Download as PDF 55848 Federal Register / Vol. 85, No. 176 / Thursday, September 10, 2020 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP20–52–000] WBI Energy Transmission, Inc.; Notice of Revised Schedule for Environmental Review of the North Bakken Expansion Project This notice identifies the Federal Energy Regulatory Commission (FERC or Commission) staff’s revised schedule for the completion of the environmental assessment (EA) for WBI Energy Transmission, Inc.’s (WBI Energy) North Bakken Expansion Project. The first notice of schedule, issued on April 10, 2020, identified September 4, 2020 as the EA issuance date. Since issuance of the April 10 notice, WBI Energy has proposed pipeline route and facility changes and has not fully responded to a previous information request. WBI Energy stated in a letter filed to the project docket that it will file the outstanding data needed for the EA, including information regarding the route changes, on or before September 11, 2020. As a result, Commission staff has revised the schedule for issuance of the EA, based on WBI Energy filing complete information within the forthcoming data response. khammond on DSKJM1Z7X2PROD with NOTICES Schedule for Environmental Review Issuance of the EA—December 17, 2020 90-day Federal Authorization Decision Deadline—March 17, 2021 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. Additional information about the project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, enter the ‘‘Docket Number’’ excluding the last three digits (i.e., CP20–52), select a date range, and follow the instructions. For assistance VerDate Sep<11>2014 16:38 Sep 09, 2020 Jkt 250001 with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: September 3, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–20002 Filed 9–9–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. EL20–70–000] Tucson Electric Power Company; Notice of Petition for Declaratory Order Take notice that on September 2, 2020, pursuant to Rule 207(a)(2) of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207 (2019), Tucson Electric Power Company (Petitioner) hereby submits a petition for declaratory order (Petition) requesting that the Commission issue a declaratory order granting incentive rate treatment for its purchase of development rights and subsequent development of a 64mile transmission project to create a new circuit between Tucson Electric’s Vail and Tortolita substations, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. Comment Date: 5:00 p.m. Eastern time on October 2, 2020. Dated: September 3, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–20000 Filed 9–9–20; 8:45 am] BILLING CODE 6717–01–P FARM CREDIT ADMINISTRATION Privacy Act of 1974; System of Records Farm Credit Administration. Notice of a modified system of AGENCY: ACTION: records. Pursuant to the provisions of the Privacy Act of 1974, as amended, notice is hereby given that the Farm Credit Administration (FCA or Agency) is amending an existing system of records, FCA–2—Financial Management Records—FCA. DATES: You may send written comments on or before October 13, 2020. FCA filed an amended System Report with Congress and the Office of Management and Budget on August 5, 2020. This notice will become effective without further publication on October 20, 2020 unless modified by a subsequent notice to incorporate comments received from the public. ADDRESSES: We offer a variety of methods for you to submit your comments. For accuracy and efficiency, commenters are encouraged to submit comments by email or through the FCA’s website. As facsimiles (faxes) are difficult for us to process and achieve SUMMARY: E:\FR\FM\10SEN1.SGM 10SEN1

Agencies

[Federal Register Volume 85, Number 176 (Thursday, September 10, 2020)]
[Notices]
[Page 55848]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-20002]



[[Page 55848]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP20-52-000]


WBI Energy Transmission, Inc.; Notice of Revised Schedule for 
Environmental Review of the North Bakken Expansion Project

    This notice identifies the Federal Energy Regulatory Commission 
(FERC or Commission) staff's revised schedule for the completion of the 
environmental assessment (EA) for WBI Energy Transmission, Inc.'s (WBI 
Energy) North Bakken Expansion Project. The first notice of schedule, 
issued on April 10, 2020, identified September 4, 2020 as the EA 
issuance date. Since issuance of the April 10 notice, WBI Energy has 
proposed pipeline route and facility changes and has not fully 
responded to a previous information request. WBI Energy stated in a 
letter filed to the project docket that it will file the outstanding 
data needed for the EA, including information regarding the route 
changes, on or before September 11, 2020. As a result, Commission staff 
has revised the schedule for issuance of the EA, based on WBI Energy 
filing complete information within the forthcoming data response.

Schedule for Environmental Review

Issuance of the EA--December 17, 2020
90-day Federal Authorization Decision Deadline--March 17, 2021

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    Additional information about the project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, enter the 
``Docket Number'' excluding the last three digits (i.e., CP20-52), 
select a date range, and follow the instructions. For assistance with 
access to eLibrary, the helpline can be reached at (866) 208-3676, TTY 
(202) 502-8659, or at [email protected]. The eLibrary link on 
the FERC website also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rule makings.

    Dated: September 3, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-20002 Filed 9-9-20; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.