DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
khammond on DSKJM1Z7X2PROD with NOTICES
September 30, 2020.
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Number: PR20–75–000.
Applicants: Mid Continent Market
Center, L.L.C.
Description: Tariff filing per
284.123(b)(1)+(g): MCMC 2020 Periodic
Rate Review to be effective 10/1/2020
under PR20–75.
Filed Date: 9/28/2020.
Accession Number: 202009285114.
Comments Due: 5 p.m. ET 10/19/
2020.
284.123(g) Protests Due: 5 p.m. ET 11/
27/2020.
Docket Numbers: RP20–1230–000.
Applicants: Tuscarora Gas
Transmission Company.
Description: Compliance filing 2020
Fuel and Line Loss Report.
Filed Date: 9/29/20.
Accession Number: 20200929–5041.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20–1231–000.
Applicants: Stagecoach Pipeline &
Storage Company LLC.
Description: § 4(d) Rate Filing:
Stagecoach Pipeline & Storage Company
LLC—Filing of Negotiated Rate
Agreement to be effective 11/1/2020.
Filed Date: 9/29/20.
Accession Number: 20200929–5073.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20–1232–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreement Update
(Conoco Oct 20) to be effective 10/1/
2020.
Filed Date: 9/29/20.
Accession Number: 20200929–5079.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20–1234–000.
Applicants: Southern Star Central Gas
Pipeline, Inc.
Description: § 4(d) Rate Filing: Vol. 2Negotiated Rate Agreements—Spotlight,
Tenaska, Conexus to be effective 9/29/
2020.
Filed Date: 9/29/20.
Accession Number: 20200929–5109.
VerDate Sep<11>2014
17:52 Oct 05, 2020
Jkt 253001
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20–1235–000.
Applicants: Algonquin Gas
Transmission, LLC.
Description: § 4(d) Rate Filing:
Negotiated Rates—Bay State to UGI
Releases to be effective 10/1/2020.
Filed Date: 9/29/20.
Accession Number: 20200929–5122.
Comments Due: 5 p.m. ET 10/13/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: September 30, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–490–000]
Columbia Gulf Transmission, LLC;
Notice of Schedule for Environmental
Review of the Mainline 300
Replacement Project
On June 30, 2020, Columbia Gulf
Transmission, LLC (Columbia Gulf)
filed an application in Docket No.
CP20–490–000 requesting a Certificate
of Public Convenience and Necessity,
pursuant to Sections 7(b) and 7(c) of the
Natural Gas Act, to abandon, replace,
and operate certain natural gas pipeline
facilities. The proposed project is
known as the Mainline 300
Replacement Project (Project) and
consists of the abandonment and
replacement of two segments of the 36inch-diameter Mainline 300 totaling
approximately 775 feet. The Project is
located in Menifee and Montgomery
Counties, Kentucky. Due to increased
Frm 00034
Fmt 4703
Sfmt 4703
population density in the area along
certain discrete sections of Mainline
300, Columbia Gulf is required,
pursuant to Part 192 of the U.S.
Department of Transportation
regulations to replace segments of its
existing Mainline 300 pipeline to meet
the Class 3 pipeline design
requirements.
On July 9, 2020, the Federal Energy
Regulatory Commission (Commission or
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
Schedule for Environmental Review
Issuance of EA—January 20, 2021
90-day Federal Authorization Decision
Deadline—April 20, 2021
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
[FR Doc. 2020–22037 Filed 10–5–20; 8:45 am]
PO 00000
63111
The Project would involve the
construction and operation of the
following facilities:
• Replacement of approximately 760
feet of existing 36-inch-diameter
pipeline, with approximately 760 feet of
new, 36-inch-diameter natural gas
transmission pipeline from Milepost
(MP) 6.8 to MP 6.9; and
• Replacement of approximately 15
feet of existing 36-inch-diameter
pipeline, with approximately 15 feet of
new, 36-inch-diameter natural gas
transmission pipeline from MP 6.9 to
MP 6.9.
Background
On July 31, 2020, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Mainline 300 Replacement
Project and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission did not
receive any comments.
E:\FR\FM\06OCN1.SGM
06OCN1
Agencies
[Federal Register Volume 85, Number 194 (Tuesday, October 6, 2020)]
[Notices]
[Page 63111]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-22037]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
September 30, 2020.
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Docket Number: PR20-75-000.
Applicants: Mid Continent Market Center, L.L.C.
Description: Tariff filing per 284.123(b)(1)+(g): MCMC 2020
Periodic Rate Review to be effective 10/1/2020 under PR20-75.
Filed Date: 9/28/2020.
Accession Number: 202009285114.
Comments Due: 5 p.m. ET 10/19/2020.
284.123(g) Protests Due: 5 p.m. ET 11/27/2020.
Docket Numbers: RP20-1230-000.
Applicants: Tuscarora Gas Transmission Company.
Description: Compliance filing 2020 Fuel and Line Loss Report.
Filed Date: 9/29/20.
Accession Number: 20200929-5041.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20-1231-000.
Applicants: Stagecoach Pipeline & Storage Company LLC.
Description: Sec. 4(d) Rate Filing: Stagecoach Pipeline & Storage
Company LLC--Filing of Negotiated Rate Agreement to be effective 11/1/
2020.
Filed Date: 9/29/20.
Accession Number: 20200929-5073.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20-1232-000.
Applicants: El Paso Natural Gas Company, L.L.C.
Description: Sec. 4(d) Rate Filing: Negotiated Rate Agreement
Update (Conoco Oct 20) to be effective 10/1/2020.
Filed Date: 9/29/20.
Accession Number: 20200929-5079.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20-1234-000.
Applicants: Southern Star Central Gas Pipeline, Inc.
Description: Sec. 4(d) Rate Filing: Vol. 2- Negotiated Rate
Agreements--Spotlight, Tenaska, Conexus to be effective 9/29/2020.
Filed Date: 9/29/20.
Accession Number: 20200929-5109.
Comments Due: 5 p.m. ET 10/13/20.
Docket Numbers: RP20-1235-000.
Applicants: Algonquin Gas Transmission, LLC.
Description: Sec. 4(d) Rate Filing: Negotiated Rates--Bay State to
UGI Releases to be effective 10/1/2020.
Filed Date: 9/29/20.
Accession Number: 20200929-5122.
Comments Due: 5 p.m. ET 10/13/20.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified date(s). Protests may be considered,
but intervention is necessary to become a party to the proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: September 30, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-22037 Filed 10-5-20; 8:45 am]