Download as PDF jbell on DSKJLSW7X2PROD with NOTICES 47202 Federal Register / Vol. 85, No. 150 / Tuesday, August 4, 2020 / Notices Filed Date: 7/29/20. Accession Number: 20200729–5046. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2533–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original ISA, SA No. 5691; Queue No. AF1–194 to be effective 6/30/2020. Filed Date: 7/29/20. Accession Number: 20200729–5049. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2534–000. Applicants: AEP Texas Inc. Description: § 205(d) Rate Filing: AEPTX-Concho Valley EC-Golden Spread EC 3rd Amended Interconnection Agreement to be effective 7/20/2020. Filed Date: 7/29/20. Accession Number: 20200729–5051. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2535–000. Applicants: Duke Energy Ohio, Inc. Description: § 205(d) Rate Filing: DEO–AEP—RS 272—Agreement for Transmission Service Billing for Retail Load to be effective 9/28/2020. Filed Date: 7/29/20. Accession Number: 20200729–5065. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2536–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Amendment to Tri-State Rate Schedule No. 129 to be effective 2/26/2020. Filed Date: 7/29/20. Accession Number: 20200729–5068. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2537–000. Applicants: Crowned Ridge Wind, LLC. Description: Baseline eTariff Filing: Crowned Ridge Wind, LLC Filing of Assignment, Co-Tenancy and SFA to be effective 8/6/2020. Filed Date: 7/29/20. Accession Number: 20200729–5105. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2538–000. Applicants: Midcontinent Independent System Operator, Inc, Michigan Electric Transmission Company, LLC. Description: § 205(d) Rate Filing: 2020–07–29_SA 2376 METC-Lowell Light & Power 2nd Rev IFA to be effective 9/28/2020. Filed Date: 7/29/20. Accession Number: 20200729–5106. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2539–000. Applicants: Duke Energy Florida, LLC. Description: § 205(d) Rate Filing: Dynamic Transfer Agreement RS–270— VerDate Sep<11>2014 18:14 Aug 03, 2020 Jkt 250001 DEF, Winter Park, FPMA, FMPP to be effective 10/1/2020. Filed Date: 7/29/20. Accession Number: 20200729–5124. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2540–000. Applicants: California Ridge Wind Energy LLC. Description: § 205(d) Rate Filing: Request for Cat. 1 Seller Status in the Central Region and Revised MBR Tariff to be effective 7/30/2020. Filed Date: 7/29/20. Accession Number: 20200729–5131. Comments Due: 5 p.m. ET 8/19/20. Docket Numbers: ER20–2541–000. Applicants: Entergy Louisiana, LLC. Description: § 205(d) Rate Filing: ELL JWLPS Reactive to be effective 10/1/ 2020. Filed Date: 7/29/20. Accession Number: 20200729–5133. Comments Due: 5 p.m. ET 8/19/20. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 29, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–16942 Filed 8–3–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10821–005] Pacific Gas and Electric Company; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following license application has been filed with the Commission and is available for public inspection. PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 a. Type of Application: Subsequent License—Transmission Line Only. b. Project No.: P–10821–005. c. Date filed: June 27, 2019. d. Applicant: Pacific Gas and Electric Company (PG&E). e. Name of Project: Camp Far West Transmission Line Project. f. Location: The existing transmission line project, with proposed modifications, would be located in Placer and Yuba Counties, California. The project would occupy a total of 52.3 acres and include tribal land managed by the U.S. Department of the Interior, Bureau of Indian Affairs (Auburn OffReservation Land Trust) and federal land managed by the U.S. Department of Defense (Beale Air Force Base). g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Robert Donovan, Senior Transmission Planner, Pacific Gas and Electric Company, 245 Market Street, Room 1053B, Mail Code N10A, San Francisco, California 94105. i. FERC Contact: Quinn Emmering, (202) 502–6382, quinn.emmering@ ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERC.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P– 10821–005. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of E:\FR\FM\04AUN1.SGM 04AUN1 jbell on DSKJLSW7X2PROD with NOTICES Federal Register / Vol. 85, No. 150 / Tuesday, August 4, 2020 / Notices that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is ready for environmental analysis at this time. l. The existing Camp Far West Transmission Line Project includes a 1.9-mile-long, three-phase, 60-kilovolt (kV) transmission line extending from the powerhouse of the Camp Far West Hydroelectric Project in Placer County to an interconnection with PG&E’s 9mile-long Smartville-Lincoln (formerly Smartville-Pleasant Grove) 60-kV transmission line. The Camp Far West Transmission Line Project is a transmission line only project; therefore, the project does not generate power, nor does it include any dams, diversions, or otherwise discharge to surface waters, nor does it include recreation facilities. The transmission line project annually transmits approximately 26,900 megawatt hours of energy generated at the project powerhouse for the Camp Far West Hydroelectric Project. PG&E proposes to include the 9-milelong Smartville-Lincoln 60-kV transmission line as a project facility in any subsequent license issued for the project. PG&E has determined that, while this segment of transmission line used to carry electricity from multiple sources, it now only carries electricity from the Camp Far West Hydroelectric Project to the integrated transmission system. Due to this, PG&E believes that the 9-mile-long segment should be considered part of the primary transmission line for the Camp Far West Hydroelectric Project and that it be incorporated into the Camp Far West Transmission Line Project. As proposed, the Camp Far West Transmission Line Project would consist of 10.9-mile-long, three-phase, 60-kV transmission line extending from the powerhouse of the Camp Far West Hydroelectric Project to the interconnection point located at Beale Air Force Base. m. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s website at https:// www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document (i.e., P– 10821). At this time, the Commission VerDate Sep<11>2014 18:14 Aug 03, 2020 Jkt 250001 has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC Online Support. All filings must (1) bear in all capital letters the title COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https://ferconline.ferc.gov/ FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Deadline for Filing Comments, Recommendations, and Agency Terms and Conditions/Prescriptions September 28, 2020 Licensee’s Reply to REA Comments November 11, 2020 Commission issues EA April 2021 Comments on EA May 2021 Commission issues license order October 2021 PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 47203 Dated: July 29, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–16949 Filed 8–3–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–2512–000] SR Baxley, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced SR Baxley, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is August 18, 2020. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all E:\FR\FM\04AUN1.SGM 04AUN1

