Texas Eastern Transmission, LP; Notice of Schedule for Environmental Review of the Appalachia to Market Project, 45413-45414 [2020-16307]
Download as PDF
Federal Register / Vol. 85, No. 145 / Tuesday, July 28, 2020 / Notices
45413
FERC–510
Number of respondents 4
Annual
number of
responses per
respondent
Total number
of responses
Average burden hrs. & cost
($) per response
Total annual burden hrs. &
total annual cost
($)
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
15 ...........................................
1
15
80 hrs.; $6,400 .....................
1,200 hrs.; $96,000 ..............
$6,400
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: July 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–16303 Filed 7–27–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER20–2380–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Saint Solar, LLC; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced Saint Solar, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
4 Due to an improved staff estimate, the annual
number of respondents has been increased to 15
(rather than the estimated 8 included in the 60-day
notice, issued April 14, 2020).
VerDate Sep<11>2014
16:43 Jul 27, 2020
Jkt 250001
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is August 11,
2020.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
may mail similar pleadings to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426. Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
Dated: July 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–16309 Filed 7–27–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–436–000]
Texas Eastern Transmission, LP;
Notice of Schedule for Environmental
Review of the Appalachia to Market
Project
On May 1, 2020, Texas Eastern
Transmission, LP filed an application in
Docket No. CP20–436–000 requesting a
Certificate of Public Convenience and
Necessity pursuant to Section 7(c) of the
Natural Gas Act to construct and operate
certain natural gas pipeline facilities.
The proposed Project is known as the
Appalachia to Market Project (Project),
and would provide up to 18,000
dekatherms per day of firm natural gas
transportation service to UGI Utilities
Inc. at an existing delivery point near
Reading, Pennsylvania.
On May 11, 2020, the Federal Energy
Regulatory Commission (Commission or
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
Schedule for Environmental Review
Issuance of EA September 15, 2020
90-day Federal Authorization Decision
Deadline December 14, 2020
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
E:\FR\FM\28JYN1.SGM
28JYN1
45414
Federal Register / Vol. 85, No. 145 / Tuesday, July 28, 2020 / Notices
Project Description
The Appalachia to Market Project
would consist of the following facilities
and actions, all in Pennsylvania.
Specifically, Texas Eastern would
construct:
• Approximately 0.8 mile of 30-inchdiameter pipeline loop 1 in the sametrench as a segment of an abandoned 30inch-diameter pipe (that would be
removed for this project) on the Texas
Eastern system in Westmoreland
County;
• one crossover at the existing
Bechtelsville pig 2-launcher site in Berks
County;
• one crossover at the existing
Uniontown pig-receiver site in Fayette
County; and
• other related appurtenances.
Background
On May 18, 2020, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Appalachia to Market Project
and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers.
khammond on DSKJM1Z7X2PROD with NOTICES
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
docs-filing/ferconline.asp to register for
eSubscription.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP20–436), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
2 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
VerDate Sep<11>2014
16:43 Jul 27, 2020
Jkt 250001
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: July 22, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–16307 Filed 7–27–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG20–217–000.
Applicants: American Kings Solar,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of American Kings
Solar, LLC.
Filed Date: 7/22/20.
Accession Number: 20200722–5025.
Comments Due: 5 p.m. ET 8/12/20.
Docket Numbers: EG20–218–000.
Applicants: Rancho Seco Solar II LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Rancho Seco Solar
II LLC.
Filed Date: 7/22/20.
Accession Number: 20200722–5054.
Comments Due: 5 p.m. ET 8/12/20.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–1783–001.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Deficiency Response for Revisions to
PJM Tariff for NEET MidAtlantic
Indiana to be effective 12/31/9998.
Filed Date: 7/22/20.
Accession Number: 20200722–5028.
Comments Due: 5 p.m. ET 8/12/20.
Docket Numbers: ER20–2065–000;
ER20–2066–000.
Applicants: Antelope Expansion 3A,
LLC, Antelope Expansion 3B, LLC.
Description: Joint Supplement to June
16, 2020 Antelope Expansion 3A, LLC,
et al. tariff filings, et al.
Filed Date: 7/15/20.
Accession Number: 20200715–5173.
Comments Due: 5 p.m. ET 7/27/20.
Docket Numbers: ER20–2286–001.
Applicants: Southwest Power Pool,
Inc.
