Download as PDF 68322 Federal Register / Vol. 85, No. 209 / Wednesday, October 28, 2020 / Notices foot-wide, 35-foot-high concrete powerhouse that would include a new 999-kilowatt Kaplan turbine-generator unit; (6) an existing 45-foot-long concrete tailrace; (7) a new 0.06-milelong transmission line; and (8) appurtenant facilities. The estimated annual generation of the Elizabeth Webbings Falls Dam Project would be 6,500 megawatt-hours. Applicant Contact: Mr. Justin Bristol, Manager, One Drop Hydro, LLC, P.O. Box 2033, Kingston, Rhode Island 02881; phone: (401) 793–6041; email: jbristol@onedrophydro.com. FERC Contact: Taconya D. Goar; phone: (202) 502–8394; email: Taconya.Goar@ferc.gov. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–15041–000. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Enter the docket number (P– 15041) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: October 22, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–23870 Filed 10–27–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD20–18–000] Offshore Wind Integration in RTOs/ ISOs Supplemental Notice of Technical Conference As first announced in the Notice of Technical Conference issued in this proceeding on June 17, 2020, the Federal Energy Regulatory Commission (Commission) will convene a staff-led technical conference in the above referenced proceeding on Tuesday, October 27, 2020, from 9:00 a.m. to 4:30 p.m. (ET).1 The conference will be held virtually and will be webcast. Commissioners may attend and participate. This conference will consider whether and how existing regional transmission organization (RTO) and independent system operator (ISO) interconnection, merchant transmission and transmission planning frameworks can accommodate anticipated growth in offshore wind generation in an efficient or costeffective manner that safeguards open access transmission principles. The conference also will provide an opportunity for participants to discuss possible changes or improvements to the current regulatory frameworks that may accommodate such growth. Attached to this Supplemental Notice is an agenda for the technical conference, which includes the final conference program and speakers. We note that discussions at the conference may involve issues raised in proceedings that are currently pending before the Commission. These proceedings include, but are not limited to: Docket Nos. Constellation Mystic Power, LLC v. ISO New England Inc ........................................................................................................ jbell on DSKJLSW7X2PROD with NOTICES Midcontinent Independent System Operator, Inc ....................................................................................................................... Midcontinent Independent System Operator, Inc. and Southwest Power Pool, Inc .................................................................. Midcontinent Independent System Operator, Inc ....................................................................................................................... Midcontinent Independent System Operator, Inc ....................................................................................................................... New York Independent System Operator Inc ............................................................................................................................. PJM Interconnection, L.L.C ......................................................................................................................................................... PJM Interconnection, L.L.C. and Midcontinent Independent System Operator, Inc .................................................................. PJM Interconnection, L.L.C ......................................................................................................................................................... Southwest Power Pool, Inc ......................................................................................................................................................... Vineyard Wind LLC ..................................................................................................................................................................... There is no fee for attendance, and the conference is open for the public to attend via webcast. Information on this 1 18 technical conference, including a link to the webcast, will be posted on the conference’s event page on the Commission’s website (https:// www.ferc.gov/news-events/events/ technical-conference-regarding-offshore- CFR 2.1(a)(1)(xi) (2020). VerDate Sep<11>2014 18:29 Oct 27, 2020 Jkt 253001 PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 EL20–52–000 and EL20–52–001. ER20–940–002. ER20–943–002. ER20–942–002. ER20–2788–000. EL20–65–000. ER20–939–001. ER20–944–002. ER20–2308–000. ER20–945–001. ER19–570–000. E:\FR\FM\28OCN1.SGM 28OCN1 Federal Register / Vol. 85, No. 209 / Wednesday, October 28, 2020 / Notices wind-integration-rtosisos-docket-noad20) prior to the event. The conference will be transcribed. Transcripts of the conference will be available for a fee from Ace-Federal Reporters, Inc. (202– 347–3700). For more information about this technical conference, please contact: Sarah McKinley (Logistical Information), Office of External Affairs, (202) 502–8004, sarah.mckinley@ferc.gov David Rosner (Technical Information), Office of Energy Policy and Innovation, (202) 502–8479, david.rosner@ferc.gov Rishi Garg (Legal Information), Office of the General Counsel, (202) 502– 8667, rishi.garg@ferc.gov Dated: October 22, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–23860 Filed 10–27–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9985–033] jbell on DSKJLSW7X2PROD with NOTICES Rivers Electric Company, Inc.; Rivers Electric, LLC; Notice of Application for Transfer of License and Soliciting Comments, Motions To Intervene, and Protests On August 18, 2020, Rivers Electric, LLC (transferee) filed an application for an after-the-fact transfer of license of the Mill Pond Hydroelectric Project No. 9985. The project is located on Catskill Creek, Greene County, New York. The applicant seeks Commission approval to transfer the license for the Mill Pond Hydroelectric Project from Rivers Electric Company, Inc. (transferor) to the transferee. On June 26, 2020, Rivers Electric Company, Inc was merged into River Electric, LLC, as a result, Rivers Electric Company, Inc. is no longer active. Applicant’s Contacts: Mr. Matthew Wenger, CEO/COO, Rivers Electric, LLC, c/o Clear Energy Hydro LLC, 18 South Wilcox Street, Castle Rock, CO 80104, Phone: (303) 993–5438; Email: notices@ clearenergyhydro.com, and Mr. Paul V. Nolan, Esq., 5515 17th Street North, Arlington, VA 22205, Phone: (703) 534– 5509 (w), (703) 587–5895 (c), Email: pvnpvndiver@gmail.com. FERC Contact: Anumzziatta Purchiaroni, (202) 502–6191, anumzziatta.purchiaroni@ferc.gov. Deadline for filing comments, motions to intervene, and protests: 30 days from VerDate Sep<11>2014 18:29 Oct 27, 2020 Jkt 253001 the date that the Commission issues this notice. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via U.S. Postal Service must be addressed to, Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to, Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–9985–033. Comments emailed to Commission staff are not considered part of the Commission record. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Dated: October 22, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–23868 Filed 10–27–20; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 68323 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP15–115–000; CP15–115– 001] National Fuel Gas Supply Corporation and Empire Pipeline, Inc.; Notice of Request for Extension of Time Take notice that on October 16, 2020, National Fuel Gas Supply Corporation (National Fuel) and Empire Pipeline, Inc. (Empire) (collectively, Applicants) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time, until December 1, 2024, to complete construction of the Northern Access 2016 Project (Project) and make the Project available for service, as authorized in the February 3, 2017 Order Granting Abandonment and Issuing Certificates (Certificate Order).1 The Project consists of approximately 99 miles of new pipeline, primarily 24inches in diameter, to be constructed in McKean County, Pennsylvania, and Allegany, Cattaraugus, Erie, and Niagara Counties, New York; a new compressor station along Empire’s system in Niagara County, New York; and additional compression at National Fuel’s existing Porterville Compressor Station in Erie County, New York, as well as new pipeline interconnects and various auxiliary and appurtenant facilities. The Certificate Order required Applicants to complete construction of the Project facilities and make them available for service by February 3, 2019.2 In January 2019, the Commission granted Applicants’ request for a three-year extension, until February 3, 2022, to complete construction and place the Project facilities into service.3 Due to ongoing legal and regulatory delays, Applicants now request an additional two-year extension of time, until December 1, 2024, to complete construction of the Project and place it into service. This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on the extension motion may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the 1 National Fuel Gas Supply Corp. et al., 158 FERC 61,145 (2017) (Certificate Order), order on reh’g and motion for waiver determination under Section 401 of the Clean Water Act, 164 FERC 61,084 (2018). 2 Certificate Order, 158 FERC 61,145 at ordering para. (C)(1). 3 Letter Order to National Fuel Gas Supply Corp. and Empire Pipeline, Inc., Docket No. CP15–115– 000 (issued Jan. 31, 2019) (National Fuel Letter Order). E:\FR\FM\28OCN1.SGM 28OCN1

