Nevada Hydro Inc.; Notice of Anticipated Schedule for Lake Elsinore Advanced Pumped Storage Project, 54554 [2020-19384]
Download as PDF
54554
Federal Register / Vol. 85, No. 171 / Wednesday, September 2, 2020 / Notices
jbell on DSKJLSW7X2PROD with NOTICES
Mountain Valley states it has not
completed Project construction due to
unforeseen litigation and permitting
delays outside of Mountain Valley’s
control. This includes litigation directly
challenging Project permits and
authorizations as well as litigation
associated with other infrastructure
projects. These challenges have affected,
directly or indirectly, Project permits
and authorizations from the U.S. Forest
Service, Bureau of Land Management,
U.S. Army Corps of Engineers, U.S. Fish
and Wildlife Service, and the National
Park Service. Because of these
permitting challenges, Mountain Valley
states it will not be able to complete
construction and make the Project
facilities available for service by October
13, 2020.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Mountain Valley’s request
for an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).2
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
(2018) (Certificate Order), aff’d sub. nom.,
Appalachian Voices v. FERC, No. 17–1271, 2019
WL 847199 (D.C. Cir. Feb. 19, 2019).
2 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC 61,144, at P 39 (2020).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
4 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
5 Id. at P 40.
VerDate Sep<11>2014
17:33 Sep 01, 2020
Jkt 250001
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFile link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on September 11, 2020.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14227–003]
Nevada Hydro Inc.; Notice of
Anticipated Schedule for Lake Elsinore
Advanced Pumped Storage Project
On October 2, 2017, Nevada Hydro
Inc. filed an application requesting
authorization to construct and operate
the Lake Elsinore Advanced Pumped
Storage Project. The project would be
located on Lake Elsinore and San Juan
Creek near the town of Lake Elsinore in
Riverside and San Diego Counties,
California. The project would occupy
about 845 acres of federal land
administered by the U.S. Forest Service.
The application will be processed
according to the following revised
schedule.
Notice of Ready for Environmental
Analysis: December 11, 2020
Draft Environmental Impact Statement:
July 9, 2021
Final Environmental Impact Statement:
December 10, 2021
In addition, in accordance with Title
41 of the Fixing America’s Surface
Transportation Act, enacted on
December 4, 2015, agencies are to
publish completion dates for all federal
environmental reviews and
authorizations. This notice identifies the
Commission’s anticipated schedule for
issuance of the final order for the
project, which is based on the
anticipated date of issuance of the final
Environmental Impact Statement.
Accordingly, we currently anticipate
issuing a final order for the project no
later than:
Issuance of Final Order March 17, 2022
[FR Doc. 2020–19376 Filed 9–1–20; 8:45 am]
BILLING CODE 6717–01–P
If a schedule change becomes
necessary, an additional notice will be
provided so that interested parties and
government agencies are kept informed
of the project’s progress.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
6 Similarly,
the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
PO 00000
Frm 00023
Fmt 4703
Sfmt 9990
[FR Doc. 2020–19384 Filed 9–1–20; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\02SEN1.SGM
02SEN1
Agencies
[Federal Register Volume 85, Number 171 (Wednesday, September 2, 2020)]
[Notices]
[Page 54554]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-19384]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14227-003]
Nevada Hydro Inc.; Notice of Anticipated Schedule for Lake
Elsinore Advanced Pumped Storage Project
On October 2, 2017, Nevada Hydro Inc. filed an application
requesting authorization to construct and operate the Lake Elsinore
Advanced Pumped Storage Project. The project would be located on Lake
Elsinore and San Juan Creek near the town of Lake Elsinore in Riverside
and San Diego Counties, California. The project would occupy about 845
acres of federal land administered by the U.S. Forest Service.
The application will be processed according to the following
revised schedule.
Notice of Ready for Environmental Analysis: December 11, 2020
Draft Environmental Impact Statement: July 9, 2021
Final Environmental Impact Statement: December 10, 2021
In addition, in accordance with Title 41 of the Fixing America's
Surface Transportation Act, enacted on December 4, 2015, agencies are
to publish completion dates for all federal environmental reviews and
authorizations. This notice identifies the Commission's anticipated
schedule for issuance of the final order for the project, which is
based on the anticipated date of issuance of the final Environmental
Impact Statement. Accordingly, we currently anticipate issuing a final
order for the project no later than:
Issuance of Final Order March 17, 2022
If a schedule change becomes necessary, an additional notice will
be provided so that interested parties and government agencies are kept
informed of the project's progress.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-19384 Filed 9-1-20; 8:45 am]