North Hartland, LLC; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 54558-54559 [2020-19382]
Download as PDF
54558
Federal Register / Vol. 85, No. 171 / Wednesday, September 2, 2020 / Notices
County, Nebraska; (4) abandon in-place
the existing 0.06-mile-long, 2-inchdiameter Jackson branch pipeline in
Dakota County, Nebraska; and (5)
construct, modify, or remove
appurtenant facilities, including pig
launchers and receivers, two new
metering facilities, regulators, tie-overs,
and associated piping and valves.
Northern states that after Commission
approval of the Project, portions of the
abandoned pipeline would be
purchased and removed by a third-party
salvage company.
Background
On July 23, 2019, the Commission
staff granted Northern’s request to use
FERC’s pre-filing environmental review
process and assigned the Project Docket
No. PF19–8–000. On November 22,
2019, the Commission issued a Notice of
Intent to Prepare an Environmental
Assessment for the Planned South Sioux
City to Sioux Falls A-Line Replacement
Project, Request for Comments on
Environmental Issues, and Notice of
Public Scoping Sessions (NOI). The NOI
was issued during the pre-filing review
of the Project and was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers.
In response to the NOI, the
Commission received comments from
the National Park Service, the Nebraska
Department of Natural Resources, and
four landowners. The primary issues
raised by the commentors were impacts
on water quality, visual resources, the
Missouri National Recreational River
and the Lewis and Clark National
Historic Trail, ground water and surface
water resources, floodplains, agriculture
and grazing, residential areas in close
proximity to the pipeline, and impacts
from soil erosion, contamination, and
landform degradation. All substantive
comments will be addressed in the EA.
The U.S. Army Corps of Engineers is
a cooperating agency in the preparation
of the EA.
jbell on DSKJLSW7X2PROD with NOTICES
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
VerDate Sep<11>2014
17:33 Sep 01, 2020
Jkt 250001
ferc-online/overview to register for
eSubscription.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP20–487), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–19377 Filed 9–1–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2816–050]
North Hartland, LLC; Notice of
Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2816–050.
c. Date filed: November 26, 2019.
d. Applicant: North Hartland, LLC
(North Hartland).
e. Name of Project: North Hartland
Hydroelectric Project (North Hartland
Project).
f. Location: The North Hartland
Project is located on the Ottauquechee
River in Windsor County, Vermont. The
North Hartland Project occupies 20.8
acres of land managed by the U.S. Army
Corps of Engineers (Corps).
g. Filed Pursuant To: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Andrew J.
Locke, President, Essex Hydro
Associates, LLC, 55 Union Street,
Boston, MA 02108; Phone at (617) 367–
0032, or email at alocke@
essexhydro.com.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
i. FERC Contact: Bill Connelly, (202)
502–8587 or william.connelly@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, terms and
conditions, and prescriptions: 60 Days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests, comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is ready for environmental
analysis at this time.
l. Project Description: The existing
North Hartland Project consists of: (1) A
steel-lined intake structure in the Corps’
North Hartland Dam that is equipped
with trashracks with 2-inch clear bar
spacing; (2) a 470-foot-long, 12-footdiameter steel penstock that provides
flow to a 4.0-megawatt (MW) adjustable
blade, vertical shaft turbine-generator
unit located inside of a 59-foot-long, 40foot-wide concrete powerhouse; (3) a
12-foot-diameter bypass conduit that
branches off of the 12-foot-diameter
penstock about 100 feet before the
powerhouse, and that empties into a 60foot-long concrete-lined channel
through a bypass control gate; (4) a 30inch-diameter steel penstock that
branches off of the 12-foot-diamater
bypass conduit about 50 feet upstream
of the bypass control gate, and that
provides flow to a 0.1375–MW fixed
geometry, horizontal pump turbinegenerator unit located on a raised
platform outside of the southern wall of
the powerhouse; (5) a 400-foot-long, 50
to 150-foot-wide tailrace channel; (6) a
E:\FR\FM\02SEN1.SGM
02SEN1
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 171 / Wednesday, September 2, 2020 / Notices
transmission line that comprises an
approximately 600-foot-long, 12.5
kilovolt (kV) underground segment, and
a 4,000-foot-long, 12.5-kV overhead
segment that connect the generators to
Green Mountain Power Corporation’s
Clay Hill Road Line 66 Transmission
Project No. 12766; and (9) appurtenant
facilities.