Agencies

[Federal Register Volume 85, Number 209 (Wednesday, October 28, 2020)]
[Notices]
[Pages 68322-68323]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-23860]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. AD20-18-000]


Offshore Wind Integration in RTOs/ISOs Supplemental Notice of 
Technical Conference

    As first announced in the Notice of Technical Conference issued in 
this proceeding on June 17, 2020, the Federal Energy Regulatory 
Commission (Commission) will convene a staff-led technical conference 
in the above referenced proceeding on Tuesday, October 27, 2020, from 
9:00 a.m. to 4:30 p.m. (ET).\1\ The conference will be held virtually 
and will be webcast. Commissioners may attend and participate. This 
conference will consider whether and how existing regional transmission 
organization (RTO) and independent system operator (ISO) 
interconnection, merchant transmission and transmission planning 
frameworks can accommodate anticipated growth in offshore wind 
generation in an efficient or cost-effective manner that safeguards 
open access transmission principles. The conference also will provide 
an opportunity for participants to discuss possible changes or 
improvements to the current regulatory frameworks that may accommodate 
such growth. Attached to this Supplemental Notice is an agenda for the 
technical conference, which includes the final conference program and 
speakers.
---------------------------------------------------------------------------

    \1\ 18 CFR 2.1(a)(1)(xi) (2020).
---------------------------------------------------------------------------

    We note that discussions at the conference may involve issues 
raised in proceedings that are currently pending before the Commission. 
These proceedings include, but are not limited to:

------------------------------------------------------------------------
                                                     Docket Nos.
------------------------------------------------------------------------
Constellation Mystic Power, LLC v. ISO New   EL20-52-000 and EL20-52-
 England Inc.                                 001.
Midcontinent Independent System Operator,    ER20-940-002.
 Inc.
Midcontinent Independent System Operator,    ER20-943-002.
 Inc. and Southwest Power Pool, Inc.
Midcontinent Independent System Operator,    ER20-942-002.
 Inc.
Midcontinent Independent System Operator,    ER20-2788-000.
 Inc.
New York Independent System Operator Inc...  EL20-65-000.
PJM Interconnection, L.L.C.................  ER20-939-001.
PJM Interconnection, L.L.C. and              ER20-944-002.
 Midcontinent Independent System Operator,
 Inc.
PJM Interconnection, L.L.C.................  ER20-2308-000.
Southwest Power Pool, Inc..................  ER20-945-001.
Vineyard Wind LLC..........................  ER19-570-000.
------------------------------------------------------------------------

    There is no fee for attendance, and the conference is open for the 
public to attend via webcast. Information on this technical conference, 
including a link to the webcast, will be posted on the conference's 
event page on the Commission's website (https://www.ferc.gov/news-
events/events/technical-conference-regarding-offshore-

[[Page 68323]]

wind-integration-rtosisos-docket-no-ad20) prior to the event. The 
conference will be transcribed. Transcripts of the conference will be 
available for a fee from Ace-Federal Reporters, Inc. (202-347-3700). 
For more information about this technical conference, please contact:

    Sarah McKinley (Logistical Information), Office of External 
Affairs, (202) 502-8004, [email protected]
    David Rosner (Technical Information), Office of Energy Policy and 
Innovation, (202) 502-8479, [email protected]
    Rishi Garg (Legal Information), Office of the General Counsel, 
(202) 502-8667, [email protected]

    Dated: October 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-23860 Filed 10-27-20; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.