Spencer Mountain Hydropower, LLC; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 50821-50822 [2020-17995]
Download as PDF
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 160 / Tuesday, August 18, 2020 / Notices
The project would operate using the
natural tidal currents of the East River,
during both ebb and flood tidal periods.
As the direction of tidal flow changes,
each turbine-generator unit would rotate
(or yaw) to align the rotor to the
direction of flow, through a passive
system caused by hydrodynamic forces
on the turbine-generator unit. The
annual generation is expected to be from
840 to 1,200 megawatt-hours.
m. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested individuals an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the eLibrary link.
At this time, the Commission has
suspended access to the Commission’s
Public Access Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process.
The Commission, in cooperation with
the U.S. Environmental Protection
Agency, intends to prepare an
environmental assessment (EA) for the
RITE Project in accordance with the
National Environmental Policy Act. The
EA will consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
Commission staff does not propose to
conduct any on-site scoping meetings at
this time. Instead, we are soliciting
comments, recommendations, and
information, on the Scoping Document
1 (SD1) issued August 12, 2020.
Copies of SD1 outlining the subject
areas to be addressed in the EA were
distributed to the parties on the
Commission’s mailing list. Copies of
SD1 may be viewed on the web at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, call 1–866–208–3676 or
for TTY, (202) 502–8659.
VerDate Sep<11>2014
17:50 Aug 17, 2020
Jkt 250001
Dated: August 12, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–17997 Filed 8–17–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
50821
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Federal Energy Regulatory
Commission
Dated: August 12, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Combined Notice of Filings
[FR Doc. 2020–18024 Filed 8–17–20; 8:45 am]
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP20–1087–000.
Applicants: Equitrans, L.P.
Description: § 4(d) Rate Filing:
Negotiated Rate Capacity Release
Agreement—8/8/2020 to be effective
8/8/2020.
Filed Date: 8/7/20.
Accession Number: 20200807–5062.
Comments Due: 5 p.m. ET 8/19/20.
Docket Numbers: RP20–1090–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 081120
Negotiated Rates—Wells Fargo
Commodities, LLC R–7810–19 to be
effective 10/1/2020.
Filed Date: 8/11/20.
Accession Number: 20200811–5027.
Comments Due: 5 p.m. ET 8/24/20.
Docket Numbers: RP20–1091–000.
Applicants: Rockies Express Pipeline
LLC.
Description: § 4(d) Rate Filing: REX
2020–08–11 Negotiated Rate Agreement
to be effective 8/11/2020.
Filed Date: 8/11/20.
Accession Number: 20200811–5093.
Comments Due: 5 p.m. ET 8/24/20.
Docket Numbers: RP20–1092–000.
Applicants: Texas Gas Transmission,
LLC.
Description: § 4(d) Rate Filing: Neg
Rate Agmt (Westlake 38162) to be
effective 8/1/2020.
Filed Date: 8/11/20.
Accession Number: 20200811–5094.
Comments Due: 5 p.m. ET 8/24/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2607–015]
Spencer Mountain Hydropower, LLC;
Notice of Intent To File License
Application, Filing of Pre-Application
Document, and Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 2607–015.
c. Date Filed: June 30, 2020.
d. Submitted By: Spencer Mountain
Hydropower, LLC.
e. Name of Project: Spencer Mountain
Hydropower Project.
f. Location: On the South Fork of the
Catawba River, in the Town of Spencer
Mountain, in Gaston County, North
Carolina. The project does not occupy
federal lands.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s Regulations.
h. Potential Applicant Contact: Kevin
Edwards, 916 Comer Road, Stoneville,
NC 27048; (336) 589–6138; email—
smhydro@pht1.com.
i. FERC Contact: Michael Spencer at
(202) 502–6093, or email at
michael.spencer@ferc.gov.
j. Spencer Mountain Hydropower,
LLC filed its request to use the
Traditional Licensing Process, and
provided public notice of its request, on
June 30, 2020. In a letter dated August
12, 2020, the Director of the Division of
Hydropower Licensing approved
Spencer Mountain Hydropower, LLC’s
request to use the Traditional Licensing
Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402. We are also initiating
consultation with the North Carolina
E:\FR\FM\18AUN1.SGM
18AUN1
50822
Federal Register / Vol. 85, No. 160 / Tuesday, August 18, 2020 / Notices
jbell on DSKJLSW7X2PROD with NOTICES
State Historic Preservation Officer, as
required by section 106 of the National
Historic Preservation Act, and the
implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Spencer Mountain Hydropower, LLC as
the Commission’s non-federal
representative for carrying out informal
consultation pursuant to section 7 of the
Endangered Species Act and
consultation pursuant to section 106 of
the National Historic Preservation Act.
m. Spencer Mountain Hydropower,
LLC filed a Pre-Application Document
(PAD; including a proposed process
plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
n. A copy of the PAD may be viewed
on the Commission’s website (https://
www.ferc.gov), using the eLibrary link.
Enter the docket number, excluding the
last three digits in the docket number
field, to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC Online
Support at FERCONlineSupport@
ferc.gov, (866) 208 3676 (toll free), or
(202) 502–8659 (TTY).