The project is managed to meet daily
peak electrical system demand, as
needed using the available head and
reservoir outflow from the Corps’ North
Hartland dam. The current license
requires North Hartland to release a
continuous minimum flow of 23 cubic
feet per second (cfs) from July 1 through
October 31, and 40 cfs during the
remainder of the year (or inflow to the
reservoir, whichever is less), for the
purpose of protecting and enhancing
aquatic resources in the Ottauquechee
River. The project has an average annual
generation of approximately 13,991,990
kilowatt-hours from 2014 through 2018.
North Hartland proposes to release
the following minimum and maximum
flows, respectively, to the downstream
reach: (1) 60 and 700 cfs from October
1 through March 31; (2) 160 and 835 cfs
from April 1 through April 31; (3) 160
and 550 cfs from May 1 through May 31;
(4) 140 and 450 cfs from June 1 through
June 30; and (5) 60 and 300 cfs from July
1 through September 30.
m. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–2816).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3673 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
VerDate Sep<11>2014
17:33 Sep 01, 2020
Jkt 250001
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must: (1) Bear in all capital
letters the title PROTEST, MOTION TO
INTERVENE, COMMENTS, REPLY
COMMENTS, RECOMMENDATIONS,
TERMS AND CONDITIONS, or
PRESCRIPTIONS; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
p. Procedural Schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestone
Target date
Filing of interventions, protests,
comments, recommendations, preliminary terms and
conditions, and preliminary
fishway prescriptions.
Commission issues Environmental Assessment.
Comments on Environmental
Assessment.
PO 00000
Frm 00028
Fmt 4703
October 2020.
May 2021.
June 2021.
Sfmt 4703
54559
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of this notice.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–19382 Filed 9–1–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EF20–7–000]
Western Area Power Administration;
Notice of Filing
Take notice that on August 25, 2020,
Southeastern Power Administration
submitted tariff filing per: 300.10:
CRSP_SLCAIP_WAPA190–20200825 to
be effective 10/1/2020.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the eLibrary link. Enter
the docket number excluding the last
three digits in the docket number field
to access the document. At this time, the
Commission has suspended access to
E:\FR\FM\02SEN1.SGM
02SEN1
Agencies
[Federal Register Volume 85, Number 171 (Wednesday, September 2, 2020)]
[Notices]
[Pages 54558-54559]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-19382]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2816-050]
North Hartland, LLC; Notice of Application Accepted for Filing,
Soliciting Motions To Intervene and Protests, Ready for Environmental
Analysis, and Soliciting Comments, Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2816-050.
c. Date filed: November 26, 2019.
d. Applicant: North Hartland, LLC (North Hartland).
e. Name of Project: North Hartland Hydroelectric Project (North
Hartland Project).
f. Location: The North Hartland Project is located on the
Ottauquechee River in Windsor County, Vermont. The North Hartland
Project occupies 20.8 acres of land managed by the U.S. Army Corps of
Engineers (Corps).
g. Filed Pursuant To: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Andrew J. Locke, President, Essex Hydro
Associates, LLC, 55 Union Street, Boston, MA 02108; Phone at (617) 367-
0032, or email at [email protected].
i. FERC Contact: Bill Connelly, (202) 502-8587 or
[email protected].
j. Deadline for filing motions to intervene and protests, comments,
recommendations, terms and conditions, and prescriptions: 60 Days from
the issuance date of this notice; reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene and protests, comments, recommendations, terms and
conditions, and prescriptions using the Commission's eFiling system at
https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at [email protected], (866) 208-3676 (toll free), or
(202) 502-8659 (TTY).
