Northern Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Lake City 1st Branch Line Abandonment and Capacity Replacement Project and Request for Comments on Environmental Issues, 55274-55275 [2020-19603]
Download as PDF
55274
Federal Register / Vol. 85, No. 173 / Friday, September 4, 2020 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–504–000]
jbell on DSKJLSW7X2PROD with NOTICES
Northern Natural Gas Company; Notice
of Intent To Prepare an Environmental
Assessment for the Proposed Lake
City 1st Branch Line Abandonment
and Capacity Replacement Project and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Lake City 1st Branch Line
Abandonment and Capacity
Replacement Project (Project) involving
construction and operation of facilities
by Northern Natural Gas Company
(Northern) in Webster and Calhoun
Counties, Iowa. The Commission will
use this EA in its decision-making
process to determine whether the
Project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies about issues
regarding the Project. The National
Environmental Policy Act (NEPA)
requires the Commission to take into
account the environmental impacts that
could result from its action whenever it
considers the issuance of a Certificate of
Public Convenience and Necessity.
NEPA also requires the Commission to
discover concerns the public may have
about proposals. This process is referred
to as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the EA on the important
environmental issues. By this notice, the
Commission requests public comments
on the scope of issues to address in the
EA. To ensure that your comments are
timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00pm
Eastern Time on September 30, 2020.
Comments may be submitted in written
form. Further details on how to submit
comments are provided in the Public
Participation section of this notice.
You can make a difference by
submitting your specific comments or
concerns about the Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
VerDate Sep<11>2014
16:42 Sep 03, 2020
Jkt 250001
evaluate in the EA. Commission staff
will consider all written comments
during the preparation of the EA.
If you sent comments on this Project
to the Commission before the opening of
this docket on July 31, 2020, you will
need to file those comments in Docket
No. CP20–504–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the Project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law.
Northern provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
which addresses a number of typically
asked questions, including the use of
eminent domain and how to participate
in the Commission’s proceedings. This
fact sheet along with other landowner
topics of interest are available for
viewing on the FERC website
(www.ferc.gov) under the Natural Gas
Questions or Landowner Topics link.
Public Participation
The Commission offers a free service
called eSubscription which makes it
easy to stay informed of all issuances
and submittals regarding the dockets/
projects to which you subscribe. These
instant email notifications are the fastest
way to receive notification and provide
a link to the document files which can
reduce the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP20–504–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Summary of the Proposed Project
The Project would consist of the
following facilities and actions in
Webster and Calhoun Counties, Iowa:
• Abandonment in place of 34.2 miles
of the four-inch-diameter Lake City 1st
branch line pipeline system from
Dayton to Lake City, Iowa;
• construction of 9.2 miles of new 6inch-diameter branch line pipeline
extension (the Lake City 2nd branch line
extension), relocation of a receiver to
the Lake City town border station, and
installation of a new take-off valve
setting for the Lohrville town border
station;
• Maximum allowable operating
pressure (MAOP) uprate of 25.3 miles of
the Lake City 2nd branch line pipeline
and installation of a new take-off
regulator setting to the Harcourt branch
line;
• MAOP uprate of the Callender
branch line pipeline; and
• MAOP uprate of the Manson 2nd
branch line pipeline and installation of
a new take-off regulator setting from the
Manson 2nd branch line pipeline to the
E:\FR\FM\04SEN1.SGM
04SEN1
Federal Register / Vol. 85, No. 173 / Friday, September 4, 2020 / Notices
Manson 1st branch line pipeline and
Rockwell City branch line pipeline.
The general location of the Project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 149 acres of land
for the aboveground facilities and the
pipeline. Following construction,
Northern would maintain about 37 acres
for permanent operation of the Project’s
facilities; the remaining acreage would
be restored and revert to former uses.
Approximately 53 percent of the Lake
City 2nd branch line extension would
be constructed adjacent to, and offset 25
feet from, Northern’s existing Lake City
1st branch line. Where the new branch
line extension deviates from the existing
pipeline, the offset was increased to
either avoid impacts on
environmentally sensitive areas or allow
for proper alignment of horizontal
directional drill crossings.
The EA Process
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• air quality and noise;
• public safety; and
• cumulative impacts
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project, and
make recommendations on how to
lessen or avoid impacts on the various
resource areas.
The EA will present Commission
staffs’ independent analysis of the
issues. The EA will be available in
electronic format in the public record
through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the EA is
jbell on DSKJLSW7X2PROD with NOTICES
1 The
appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
2 For instructions on connecting to eLibrary, refer
to the last page of this notice.
VerDate Sep<11>2014
16:42 Sep 03, 2020
Jkt 250001
55275
issued. The EA may be issued for an
allotted public comment period.
Commission staff will consider all
comments on the EA before making
recommendations to the Commission.
To ensure Commission staff have the
opportunity to address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the EA.3 Agencies that would like to
request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If the Commission issues the EA for
an allotted public comment period, a
Notice of Availability of the EA will be
sent to the environmental mailing list
and will provide instructions to access
the electronic document on the FERC’s
website (www.ferc.gov). If you need to
make changes to your name/address, or
if you would like to remove your name
from the mailing list, please return the
attached ‘‘Mailing List Update Form’’
(appendix 2).
