Brookfield White Pine Hydro, LLC; Notice of Application for Amendment of License, Soliciting Comments, Motions To Intervene, and Protests, 54370 [2020-19254]

Download as PDF 54370 Federal Register / Vol. 85, No. 170 / Tuesday, September 1, 2020 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2375–112] jbell on DSKJLSW7X2PROD with NOTICES Brookfield White Pine Hydro, LLC; Notice of Application for Amendment of License, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Proceeding: Application non-capacity amendment of license. b. Project No.: 2375–112. c. Date Filed: August 13, 2020. d. Licensee: Andro Hydro, LLC. e. Name of Project: Riley-JayLivermore Hydroelectric Project. f. Location: The project is located on the Androscoggin River in Oxford, Franklin, and Androscoggin counties, Maine. The proposed work is in the Towns of Jay and Livermore Falls. g. Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Licensee Contact: Mr. Michael Scarzello, Regulatory Director, Eagle Creek Renewable Energy, LLC, 116 N. State Street, PO Box 167, Neshkoro, WI 54960–0167, (973) 998–8400, or michael.scarzello@eaglecreekre.com. i. FERC Contact: Christopher Chaney, (202) 502–6788 or christopher.chaney@ ferc.gov. j. Deadline for filing comments, interventions, and protests is September 25, 2020. The Commission strongly encourages electronic filing. Please file motions to intervene, protests and comments using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The first page of VerDate Sep<11>2014 19:00 Aug 31, 2020 Jkt 250001 any filing should include docket number P–2375–112. k. Description of Proceeding: The applicant proposes to bury a 4,000-foot section of the of the Livermore Development’s existing 3.2-mile overhead transmission. The buried section would be within an existing, previously disturbed right-of-way over which it holds an easement to occupy and access for maintenance. The application includes revised Exhibit G drawings to meet the Commission’s current requirements. The applicant is not proposing any changes to project operations, recreation facilities, or public access, and the proposal will not impact the project’s generating or water control capabilities. l. Filings may be viewed on the Commission’s website at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–2375–112) excluding the last three digits in the docket number field to access the documents. You may also register online at https://www.ferc.gov/docsfiling/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .212 and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title COMMENTS, PROTEST, or MOTION TO INTERVENE as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: August 26, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–19254 Filed 8–31–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AC20–162–000] Alliance Pipeline L.P.; Notice of Filing Take notice that on August 24, 2020, pursuant to 18 CFR part 201, Alliance Pipeline L.P. submitted a request for approval of accounting treatment for certain deferred tax balances. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 or 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the eLibrary link. Enter the docket number excluding the E:\FR\FM\01SEN1.SGM 01SEN1

Agencies

[Federal Register Volume 85, Number 170 (Tuesday, September 1, 2020)]
[Notices]
[Page 54370]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-19254]



[[Page 54370]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2375-112]


Brookfield White Pine Hydro, LLC; Notice of Application for 
Amendment of License, Soliciting Comments, Motions To Intervene, and 
Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Proceeding: Application non-capacity amendment of 
license.
    b. Project No.: 2375-112.
    c. Date Filed: August 13, 2020.
    d. Licensee: Andro Hydro, LLC.
    e. Name of Project: Riley-Jay-Livermore Hydroelectric Project.
    f. Location: The project is located on the Androscoggin River in 
Oxford, Franklin, and Androscoggin counties, Maine. The proposed work 
is in the Towns of Jay and Livermore Falls.
    g. Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Licensee Contact: Mr. Michael Scarzello, Regulatory Director, 
Eagle Creek Renewable Energy, LLC, 116 N. State Street, PO Box 167, 
Neshkoro, WI 54960-0167, (973) 998-8400, or 
[email protected].
    i. FERC Contact: Christopher Chaney, (202) 502-6788 or 
[email protected].
    j. Deadline for filing comments, interventions, and protests is 
September 25, 2020.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests and comments using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, MD 20852. The first page of any filing should 
include docket number P-2375-112.
    k. Description of Proceeding: The applicant proposes to bury a 
4,000-foot section of the of the Livermore Development's existing 3.2-
mile overhead transmission. The buried section would be within an 
existing, previously disturbed right-of-way over which it holds an 
easement to occupy and access for maintenance. The application includes 
revised Exhibit G drawings to meet the Commission's current 
requirements. The applicant is not proposing any changes to project 
operations, recreation facilities, or public access, and the proposal 
will not impact the project's generating or water control capabilities.
    l. Filings may be viewed on the Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-2375-
112) excluding the last three digits in the docket number field to 
access the documents. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of 
new filings and issuances related to this or other pending projects. 
For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.212 and .214. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title COMMENTS, PROTEST, or MOTION TO INTERVENE as 
applicable; (2) set forth in the heading the name of the applicant and 
the project number of the application to which the filing responds; (3) 
furnish the name, address, and telephone number of the person 
protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, motions 
to intervene, or protests must set forth their evidentiary basis. Any 
filing made by an intervenor must be accompanied by proof of service on 
all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 385.2010.

    Dated: August 26, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-19254 Filed 8-31-20; 8:45 am]
BILLING CODE 6717-01-P