Tuscarora Gas Transmission Company; Notice of Intent To Prepare An Environmental Assessment for the Proposed Tuscarora Xpress Project and Request for Comments on Environmental Issues, 48517-48519 [2020-17512]
Download as PDF
Federal Register / Vol. 85, No. 155 / Tuesday, August 11, 2020 / Notices
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Comment Date: 5:00 p.m. Eastern
Time on August 25, 2020.
Dated: August 5, 2020.
Kimberly D. Bose,
Secretary.1
[FR Doc. 2020–17500 Filed 8–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD20–14–000]
Carbon Pricing in Organized
Wholesale Electricity Markets;
Supplemental Notice of Technical
Conference
As announced in the Notice of
Technical Conference issued in this
proceeding on June 17, 2020, the
Federal Energy Regulatory Commission
(Commission) will convene a
Commissioner-led technical conference
in the above-referenced proceeding on
Wednesday, September 30, 2020, from
approximately 9:00 a.m. to 5:00 p.m.
Eastern time. The conference will be
held either in-person—at the
Commission’s headquarters at 888 First
Street NE, Washington, DC 20426 in the
Commission Meeting Room (with a
webcast option available)—or
electronically.
The purpose of this conference is to
discuss considerations related to stateadoption of mechanisms to price carbon
dioxide emissions, commonly referred
to as carbon pricing, in regions with
Commission-jurisdictional organized
wholesale electricity markets (i.e.,
regions with regional transmission
organizations/independent system
operators, or RTOs/ISOs). This
conference will address carbon pricing
approaches where a state (or group of
states) sets an explicit carbon price,
whether through a price-based or
1 18
quantity-based approach, and how that
carbon price intersects with RTO/ISOadministered markets, addressing both
legal and technical issues.
A high-level agenda for this
conference is attached. The Commission
will issue a further supplemental notice
with a full agenda that includes
questions for each panel and the list of
panelists, and further details regarding
whether this conference will be held inperson or electronically. There is no fee
for attendance, and the conference will
be webcast as an option for the public
to attend electronically. Information on
this technical conference, including a
link to the webcast, will also be posted
on this conference’s event page on the
Commission’s website, www.ferc.gov/
news-events/events/technicalconference-regarding-carbon-pricingorganized-wholesale-electricity, prior to
the event. The conference will be
transcribed. Transcripts will be
available for a fee from Ace Reporting,
(202) 347–3700.
Commission conferences are
accessible under section 508 of the
Rehabilitation Act of 1973. For
accessibility accommodations, please
send an email to accessibility@ferc.gov,
call toll-free (866) 208–3372 (voice) or
(202) 208–8659 (TTY), or send a fax to
(202) 208–2106 with the required
accommodations. This notice is issued
and published in accordance with 18
CFR 2.1 (2019).
For more information about this
technical conference, please contact:
John Miller (Technical Information),
Office of Energy Market Regulation,
(202) 502–6016, john.miller@ferc.gov
Anne Marie Hirschberger (Legal
Information), Office of the General
Counsel, (202) 502–8387,
annemarie.hirschberger@ferc.gov
Sarah McKinley (Logistical
Information), Office of External
Affairs, (202) 502–8004,
sarah.mckinley@ferc.gov
Dated: August 5, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–17505 Filed 8–10–20; 8:45 am]
BILLING CODE 6717–01–P
CFR 2.1 (2019).
VerDate Sep<11>2014
17:02 Aug 10, 2020
Jkt 250001
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
48517
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–486–000]
Tuscarora Gas Transmission
Company; Notice of Intent To Prepare
An Environmental Assessment for the
Proposed Tuscarora Xpress Project
and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Tuscarora Xpress Project (Project)
involving construction and operation of
facilities by Tuscarora Gas Transmission
Company (Tuscarora) in Washoe
County, Nevada. The Commission will
use this EA in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies about issues
regarding the project. The National
Environmental Policy Act (NEPA)
requires the Commission to take into
account the environmental impacts that
could result from its action whenever it
considers the issuance of a Certificate of
Public Convenience and Necessity.
NEPA also requires the Commission to
discover concerns the public may have
about proposals. This process is referred
to as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the EA on the important
environmental issues. By this notice, the
Commission requests public comments
on the scope of issues to address in the
EA. To ensure that your comments are
timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00pm
Eastern Time on September 3, 2020.
Comments may be submitted in written
form. Further details on how to submit
comments are provided in the Public
Participation section of this notice.
You can make a difference by
submitting your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. Commission staff
will consider all written comments
during the preparation of the EA.