Agencies

[Federal Register Volume 85, Number 150 (Tuesday, August 4, 2020)]
[Notices]
[Pages 47202-47203]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-16949]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10821-005]


Pacific Gas and Electric Company; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following license application has been filed 
with the Commission and is available for public inspection.
    a. Type of Application: Subsequent License--Transmission Line Only.
    b. Project No.: P-10821-005.
    c. Date filed: June 27, 2019.
    d. Applicant: Pacific Gas and Electric Company (PG&E).
    e. Name of Project: Camp Far West Transmission Line Project.
    f. Location: The existing transmission line project, with proposed 
modifications, would be located in Placer and Yuba Counties, 
California. The project would occupy a total of 52.3 acres and include 
tribal land managed by the U.S. Department of the Interior, Bureau of 
Indian Affairs (Auburn Off-Reservation Land Trust) and federal land 
managed by the U.S. Department of Defense (Beale Air Force Base).
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Robert Donovan, Senior Transmission 
Planner, Pacific Gas and Electric Company, 245 Market Street, Room 
1053B, Mail Code N10A, San Francisco, California 94105.
    i. FERC Contact: Quinn Emmering, (202) 502-6382, 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERC.aspx. Commenters can submit brief comments up to 6,000 characters, 
without prior registration, using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. You must include your name and 
contact information at the end of your comments. For assistance, please 
contact FERC Online Support at [email protected], (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, you may submit a paper copy. Submissions sent via the U.S. 
Postal Service must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426. Submissions sent via any other carrier must be 
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first 
page of any filing should include docket number P-10821-005.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of

[[Page 47203]]

that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted and is ready for 
environmental analysis at this time.
    l. The existing Camp Far West Transmission Line Project includes a 
1.9-mile-long, three-phase, 60-kilovolt (kV) transmission line 
extending from the powerhouse of the Camp Far West Hydroelectric 
Project in Placer County to an interconnection with PG&E's 9-mile-long 
Smartville-Lincoln (formerly Smartville-Pleasant Grove) 60-kV 
transmission line. The Camp Far West Transmission Line Project is a 
transmission line only project; therefore, the project does not 
generate power, nor does it include any dams, diversions, or otherwise 
discharge to surface waters, nor does it include recreation facilities. 
The transmission line project annually transmits approximately 26,900 
megawatt hours of energy generated at the project powerhouse for the 
Camp Far West Hydroelectric Project.
    PG&E proposes to include the 9-mile-long Smartville-Lincoln 60-kV 
transmission line as a project facility in any subsequent license 
issued for the project. PG&E has determined that, while this segment of 
transmission line used to carry electricity from multiple sources, it 
now only carries electricity from the Camp Far West Hydroelectric 
Project to the integrated transmission system. Due to this, PG&E 
believes that the 9-mile-long segment should be considered part of the 
primary transmission line for the Camp Far West Hydroelectric Project 
and that it be incorporated into the Camp Far West Transmission Line 
Project. As proposed, the Camp Far West Transmission Line Project would 
consist of 10.9-mile-long, three-phase, 60-kV transmission line 
extending from the powerhouse of the Camp Far West Hydroelectric 
Project to the interconnection point located at Beale Air Force Base.
    m. In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's website at https://www.ferc.gov using 
the eLibrary link. Enter the docket number excluding the last three 
digits in the docket number field to access the document (i.e., P-
10821). At this time, the Commission has suspended access to the 
Commission's Public Reference Room, due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact FERC 
Online Support.
    All filings must (1) bear in all capital letters the title 
COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or 
PRESCRIPTIONS; (2) set forth in the heading the name of the applicant 
and the project number of the application to which the filing responds; 
(3) furnish the name, address, and telephone number of the person 
submitting the filing; and (4) otherwise comply with the requirements 
of 18 CFR 385.2001 through 385.2005. All comments, recommendations, 
terms and conditions or prescriptions must set forth their evidentiary 
basis and otherwise comply with the requirements of 18 CFR 4.34(b). 
Agencies may obtain copies of the application directly from the 
applicant. Each filing must be accompanied by proof of service on all 
persons listed on the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.
Deadline for Filing Comments, Recommendations, and Agency Terms and 
Conditions/Prescriptions September 28, 2020
Licensee's Reply to REA Comments November 11, 2020
Commission issues EA April 2021
Comments on EA May 2021
Commission issues license order October 2021

    Dated: July 29, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-16949 Filed 8-3-20; 8:45 am]
BILLING CODE 6717-01-P