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
Description: Tariff Amendment:
2236R12 Golden Spread Electric
Cooperative, Inc. NITSA NOA Amended
to be effective 6/1/2020.
Filed Date: 7/22/20.
Accession Number: 20200722–5032.
Comments Due: 5 p.m. ET 8/12/20.
Docket Numbers: ER20–2465–000.
Applicants: Alcoa Power Generating
Inc.
Description: Tariff Cancellation:
Cancellation of APGI Transmission
Service Agreements to be effective 9/20/
2020.
Filed Date: 7/21/20.
Accession Number: 20200721–5132.
Comments Due: 5 p.m. ET 8/11/20.
Docket Numbers: ER20–2466–000.
Applicants: Alcoa Power Generating
Inc.
Description: § 205(d) Rate Filing:
Executed, Bilateral Transmission
Service Agreements for Native Load
Customers to be effective 9/20/2020.
Filed Date: 7/21/20.
Accession Number: 20200721–5133.
Comments Due: 5 p.m. ET 8/11/20.
Docket Numbers: ER20–2467–000.
Applicants: Alcoa Power Generating
Inc.
Description: § 205(d) Rate Filing:
Executed, Bilateral Transmission
Service Agreements for Native Load
Customers to be effective 9/20/2020.
Filed Date: 7/21/20.
Accession Number: 20200721–5135.
Comments Due: 5 p.m. ET 8/11/20.
Docket Numbers: ER20–2468–000.
Applicants: Alcoa Power Generating
Inc.
Description: § 205(d) Rate Filing:
Executed, Bilateral Transmission
Service Agreements for Native Load
Customers to be effective 9/20/2020.
Filed Date: 7/21/20.
Accession Number: 20200721–5127.
Comments Due: 5 p.m. ET 8/11/20.
Docket Numbers: ER20–2469–000.
Applicants: Mid-Atlantic Interstate
Transmission, LLC, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
MAIT submits ECSA No. 5647 to be
effective 9/20/2020.
Filed Date: 7/21/20.
Accession Number: 20200721–5136.
Comments Due: 5 p.m. ET 8/11/20.
Docket Numbers: ER20–2470–000.
Applicants: Carroll County Energy
LLC.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 7/23/2020.
Filed Date: 7/22/20.
Accession Number: 20200722–5037.
Comments Due: 5 p.m. ET 8/12/20.
Docket Numbers: ER20–2471–000.
E:\FR\FM\28JYN1.SGM
28JYN1
Agencies
[Federal Register Volume 85, Number 145 (Tuesday, July 28, 2020)]
[Notices]
[Pages 45413-45414]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-16307]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-436-000]
Texas Eastern Transmission, LP; Notice of Schedule for
Environmental Review of the Appalachia to Market Project
On May 1, 2020, Texas Eastern Transmission, LP filed an application
in Docket No. CP20-436-000 requesting a Certificate of Public
Convenience and Necessity pursuant to Section 7(c) of the Natural Gas
Act to construct and operate certain natural gas pipeline facilities.
The proposed Project is known as the Appalachia to Market Project
(Project), and would provide up to 18,000 dekatherms per day of firm
natural gas transportation service to UGI Utilities Inc. at an existing
delivery point near Reading, Pennsylvania.
On May 11, 2020, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA September 15, 2020
90-day Federal Authorization Decision Deadline December 14, 2020
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
[[Page 45414]]
Project Description
The Appalachia to Market Project would consist of the following
facilities and actions, all in Pennsylvania. Specifically, Texas
Eastern would construct:
Approximately 0.8 mile of 30-inch-diameter pipeline loop
\1\ in the same-trench as a segment of an abandoned 30-inch-diameter
pipe (that would be removed for this project) on the Texas Eastern
system in Westmoreland County;
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
one crossover at the existing Bechtelsville pig \2\-
launcher site in Berks County;
---------------------------------------------------------------------------
\2\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
one crossover at the existing Uniontown pig-receiver site
in Fayette County; and
other related appurtenances.
Background
On May 18, 2020, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed Appalachia to
Market Project and Request for Comments on Environmental Issues (NOI).
The NOI was sent to affected landowners; federal, state, and local
government agencies; elected officials; environmental and public
interest groups; Native American tribes; other interested parties; and
local libraries and newspapers.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to https://www.ferc.gov/docs-filing/ferconline.asp to register for eSubscription.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP20-436), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: July 22, 2020.