E:\FR\FM\11AUN1.SGM
11AUN1
48518
Federal Register / Vol. 85, No. 155 / Tuesday, August 11, 2020 / Notices
If you sent comments on this project
to the Commission before the opening of
this docket on June 24, 2020, you will
need to file those comments in Docket
No. CP20–486–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law.
Tuscarora provided landowners with
a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas Questions or
Landowner Topics link.
Public Participation
The Commission offers a free service
called eSubscription which makes it
easy to stay informed of all issuances
and submittals regarding the dockets/
projects to which you subscribe. These
instant email notifications are the fastest
way to receive notification and provide
a link to the document files which can
reduce the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
VerDate Sep<11>2014
17:02 Aug 10, 2020
Jkt 250001
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP20–486–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Summary of the Proposed Project
Tuscarora proposes to upgrade and
replace an existing reciprocating
compressor unit (and building) and
construct a new skid-mounted
compressor unit at the same location
within the existing Wadsworth
Compressor Station in Washoe County,
Nevada. Additionally, Tuscarora would
upgrade an existing meter, replace the
existing meter bypass line with a new
meter piping run, and install a second
new meter within the existing
compressor station site. According to
Tuscarora, the Tuscarora Xpress Project
would provide 15,000 dekatherms per
day (Dth/d) of incremental firm
transportation capacity on Tuscarora’s
interstate natural gas pipeline system
from its interconnection with Gas
Transmission Northwest LLC in Malin,
Oregon to its Wadsworth Compressor
Station in northern Nevada to meet the
growing market demand for natural gas
in this area.
The Tuscarora Xpress Project would
consist of the following activities:
• Demolition and replacement of one
compressor facility and foundation;
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
• upgrade and replacement of a
reciprocating compressor unit and
foundation;
• replacement of metering facilities;
and
• installation of station piping.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb approximately 4.6 acres
of land, 4.0 acres of which would be
restored to pre-existing conditions after
construction is complete.
The EA Process
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• air quality and noise;
• public safety; and
• cumulative impacts
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas.
The EA will present Commission
staffs’ independent analysis of the
issues. The EA will be available in
electronic format in the public record
through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the EA is
issued. The EA may be issued for an
allotted public comment period.
Commission staff will consider all
comments on the EA before making
recommendations to the Commission.
To ensure Commission staff have the
opportunity to address your comments,
please carefully follow the instructions
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
2 For instructions on connecting to eLibrary, refer
to the last page of this notice.
E:\FR\FM\11AUN1.SGM
11AUN1
Federal Register / Vol. 85, No. 155 / Tuesday, August 11, 2020 / Notices
in the Public Participation section,
beginning on page 2.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the EA.3 Agencies that would like to
request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
If the Commission issues the EA for
an allotted public comment period, a
Notice of Availability of the EA will be
sent to the environmental mailing list
and will provide instructions to access
the electronic document on the FERC’s
website (www.ferc.gov). If you need to
make changes to your name/address, or
if you would like to remove your name
from the mailing list, please return the
attached ‘‘Mailing List Update Form’’
(appendix 2).
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office, and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.4 The EA
for this project will document findings
on the impacts on historic properties
and summarize the status of
consultations under section 106.
Additional Information
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
17:02 Aug 10, 2020
Jkt 250001
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field, excluding the last three digits (i.e.,
CP20–486). Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: August 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–17512 Filed 8–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–52–001; CP20–52–000]
WBI Energy Transmission, Inc.; Notice
of Application
Take notice that on July 28, 2020, WBI
Energy Transmission, Inc. (WBI Energy),
1250 West Century Avenue, Bismarck,
North Dakota 58503, filed in the above
referenced docket an amendment to its
application filed on February 14, 2020,
pursuant to section 7(c) of the Natural
Gas Act and Part 157 of the
Commission’s regulations, to construct,
modify and maintain the North Bakken
Expansion Project (Project). By this
amendment, WBI Energy proposes (i) to
reduce the Project’s incremental firm
transportation design capacity from
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
48519
350,000 Mcf/d to 250,000 Mcf/d by
reducing the number of additional
compressor units at its existing Tioga
Compressor Station from six units to
three units; (ii) to update the Project’s
cost, and (iii) to update certain
appurtenant Project facilities.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed Lori
Myerchin, Director, Regulatory Affairs
and Transportation Services, WBI
Energy Transmission, Inc., 1250 West
Century Avenue, Bismarck, North
Dakota 58503, by telephone at (701)
530–1563 or by email at lori.myerchin@
wbienergy.com.