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office, and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.4 The EA
for this project will document findings
on the impacts on historic properties
and summarize the status of
consultations under section 106.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field, excluding the last three digits (i.e.,
CP20–504). Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
3 The
Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
Dated: August 31, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–19603 Filed 9–3–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP19–1340–000.
Applicants: Viking Gas Transmission
Company.
Description: Report Filing: Refund
Report.
Filed Date: 8/28/20.
E:\FR\FM\04SEN1.SGM
04SEN1
Agencies
[Federal Register Volume 85, Number 173 (Friday, September 4, 2020)]
[Notices]
[Pages 55274-55275]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-19603]
[[Page 55274]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-504-000]
Northern Natural Gas Company; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Lake City 1st Branch Line
Abandonment and Capacity Replacement Project and Request for Comments
on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Lake City 1st Branch Line
Abandonment and Capacity Replacement Project (Project) involving
construction and operation of facilities by Northern Natural Gas
Company (Northern) in Webster and Calhoun Counties, Iowa. The
Commission will use this EA in its decision-making process to determine
whether the Project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies about issues regarding the Project. The National Environmental
Policy Act (NEPA) requires the Commission to take into account the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. NEPA also requires the Commission to discover concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of issues
to address in the EA. To ensure that your comments are timely and
properly recorded, please submit your comments so that the Commission
receives them in Washington, DC on or before 5:00pm Eastern Time on
September 30, 2020. Comments may be submitted in written form. Further
details on how to submit comments are provided in the Public
Participation section of this notice.
You can make a difference by submitting your specific comments or
concerns about the Project. Your comments should focus on the potential
environmental effects, reasonable alternatives, and measures to avoid
or lessen environmental impacts. Your input will help the Commission
staff determine what issues they need to evaluate in the EA. Commission
staff will consider all written comments during the preparation of the
EA.
If you sent comments on this Project to the Commission before the
opening of this docket on July 31, 2020, you will need to file those
comments in Docket No. CP20-504-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the Project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law.
Northern provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses a number of typically asked questions,
including the use of eminent domain and how to participate in the
Commission's proceedings. This fact sheet along with other landowner
topics of interest are available for viewing on the FERC website
(www.ferc.gov) under the Natural Gas Questions or Landowner Topics
link.
Public Participation
The Commission offers a free service called eSubscription which
makes it easy to stay informed of all issuances and submittals
regarding the dockets/projects to which you subscribe. These instant
email notifications are the fastest way to receive notification and
provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP20-
504-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Summary of the Proposed Project
The Project would consist of the following facilities and actions
in Webster and Calhoun Counties, Iowa:
Abandonment in place of 34.2 miles of the four-inch-
diameter Lake City 1st branch line pipeline system from Dayton to Lake
City, Iowa;
construction of 9.2 miles of new 6-inch-diameter branch
line pipeline extension (the Lake City 2nd branch line extension),
relocation of a receiver to the Lake City town border station, and
installation of a new take-off valve setting for the Lohrville town
border station;
Maximum allowable operating pressure (MAOP) uprate of 25.3
miles of the Lake City 2nd branch line pipeline and installation of a
new take-off regulator setting to the Harcourt branch line;
MAOP uprate of the Callender branch line pipeline; and
MAOP uprate of the Manson 2nd branch line pipeline and
installation of a new take-off regulator setting from the Manson 2nd
branch line pipeline to the
[[Page 55275]]
Manson 1st branch line pipeline and Rockwell City branch line pipeline.
The general location of the Project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE, Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 149
acres of land for the aboveground facilities and the pipeline.
Following construction, Northern would maintain about 37 acres for
permanent operation of the Project's facilities; the remaining acreage
would be restored and revert to former uses. Approximately 53 percent
of the Lake City 2nd branch line extension would be constructed
adjacent to, and offset 25 feet from, Northern's existing Lake City 1st
branch line. Where the new branch line extension deviates from the
existing pipeline, the offset was increased to either avoid impacts on
environmentally sensitive areas or allow for proper alignment of
horizontal directional drill crossings.
The EA Process
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
air quality and noise;
public safety; and
cumulative impacts
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project, and make recommendations
on how to lessen or avoid impacts on the various resource areas.
The EA will present Commission staffs' independent analysis of the
issues. The EA will be available in electronic format in the public
record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the EA is issued. The EA
may be issued for an allotted public comment period. Commission staff
will consider all comments on the EA before making recommendations to
the Commission. To ensure Commission staff have the opportunity to
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the EA.\3\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office,
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The EA for this project will
document findings on the impacts on historic properties and summarize
the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If the Commission issues the EA for an allotted public comment
period, a Notice of Availability of the EA will be sent to the
environmental mailing list and will provide instructions to access the
electronic document on the FERC's website (www.ferc.gov). If you need
to make changes to your name/address, or if you would like to remove
your name from the mailing list, please return the attached ``Mailing
List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field, excluding the last three digits (i.e.,
CP20-504). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or (866) 208-3676, or for TTY, contact (202)
502-8659. The eLibrary link also provides access to the texts of all
formal documents issued by the Commission, such as orders, notices, and
rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: August 31, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-19603 Filed 9-3-20; 8:45 am]