703
Sfmt 9990
6. Historic and Cultural Resources:
Section 106 of the National Historic
Preservation Act of 1966, as amended
[54 U.S.C. 306108]; Archeological
Resources Protection Act of 1977 [54
U.S.C. 312501–312508]; Native
American Grave Protection and
Repatriation Act (NAGPRA) [25 U.S.C.
3001–3013].
7. Social and Economic: American
Indian Religious Freedom Act [42 U.S.C.
1996]; Farmland Protection Policy Act
(FPPA) [7 U.S.C. 4201–4209].
8. Wetlands and Water Resources:
Clean Water Act (Section 404, Section
401, Section 319) [33 U.S.C. 1251–
1387]; Land and Water Conservation
Fund (LWCF) [16 U.S.C. 4601–4604];
Safe Drinking Water Act (SDWA) [42
U.S.C. 300f–300j–26]; Rivers and
Harbors Act of 1899 [33 U.S.C. 401–
406]; Wild and Scenic Rivers Act [16
U.S.C. 1271–1287]; Emergency
Wetlands Resources Act, [16 U.S.C.
3901, 3921]; Wetlands Mitigation [23
U.S.C. 119(g) and 133(b)(14)]; Flood
Disaster Protection Act, 42 U.S.C. 4012a,
4106.
9. Executive Orders: E.O. 11990
Protection of Wetlands; E.O. 11988
Floodplain Management; E.O. 12898,
Federal Actions to Address
Environmental Justice in Minority
Populations and Low Income
Populations; E.O. 11593 Protection and
Enhancement of Cultural Resources;
E.O. 13007 Indian Sacred Sites; E.O.
13287 Preserve America; E.O. 13175
Consultation and Coordination with
Indian Tribal Governments; E.O. 11514
Protection and Enhancement of
Environmental Quality; E.O. 13112
Invasive Species.
(Catalog of Federal Domestic Assistance
Program Number 20.205, Highway Planning
and Construction. The regulations
implementing Executive Order 12372
regarding intergovernmental consultation on
Federal programs and activities apply to this
program.)
Authority: 23 U.S.C. 139(l)(1).
Issued on: November 2, 2020.
Phillip A. Ditzler,
Division Administrator, Salem, Oregon.
[FR Doc. 2020–24596 Filed 11–5–20; 8:45 am]
BILLING CODE 4910–RY–P
E:\FR\FM\06NON1.SGM
06NON1
Agencies
[Federal Register Volume 85, Number 216 (Friday, November 6, 2020)]
[Notices]
[Page 71136]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-24596]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Notice of Final Federal Agency Actions on I-5 Rose Quarter
Improvement Project in City of Portland, Multnomah County, Oregon
AGENCY: Federal Highway Administration (FHWA), DOT.
ACTION: Notice of Limitation on Claims for Judicial Review of Actions
by FHWA.
-----------------------------------------------------------------------
SUMMARY: This notice announces actions taken by the FHWA that are
final. The actions relate to a proposed highway project, I-5 Rose
Quarter Improvement Project, in the City of Portland, Multnomah County,
Oregon. Those actions grant approvals for the project.
DATES: By this notice, FHWA is advising the public of final agency
actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review
of the Federal agency actions on the highway project will be barred
unless the claim is filed on or before April 5, 2021. If the Federal
law that authorizes judicial review of a claim provides a time period
of less than 150 days for filing such claim, then that shorter time
period still applies.
FOR FURTHER INFORMATION CONTACT: Emily Cline, Environmental Program
Manager, FHWA Oregon Division Office, 530 Center St. NE, Salem, OR
97301, Office Hours: 7:30 a.m. to 4:00 p.m., Office Phone: 503-316-
2547, Email: [email protected]. You may also contact Megan Channell,
Rose Quarter Project Director, ODOT Region 1, 123 NW Flanders St.,
Portland, OR 97209, Office Phone: (971) 233-6510, Office Hours: 8:00
a.m.-5:00 p.m., Email: [email protected].