Pursuant to section 157.9 of the
Commission’s rules (18 CFR 157.9),
within 90 days of this Notice, the
Commission staff will issue a Notice of
Schedule for Environmental Review. If
a Notice of Schedule for Environmental
Review is issued, it will indicate, among
other milestones, the anticipated date
for the Commission staff’s issuance of
the environmental assessment (EA) for
this proposal. The issuance of a Notice
of Schedule for Environmental Review
will serve to notify federal and state
agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
E:\FR\FM\11AUN1.SGM
11AUN1
Agencies
[Federal Register Volume 85, Number 155 (Tuesday, August 11, 2020)]
[Notices]
[Pages 48517-48519]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-17512]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-486-000]
Tuscarora Gas Transmission Company; Notice of Intent To Prepare
An Environmental Assessment for the Proposed Tuscarora Xpress Project
and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Tuscarora Xpress Project
(Project) involving construction and operation of facilities by
Tuscarora Gas Transmission Company (Tuscarora) in Washoe County,
Nevada. The Commission will use this EA in its decision-making process
to determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies about issues regarding the project. The National Environmental
Policy Act (NEPA) requires the Commission to take into account the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. NEPA also requires the Commission to discover concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of issues
to address in the EA. To ensure that your comments are timely and
properly recorded, please submit your comments so that the Commission
receives them in Washington, DC on or before 5:00pm Eastern Time on
September 3, 2020. Comments may be submitted in written form. Further
details on how to submit comments are provided in the Public
Participation section of this notice.
You can make a difference by submitting your specific comments or
concerns about the project. Your comments should focus on the potential
environmental effects, reasonable alternatives, and measures to avoid
or lessen environmental impacts. Your input will help the Commission
staff determine what issues they need to evaluate in the EA. Commission
staff will consider all written comments during the preparation of the
EA.
[[Page 48518]]
If you sent comments on this project to the Commission before the
opening of this docket on June 24, 2020, you will need to file those
comments in Docket No. CP20-486-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law.
Tuscarora provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. This fact sheet along with other
landowner topics of interest are available for viewing on the FERC
website (www.ferc.gov) under the Natural Gas Questions or Landowner
Topics link.
Public Participation
The Commission offers a free service called eSubscription which
makes it easy to stay informed of all issuances and submittals
regarding the dockets/projects to which you subscribe. These instant
email notifications are the fastest way to receive notification and
provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP20-
486-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Summary of the Proposed Project
Tuscarora proposes to upgrade and replace an existing reciprocating
compressor unit (and building) and construct a new skid-mounted
compressor unit at the same location within the existing Wadsworth
Compressor Station in Washoe County, Nevada. Additionally, Tuscarora
would upgrade an existing meter, replace the existing meter bypass line
with a new meter piping run, and install a second new meter within the
existing compressor station site. According to Tuscarora, the Tuscarora
Xpress Project would provide 15,000 dekatherms per day (Dth/d) of
incremental firm transportation capacity on Tuscarora's interstate
natural gas pipeline system from its interconnection with Gas
Transmission Northwest LLC in Malin, Oregon to its Wadsworth Compressor
Station in northern Nevada to meet the growing market demand for
natural gas in this area.
The Tuscarora Xpress Project would consist of the following
activities:
Demolition and replacement of one compressor facility and
foundation;
upgrade and replacement of a reciprocating compressor unit
and foundation;
replacement of metering facilities; and
installation of station piping.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE, Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb approximately
4.6 acres of land, 4.0 acres of which would be restored to pre-existing
conditions after construction is complete.
The EA Process
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
air quality and noise;
public safety; and
cumulative impacts
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas.
The EA will present Commission staffs' independent analysis of the
issues. The EA will be available in electronic format in the public
record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the EA is issued. The EA
may be issued for an allotted public comment period. Commission staff
will consider all comments on the EA before making recommendations to
the Commission. To ensure Commission staff have the opportunity to
address your comments, please carefully follow the instructions
[[Page 48519]]
in the Public Participation section, beginning on page 2.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the EA.\3\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office,
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The EA for this project will
document findings on the impacts on historic properties and summarize
the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If the Commission issues the EA for an allotted public comment
period, a Notice of Availability of the EA will be sent to the
environmental mailing list and will provide instructions to access the
electronic document on the FERC's website (www.ferc.gov). If you need
to make changes to your name/address, or if you would like to remove
your name from the mailing list, please return the attached ``Mailing
List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field, excluding the last three digits (i.e.,
CP20-486). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or (866) 208-3676, or for TTY, contact (202)
502-8659. The eLibrary link also provides access to the texts of all
formal documents issued by the Commission, such as orders, notices, and
rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: August 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-17512 Filed 8-10-20; 8:45 am]
BILLING CODE 6717-01-P