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is ready for
environmental analysis at this time.
l. Project Description: The existing North Hartland Project
consists of: (1) A steel-lined intake structure in the Corps' North
Hartland Dam that is equipped with trashracks with 2-inch clear bar
spacing; (2) a 470-foot-long, 12-foot-diameter steel penstock that
provides flow to a 4.0-megawatt (MW) adjustable blade, vertical shaft
turbine-generator unit located inside of a 59-foot-long, 40-foot-wide
concrete powerhouse; (3) a 12-foot-diameter bypass conduit that
branches off of the 12-foot-diameter penstock about 100 feet before the
powerhouse, and that empties into a 60-foot-long concrete-lined channel
through a bypass control gate; (4) a 30-inch-diameter steel penstock
that branches off of the 12-foot-diamater bypass conduit about 50 feet
upstream of the bypass control gate, and that provides flow to a
0.1375-MW fixed geometry, horizontal pump turbine-generator unit
located on a raised platform outside of the southern wall of the
powerhouse; (5) a 400-foot-long, 50 to 150-foot-wide tailrace channel;
(6) a
[[Page 54559]]
transmission line that comprises an approximately 600-foot-long, 12.5
kilovolt (kV) underground segment, and a 4,000-foot-long, 12.5-kV
overhead segment that connect the generators to Green Mountain Power
Corporation's Clay Hill Road Line 66 Transmission Project No. 12766;
and (9) appurtenant facilities.
The project is managed to meet daily peak electrical system demand,
as needed using the available head and reservoir outflow from the
Corps' North Hartland dam. The current license requires North Hartland
to release a continuous minimum flow of 23 cubic feet per second (cfs)
from July 1 through October 31, and 40 cfs during the remainder of the
year (or inflow to the reservoir, whichever is less), for the purpose
of protecting and enhancing aquatic resources in the Ottauquechee
River. The project has an average annual generation of approximately
13,991,990 kilowatt-hours from 2014 through 2018.
North Hartland proposes to release the following minimum and
maximum flows, respectively, to the downstream reach: (1) 60 and 700
cfs from October 1 through March 31; (2) 160 and 835 cfs from April 1
through April 31; (3) 160 and 550 cfs from May 1 through May 31; (4)
140 and 450 cfs from June 1 through June 30; and (5) 60 and 300 cfs
from July 1 through September 30.
m. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov)
using the eLibrary link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
2816). At this time, the Commission has suspended access to the
Commission's Public Reference Room due to the proclamation declaring a
National Emergency concerning the Novel Coronavirus Disease (COVID-19)
issued by the President on March 13, 2020. For assistance, contact FERC
at [email protected] or call toll-free, (886) 208-3673 or
(202) 502-8659 (TTY).
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must: (1) Bear in all capital letters the title
PROTEST, MOTION TO INTERVENE, COMMENTS, REPLY COMMENTS,
RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth
in the heading the name of the applicant and the project number of the
application to which the filing responds; (3) furnish the name,
address, and telephone number of the person protesting or intervening;
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. All comments, recommendations, terms and conditions
or prescriptions must set forth their evidentiary basis and otherwise
comply with the requirements of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from the applicant. A copy of any
protest or motion to intervene must be served upon each representative
of the applicant specified in the particular application. A copy of all
other filings in reference to this application must be accompanied by
proof of service on all persons listed in the service list prepared by
the Commission in this proceeding, in accordance with 18 CFR 4.34(b)
and 385.2010.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
p. Procedural Schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Filing of interventions, protests, October 2020.
comments, recommendations, preliminary
terms and conditions, and preliminary
fishway prescriptions.
Commission issues Environmental May 2021.
Assessment.
Comments on Environmental Assessment... June 2021.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: August 27, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-19382 Filed 9-1-20; 8:45 am]
BILLING CODE 6717-01-P