Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–11–000.
Applicants: AL Solar A, LLC, Five
Points Solar Park LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of AL Solar A,
LLC, et al.
Filed Date: 10/21/20.
Accession Number: 20201021–5148.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG21–11–000.
Applicants: Nutmeg Solar, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Nutmeg Solar, LLC.
Filed Date: 10/22/20.
Accession Number: 20201022–5078.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER19–5–005.
Applicants: Commonwealth Edison
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
ComEd submits Compliance Filing in
ER19–5 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5119.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–6–006.
Applicants: Delmarva Power & Light
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Delmarva submits Compliance Filing in
ER19–6 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5122.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–14–005.
Applicants: Baltimore Gas and
Electric Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: BGE
submits Compliance Filing in ER19–14
to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5132.
VerDate Sep<11>2014
18:29 Oct 27, 2020
Jkt 253001
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–18–005.
Applicants: Atlantic City Electric
Company, PJM Interconnection, L.L.C.
Description: Compliance filing: ACE
submits Compliance Filing in ER19–18
to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5125.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–1475–004.
Applicants: Potomac Electric Power
Company, PJM Interconnection, L.L.C.
Description: Compliance filing: Pepco
submits Compliance Filing in ER19–
1475 to be effective 6/1/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5081.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19–1553–005.
Applicants: Southern California
Edison Company.
Description: Compliance filing:
Compliance Filing—Appendix XII
Stakeholder Review Process to be
effective 9/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5070.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–61–001.
Applicants: El Paso Electric Company.
Description: Compliance filing: WECC
Soft Cap Justification to be effective
N/A.
Filed Date: 10/21/20.
Accession Number: 20201021–5130.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–173–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: First
Revised ISA, Service Agreement No.
1504; Queue No. AE1–178 to be
effective 9/21/2020.
Filed Date: 10/21/20.
Accession Number: 20201021–5126.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–174–000.
Applicants: Kanstar Transmission,
LLC.
Description: Tariff Cancellation:
Cancellation of Kanstar Database to be
effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5000.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–175–000.
Applicants: Midwest Power
Transmission Arkansas, LLC.
Description: Tariff Cancellation:
Cancellation of Midwest Power
Transmission Ark. Database to be
effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5001.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–176–000.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
68319
Applicants: Golden Springs
Development Company LLC.
Description: Appeal for Relief from
Assessed Penalty of Electric of Golden
Springs Development Company LLC.
Filed Date: 10/19/20.
Accession Number: 20201019–5162.
Comments Due: 5 p.m. ET 11/9/20.
Docket Numbers: ER21–177–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Michigan Electric Transmission
Company.
Description: § 205(d) Rate Filing:
2020–10–22_SA 3132 METC-Wolverine
T–T 1st Rev Appendix to be effective
6/1/2018.
Filed Date: 10/22/20.
Accession Number: 20201022–5003.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–178–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Amendment to Southern’s Tariff Vol.
No. 4 to add JEA BAA Mitigation to be
effective 10/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5041.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–179–000.
Applicants: Deuel Harvest Wind
Energy LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff Filing
to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5047.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–180–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, Service Agreement No.
5814; Queue No. AD1–041 to be
effective 9/29/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5052.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–181–000.
Applicants: Contrail Wind Project,
LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5054.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–182–000.
Applicants: Crescent Wind LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff Filing
to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5056.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–183–000.
E:\FR\FM\28OCN1.SGM
28OCN1
jbell on DSKJLSW7X2PROD with NOTICES
68320
Federal Register / Vol. 85, No. 209 / Wednesday, October 28, 2020 / Notices
Applicants: Nutmeg Solar, LLC.
Description: Baseline eTariff Filing:
Nutmeg Solar, LLC Application for MBR
Authority to be effective 11/15/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5062.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–184–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Amendment to Southern’s Tariff Vol.
No. 4 to remove SCEG BAA Mitigation
to be effective 12/31/9998.
Filed Date: 10/22/20.
Accession Number: 20201022–5064.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–185–000.
Applicants: Southwestern Electric
Power Company.
Description: § 205(d) Rate Filing:
SWEPCO–ETEC Deep East Loop
Contracting Services Agreement—
Amended to be effective 10/1/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5066.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21–186–000.