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 2607–015.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by June 30, 2023.
p. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: August 12, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–17995 Filed 8–17–20; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:50 Aug 17, 2020
Jkt 250001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP20–503–000; PF20–1–000]
Northern Natural Gas Company; Notice
of Application
Take notice that on July 31, 2020,
Northern Natural Gas Company
(Northern), 1111 South 103rd Street,
Omaha, NE 68124, filed an application
in Docket No. CP20–503–000, pursuant
to section 7 of the Natural Gas Act and
Part 157 of the Commission’s
Regulations thereunder, requesting the
issuance of a certificate of public
convenience and necessity to construct,
modify, replace and operate certain
compression and pipeline facilities,
with appurtenances, located in various
counties in Minnesota. All relevant
information is more fully set forth in the
application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this
application should be directed to
Michael T. Loeffler, Senior Director,
Certificates and External Affairs for
Northern, 1111 South 103rd Street,
Omaha, Nebraska 68124, or by calling
(402) 398–7103.
Specifically, Northern proposes to: (1)
Construct an 0.80-mile-long, 24-inchdiameter pipeline extension and an
0.63-mile-long, 24-inch-diameter
pipeline loop; (2) replace an 0.08-milelong, 8-inch-diameter branch line with
an equivalent length of 12-inchdiameter pipeline; (3) construct a new
11,153 hp gas-fired turbine greenfield
compressor station; (4) install an
additional 1,100 hp electric-driven
reciprocating compressor unit at its
Pierz Compressor Station; and (5)
construct various appurtenances, all
located within Minnesota.
On December 6, 2019, the
Commission staff granted Northern’s
request to utilize the National
Environmental Policy Act (NEPA) PreFiling Process and assigned Docket No.
PF20–1–000 to staff activities involving
the Project. Now, as of the filing of this
application on July 31, 2020, the NEPA
Pre-Filing Process for this project has
ended. From this time forward, this
proceeding will be conducted in Docket
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
No. CP20–503–000, as noted in the
caption of this Notice.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
3 copies of filings made in the
proceeding with the Commission and
must provide a copy to the applicant
and to every other party. Only parties to
the proceeding can ask for court review
of Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
E:\FR\FM\18AUN1.SGM
18AUN1
Agencies
[Federal Register Volume 85, Number 160 (Tuesday, August 18, 2020)]
[Notices]
[Pages 50821-50822]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-17995]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2607-015]
Spencer Mountain Hydropower, LLC; Notice of Intent To File
License Application, Filing of Pre-Application Document, and Approving
Use of the Traditional Licensing Process
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project No.: 2607-015.
c. Date Filed: June 30, 2020.
d. Submitted By: Spencer Mountain Hydropower, LLC.
e. Name of Project: Spencer Mountain Hydropower Project.
f. Location: On the South Fork of the Catawba River, in the Town of
Spencer Mountain, in Gaston County, North Carolina. The project does
not occupy federal lands.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's Regulations.
h. Potential Applicant Contact: Kevin Edwards, 916 Comer Road,
Stoneville, NC 27048; (336) 589-6138; [email protected]
i. FERC Contact: Michael Spencer at (202) 502-6093, or email at
[email protected].
j. Spencer Mountain Hydropower, LLC filed its request to use the
Traditional Licensing Process, and provided public notice of its
request, on June 30, 2020. In a letter dated August 12, 2020, the
Director of the Division of Hydropower Licensing approved Spencer
Mountain Hydropower, LLC's request to use the Traditional Licensing
Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section
7 of the Endangered Species Act and the joint agency regulations
thereunder at 50 CFR, Part 402. We are also initiating consultation
with the North Carolina
[[Page 50822]]
State Historic Preservation Officer, as required by section 106 of the
National Historic Preservation Act, and the implementing regulations of
the Advisory Council on Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating Spencer Mountain
Hydropower, LLC as the Commission's non-federal representative for
carrying out informal consultation pursuant to section 7 of the
Endangered Species Act and consultation pursuant to section 106 of the
National Historic Preservation Act.
m. Spencer Mountain Hydropower, LLC filed a Pre-Application
Document (PAD; including a proposed process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of the Commission's regulations.
n. A copy of the PAD may be viewed on the Commission's website
(https://www.ferc.gov), using the eLibrary link. Enter the docket
number, excluding the last three digits in the docket number field, to
access the document. At this time, the Commission has suspended access
to the Commission's Public Reference Room, due to the proclamation
declaring a National Emergency concerning the Novel Coronavirus Disease
(COVID-19), issued by the President on March 13, 2020. For assistance,
contact FERC Online Support at [email protected], (866) 208
3676 (toll free), or (202) 502-8659 (TTY).
o. The licensee states its unequivocal intent to submit an
application for a new license for Project No. 2607-015. Pursuant to 18
CFR 16.8, 16.9, and 16.10 each application for a new license and any
competing license applications must be filed with the Commission at
least 24 months prior to the expiration of the existing license. All
applications for license for this project must be filed by June 30,
2023.
p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: August 12, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-17995 Filed 8-17-20; 8:45 am]
BILLING CODE 6717-01-P