Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests; Dominion Energy South Carolina, Inc., 68318-68319 [2020-23867]
Download as PDF
68318
Federal Register / Vol. 85, No. 209 / Wednesday, October 28, 2020 / Notices
at any time if it determines the factual
basis underlying the petition for waiver
is incorrect, or the results from the
alternate test procedure are
unrepresentative of a basic model’s true
energy consumption characteristics. 10
CFR 431.401(k)(1). Likewise, Hoshizaki
may request that DOE rescind or modify
the waiver if Hoshizaki discovers an
error in the information provided to
DOE as part of its petition, determines
that the waiver is no longer needed, or
for other appropriate reasons. 10 CFR
431.401(k)(2).
(6) Hoshizaki remains obligated to
fulfill any certification requirements set
forth at 10 CFR part 429.
Signed in Washington, DC, on October 22,
2020.
Alexander N. Fitzsimmons,
Deputy Assistant Secretary for Energy
Efficiency, Energy Efficiency and Renewable
Energy.
[FR Doc. 2020–23818 Filed 10–27–20; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 516–505]
jbell on DSKJLSW7X2PROD with NOTICES
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests;
Dominion Energy South Carolina, Inc.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-project use
of project lands and water.
b. Project No: 516–505.
c. Date Filed: June 12, 2020 and
supplemented on September 17, 2020.
d. Applicant: Dominion Energy South
Carolina, Inc.
e. Name of Project: Saluda
Hydroelectric Project.
f. Location: Lake Murray of the Saluda
Hydroelectric Project located in
Lexington, Newberry, Richland and
Saluda counties, South Carolina.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Raymond
Ammarell, Manager, Dominion Energy
South Carolina, Inc., 220 Operation
Way, MC A221, Cayce, South Carolina,
29033; phone (803) 217–7322.
i. FERC Contact: Ms. Joy Kurtz, 202–
502–6760, joy.kurtz@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
November 21, 2020.
The Commission strongly encourages
electronic filing. Please file comments,
VerDate Sep<11>2014
18:29 Oct 27, 2020
Jkt 253001
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include the
docket number P–516–505. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
licensee requests Commission approval
to grant the Joint Municipal Water and
Sewer Commission (JMWSC)
permission to use project lands and
water within the project boundary on
Lake Murray for the construction and
operation of a component of a raw water
intake facility (facility) to provide
public drinking water. The component
of the facility proposed to be
constructed within the project boundary
is a single screened 84′ intake pipe that
would extend from the shoreline of Lake
Murray into Lake Murray itself. The
remaining components of the facility
would be constructed outside of the
project boundary. Once constructed and
operational, the facility would initially
withdraw 10 million gallons per day
(MGD) from Lake Murray. Subsequently,
JMWSC would increase withdrawals
made by the facility in 10 MGD
increments over time, as needed, up to
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
a maximum of 50 MGD, as water
demands dictate.
l. Locations of the Application: In
addition to publishing the full text of
this document in the Federal Register,
the Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
Home Page (https://ferc.gov) using the
eLibrary link. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact the Federal
Energy Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title COMMENTS, PROTEST,
or MOTION TO INTERVENE as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person commenting,
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, motions to intervene, or
protests must set forth their evidentiary
basis. Any filing made by an intervenor
must be accompanied by proof of
service on all persons listed in the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 385.2010.
E:\FR\FM\28OCN1.SGM
28OCN1
Federal Register / Vol. 85, No. 209 / Wednesday, October 28, 2020 / Notices
Dated: October 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–23867 Filed 10–27–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
jbell on DSKJLSW7X2PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–11–000.
Applicants: AL Solar A, LLC, Five
Points Solar Park LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of AL Solar A,
LLC, et al.
Filed Date: 10/21/20.
Accession Number: 20201021–5148.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG21–11–000.
Applicants: Nutmeg Solar, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Nutmeg Solar, LLC.
Filed Date: 10/22/20.
Accession Number: 20201022–5078.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER19–5–005.
Applicants: Commonwealth Edison
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
ComEd submits Compliance Filing in
ER19–5 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5119.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–6–006.
Applicants: Delmarva Power & Light
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Delmarva submits Compliance Filing in
ER19–6 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5122.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–14–005.
Applicants: Baltimore Gas and
Electric Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: BGE
submits Compliance Filing in ER19–14
to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5132.
VerDate Sep<11>2014
18:29 Oct 27, 2020
Jkt 253001
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–18–005.
Applicants: Atlantic City Electric
Company, PJM Interconnection, L.L.C.
Description: Compliance filing: ACE
submits Compliance Filing in ER19–18
to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5125.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–1475–004.
Applicants: Potomac Electric Power
Company, PJM Interconnection, L.L.C.
Description: Compliance filing: Pepco
submits Compliance Filing in ER19–
1475 to be effective 6/1/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5081.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–1553–005.
Applicants: Southern California
Edison Company.