SUPPLEMENTARY INFORMATION: Notice is hereby given that FHWA has taken
final agency action subject to 23 U.S.C. 139(l)(1) by issuing approvals
for the following highway project in the State of Oregon. The I-5 Rose
Quarter Improvement Project proposed to construct auxiliary lanes on
Interstate 5 for 1.5 miles in Portland, Oregon, along with associated
surface street improvements. The purpose of the Project is to improve
the safety and operations on Interstate 5 (I-5) between Interstate 405
(I-405) and Interstate 84 (I-84), of the Broadway/Weidler interchange,
and on adjacent surface streets in the vicinity of the Broadway/Weidler
interchange, and to enhance multimodal facilities in the Project Area
[Federal ID No. S001(483)]. The actions by the agencies, and the laws
under which such actions were taken, are described in the Environmental
Assessment (EA) and Revised Environmental Assessment (REA) and Finding
of No Significant Impact (FONSI) for the project, approved on October
30, 2020. The I-5 Rose Quarter Improvement Project REA/FONSI and other
project records are available by contacting FHWA or Oregon DOT at the
addresses provided above. The REA/FONSI can be viewed and downloaded
from the project website at https://www.i5rosequarter.org/ or obtained
from any contact listed above. This notice applies to all Federal
agency decisions that are final as of the issuance date of this notice
and all laws under which such actions were taken, including but not
limited to:
1. General: National Environmental Policy Act (NEPA) [42 U.S.C.
4321-4351]; Federal-Aid Highway Act [23 U.S.C. 109 and 23 U.S.C. 128].
2. Air: Clean Air Act [42 U.S.C. 7401-7671q].
3. Land: Section 4(f) of the Department of Transportation Act of
1966 [49 U.S.C. 303; 23 U.S.C. 138]; Landscaping and Scenic Enhancement
(Wildflowers) [23 U.S.C. 319].
4. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and
Section 1536]; Marine Mammal Protection Act [16 U.S.C. 1361-1423h];
Fish and Wildlife Coordination Act [16 U.S.C. 661-667d]; Migratory Bird
Treaty Act [16 U.S.C. 703-712].
5. Historic and Cultural Resources: Section 106 of the National
Historic Preservation Act of 1966, as amended [54 U.S.C. 306108];
Archeological Resources Protection Act of 1977 [54 U.S.C. 312501-
312508]; Native American Grave Protection and Repatriation Act (NAGPRA)
[25 U.S.C. 3001-3013].
6. Historic and Cultural Resources: Section 106 of the National
Historic Preservation Act of 1966, as amended [54 U.S.C. 306108];
Archeological Resources Protection Act of 1977 [54 U.S.C. 312501-
312508]; Native American Grave Protection and Repatriation Act (NAGPRA)
[25 U.S.C. 3001-3013].
7. Social and Economic: American Indian Religious Freedom Act [42
U.S.C. 1996]; Farmland Protection Policy Act (FPPA) [7 U.S.C. 4201-
4209].
8. Wetlands and Water Resources: Clean Water Act (Section 404,
Section 401, Section 319) [33 U.S.C. 1251-1387]; Land and Water
Conservation Fund (LWCF) [16 U.S.C. 4601-4604]; Safe Drinking Water Act
(SDWA) [42 U.S.C. 300f-300j-26]; Rivers and Harbors Act of 1899 [33
U.S.C. 401-406]; Wild and Scenic Rivers Act [16 U.S.C. 1271-1287];
Emergency Wetlands Resources Act, [16 U.S.C. 3901, 3921]; Wetlands
Mitigation [23 U.S.C. 119(g) and 133(b)(14)]; Flood Disaster Protection
Act, 42 U.S.C. 4012a, 4106.
9. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988
Floodplain Management; E.O. 12898, Federal Actions to Address
Environmental Justice in Minority Populations and Low Income
Populations; E.O. 11593 Protection and Enhancement of Cultural
Resources; E.O. 13007 Indian Sacred Sites; E.O. 13287 Preserve America;
E.O. 13175 Consultation and Coordination with Indian Tribal
Governments; E.O. 11514 Protection and Enhancement of Environmental
Quality; E.O. 13112 Invasive Species.
(Catalog of Federal Domestic Assistance Program Number 20.205,
Highway Planning and Construction. The regulations implementing
Executive Order 12372 regarding intergovernmental consultation on
Federal programs and activities apply to this program.)
Authority: 23 U.S.C. 139(l)(1).
Issued on: November 2, 2020.
Phillip A. Ditzler,
Division Administrator, Salem, Oregon.
[FR Doc. 2020-24596 Filed 11-5-20; 8:45 am]