Applicants: Tampa Electric Company.
Description: § 205(d) Rate Filing:
Third Revised Rate Schedule FERC No.
7—Amendment to Exhibit A to be
effective 10/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022–5080.
Comments Due: 5 p.m. ET 11/12/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: October 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–23862 Filed 10–27–20; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
18:29 Oct 27, 2020
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–6–000]
RH energytrans, LLC; Notice of
Request for Extension of Time
Take notice that on October 19, 2020,
RH energytrans, LLC (RH) requested that
the Federal Energy Regulatory
Commission (Commission) grant an
extension of time, until December 7,
2022, to complete construction of, and
place into service, its Meadville and
County Line compressor stations in
Crawford and Erie Counties,
Pennsylvania as authorized in the
December 7, 2018 Order Issuing
Certificate (Certificate Order).1 Ordering
Paragraph B(1) of the Certificate Order
required RH to complete the
construction of the proposed Risberg
Line Project facilities 2 and make them
available for service within two years
from issuance, or by December 7, 2020.3
On November 22, 2019, the
Commission granted RH partial
authorization to place into service the
pipeline facilities associated with the
Risberg Line Project,4 and subsequently,
on December 1, 2019, RH placed those
facilities into service.5 RH states that it
has experienced construction delays
due to winter weather, the dissolution
of one of its pipeline contractors, and
delays resulting from COVID–19
pandemic restrictions. As a result, RH
now requests an additional two years, or
until December 7, 2022, to complete the
authorized construction at the
Meadville and County Line compressor
stations and make them available for
service.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on RH’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
1 RH energytrans, LLC, 165 FERC 61,218 (2018)
(Certificate Order).
2 The Risberg Line Project consists of the
conversion of 31.6 miles of existing 8-inch and 12inch natural gas gathering pipeline to transmission
service, construction of 28.3 miles of new 12-inch
pipeline, conversion of the existing Countyline
Compressor station from gathering to transmission
service, and construction of a new compressor
station at Meadville, PA.
3 Id. at ordering para. (B)(1).
4 RH energytrans, LLC, Docket No. CP18–6–000,
Partial Authorization to Commence Service
(November 22, 2019).
5 The only authorized facilities not placed into
service at that time were the two compressor
stations, and the approval was conditioned on RH’s
commitment to finalize restoration of the disturbed
right-of -way in the spring/summer of 2020.
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).6
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,7 the Commission will aim to
issue an order acting on the request
within 45 days.8 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.9 The Commission will not
consider arguments that re-litigate the
issuance of the Certificate Order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.10 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.11 The OEP Director, or his or
her designee, will act on those extension
requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the eLibrary link. Enter
the docket number excluding the last
three digits in the docket number field
to access the document. At this time, the
Commission has suspended access to
the Commission’s Public Reference
Room, due to the proclamation
6 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC 61,144, at P 39 (2020).
7 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2020).
8 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
9 Id. P 40.
10 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
11 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
E:\FR\FM\28OCN1.SGM
28OCN1
Agencies
[Federal Register Volume 85, Number 209 (Wednesday, October 28, 2020)]
[Notices]
[Pages 68319-68320]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-23862]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC21-11-000.
Applicants: AL Solar A, LLC, Five Points Solar Park LLC.
Description: Application for Authorization Under Section 203 of the
Federal Power Act, et al. of AL Solar A, LLC, et al.
Filed Date: 10/21/20.
Accession Number: 20201021-5148.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG21-11-000.
Applicants: Nutmeg Solar, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Nutmeg Solar, LLC.
Filed Date: 10/22/20.
Accession Number: 20201022-5078.
Comments Due: 5 p.m. ET 11/12/20.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER19-5-005.
Applicants: Commonwealth Edison Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: ComEd submits Compliance Filing in
ER19-5 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021-5119.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19-6-006.
Applicants: Delmarva Power & Light Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: Delmarva submits Compliance Filing
in ER19-6 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021-5122.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19-14-005.
Applicants: Baltimore Gas and Electric Company, PJM
Interconnection, L.L.C.
Description: Compliance filing: BGE submits Compliance Filing in
ER19-14 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021-5132.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19-18-005.