Description: Compliance filing:
Compliance Filing—Appendix XII
Stakeholder Review Process to be
effective 9/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5070.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–61–001.
Applicants: El Paso Electric Company.
Description: Compliance filing: WECC
Soft Cap Justification to be effective
N/A.
Filed Date: 10/21/20.
Accession Number: 20201021–5130.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–173–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: First
Revised ISA, Service Agreement No.
1504; Queue No. AE1–178 to be
effective 9/21/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5126.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–174–000.
Applicants: Kanstar Transmission,
LLC.
Description: Tariff Cancellation:
Cancellation of Kanstar Database to be
effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5000.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–175–000.
Applicants: Midwest Power
Transmission Arkansas, LLC.
Description: Tariff Cancellation:
Cancellation of Midwest Power
Transmission Ark. Database to be
effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5001.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–176–000.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
68319
Applicants: Golden Springs
Development Company LLC.
Description: Appeal for Relief from
Assessed Penalty of Electric of Golden
Springs Development Company LLC.
Filed Date: 10/19/20.
Accession Number: 20201019–5162.
Comments Due: 5 p.m. ET 11/9/20.
Docket Numbers: ER21–177–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Michigan Electric Transmission
Company.
Description: § 205(d) Rate Filing:
2020–10–22_SA 3132 METC-Wolverine
T–T 1st Rev Appendix to be effective
6/1/2018.
Filed Date: 10/22/20.
Accession Number: 20201022–5003.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–178–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Amendment to Southern’s Tariff Vol.
No. 4 to add JEA BAA Mitigation to be
effective 10/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5041.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–179–000.
Applicants: Deuel Harvest Wind
Energy LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff Filing
to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5047.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–180–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, Service Agreement No.
5814; Queue No. AD1–041 to be
effective 9/29/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5052.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–181–000.
Applicants: Contrail Wind Project,
LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5054.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–182–000.
Applicants: Crescent Wind LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff Filing
to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5056.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–183–000.
E:\FR\FM\28OCN1.SGM
28OCN1
Agencies
[Federal Register Volume 85, Number 209 (Wednesday, October 28, 2020)]
[Notices]
[Pages 68318-68319]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-23867]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 516-505]
Notice of Application Accepted for Filing and Soliciting
Comments, Motions To Intervene, and Protests; Dominion Energy South
Carolina, Inc.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Non-project use of project lands and water.
b. Project No: 516-505.
c. Date Filed: June 12, 2020 and supplemented on September 17,
2020.
d. Applicant: Dominion Energy South Carolina, Inc.
e. Name of Project: Saluda Hydroelectric Project.
f. Location: Lake Murray of the Saluda Hydroelectric Project
located in Lexington, Newberry, Richland and Saluda counties, South
Carolina.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Raymond Ammarell, Manager, Dominion
Energy South Carolina, Inc., 220 Operation Way, MC A221, Cayce, South
Carolina, 29033; phone (803) 217-7322.
i. FERC Contact: Ms. Joy Kurtz, 202-502-6760, [email protected].
j. Deadline for filing comments, motions to intervene, and
protests: November 21, 2020.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include the docket number P-516-505. Comments emailed to Commission
staff are not considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: The licensee requests Commission
approval to grant the Joint Municipal Water and Sewer Commission
(JMWSC) permission to use project lands and water within the project
boundary on Lake Murray for the construction and operation of a
component of a raw water intake facility (facility) to provide public
drinking water. The component of the facility proposed to be
constructed within the project boundary is a single screened 84' intake
pipe that would extend from the shoreline of Lake Murray into Lake
Murray itself. The remaining components of the facility would be
constructed outside of the project boundary. Once constructed and
operational, the facility would initially withdraw 10 million gallons
per day (MGD) from Lake Murray. Subsequently, JMWSC would increase
withdrawals made by the facility in 10 MGD increments over time, as
needed, up to a maximum of 50 MGD, as water demands dictate.
l. Locations of the Application: In addition to publishing the full
text of this document in the Federal Register, the Commission provides
all interested persons an opportunity to view and/or print the contents
of this document via the internet through the Commission's Home Page
(https://ferc.gov) using the eLibrary link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. At this time, the Commission has suspended access to the
Commission's Public Reference Room, due to the proclamation declaring a
National Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact the
Federal Energy Regulatory Commission at [email protected] or
call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title COMMENTS, PROTEST, or MOTION TO INTERVENE as
applicable; (2) set forth in the heading the name of the applicant and
the project number of the application to which the filing responds; (3)
furnish the name, address, and telephone number of the person
commenting, protesting or intervening; and (4) otherwise comply with
the requirements of 18 CFR 385.2001 through 385.2005. All comments,
motions to intervene, or protests must set forth their evidentiary
basis. Any filing made by an intervenor must be accompanied by proof of
service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 385.2010.
[[Page 68319]]
Dated: October 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-23867 Filed 10-27-20; 8:45 am]