Applicants: Atlantic City Electric Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: ACE submits Compliance Filing in
ER19-18 to be effective 6/1/2020.
Filed Date: 10/21/20.
Accession Number: 20201021-5125.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19-1475-004.
Applicants: Potomac Electric Power Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: Pepco submits Compliance Filing in
ER19-1475 to be effective 6/1/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5081.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER19-1553-005.
Applicants: Southern California Edison Company.
Description: Compliance filing: Compliance Filing--Appendix XII
Stakeholder Review Process to be effective 9/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5070.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-61-001.
Applicants: El Paso Electric Company.
Description: Compliance filing: WECC Soft Cap Justification to be
effective N/A.
Filed Date: 10/21/20.
Accession Number: 20201021-5130.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-173-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: First Revised ISA, Service
Agreement No. 1504; Queue No. AE1-178 to be effective 9/21/2020.
Filed Date: 10/21/20.
Accession Number: 20201021-5126.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-174-000.
Applicants: Kanstar Transmission, LLC.
Description: Tariff Cancellation: Cancellation of Kanstar Database
to be effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5000.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-175-000.
Applicants: Midwest Power Transmission Arkansas, LLC.
Description: Tariff Cancellation: Cancellation of Midwest Power
Transmission Ark. Database to be effective 10/31/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5001.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-176-000.
Applicants: Golden Springs Development Company LLC.
Description: Appeal for Relief from Assessed Penalty of Electric of
Golden Springs Development Company LLC.
Filed Date: 10/19/20.
Accession Number: 20201019-5162.
Comments Due: 5 p.m. ET 11/9/20.
Docket Numbers: ER21-177-000.
Applicants: Midcontinent Independent System Operator, Inc.,
Michigan Electric Transmission Company.
Description: Sec. 205(d) Rate Filing: 2020-10-22_SA 3132 METC-
Wolverine T-T 1st Rev Appendix to be effective 6/1/2018.
Filed Date: 10/22/20.
Accession Number: 20201022-5003.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-178-000.
Applicants: Alabama Power Company.
Description: Sec. 205(d) Rate Filing: Amendment to Southern's
Tariff Vol. No. 4 to add JEA BAA Mitigation to be effective 10/23/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5041.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-179-000.
Applicants: Deuel Harvest Wind Energy LLC.
Description: Sec. 205(d) Rate Filing: Revised Market-Based Rate
Tariff Filing to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5047.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-180-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original ISA, Service
Agreement No. 5814; Queue No. AD1-041 to be effective 9/29/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5052.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-181-000.
Applicants: Contrail Wind Project, LLC.
Description: Sec. 205(d) Rate Filing: Revised Market-Based Rate
Tariff to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5054.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-182-000.
Applicants: Crescent Wind LLC.
Description: Sec. 205(d) Rate Filing: Revised Market-Based Rate
Tariff Filing to be effective 12/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5056.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-183-000.
[[Page 68320]]
Applicants: Nutmeg Solar, LLC.
Description: Baseline eTariff Filing: Nutmeg Solar, LLC Application
for MBR Authority to be effective 11/15/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5062.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-184-000.
Applicants: Alabama Power Company.
Description: Sec. 205(d) Rate Filing: Amendment to Southern's
Tariff Vol. No. 4 to remove SCEG BAA Mitigation to be effective 12/31/
9998.
Filed Date: 10/22/20.
Accession Number: 20201022-5064.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-185-000.
Applicants: Southwestern Electric Power Company.
Description: Sec. 205(d) Rate Filing: SWEPCO-ETEC Deep East Loop
Contracting Services Agreement--Amended to be effective 10/1/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5066.
Comments Due: 5 p.m. ET 11/12/20.
Docket Numbers: ER21-186-000.
Applicants: Tampa Electric Company.
Description: Sec. 205(d) Rate Filing: Third Revised Rate Schedule
FERC No. 7--Amendment to Exhibit A to be effective 10/22/2020.
Filed Date: 10/22/20.
Accession Number: 20201022-5080.
Comments Due: 5 p.m. ET 11/12/20.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: October 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-23862 Filed 10-27-20; 8:45 am]
BILLING CODE 6717-01-P