Texas Eastern Transmission, LP; Notice of Request Under Blanket Authorization, 44293-44294 [2020-15878]

Download as PDF Federal Register / Vol. 85, No. 141 / Wednesday, July 22, 2020 / Notices and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. jbell on DSKJLSW7X2PROD with NOTICES Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 18:11 Jul 21, 2020 Jkt 250001 website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached Mailing List Update Form (appendix 2). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP20–455). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/newsevents/events along with other related information. Dated: July 16, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–15877 Filed 7–21–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP20–494–000] Texas Eastern Transmission, LP; Notice of Request Under Blanket Authorization Take notice that on July 6, 2020, Texas Eastern Transmission, LP (Texas Eastern), 5400 Westheimer Court, Houston, Texas 77056, filed in Docket No. CP20–494–000 a prior notice request pursuant to sections 157.205 and 157.216 of the Commission’s regulations under the Natural Gas Act (NGA), and Texas Eastern’s blanket certificate issued in Docket No. CP82– 535–000, to abandon a supply lateral and related facilities located in offshore federal waters in the Gulf of Mexico near Louisiana. Specifically Texas Eastern intends to: (i) Abandon in place approximately 3.53 miles of its 12-inch Line 40–G–1 from milepost (MP) 0.00 in West Delta Block 87 to approximately MP 3.53 in West Delta Block 86, and (ii) PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 44293 abandon by removal metering and regulating (M&R) station 72137 and approximately 0.07 miles of connecting 12-inch Line 40–G–1 pipeline from MP 3.53 to MP 3.60 on Platform A, West Delta Block 86. (Line 40–G–1 Abandonment Project). In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application may be directed to Lisa A. Connolly, Director, Rates & Certificates, Texas Eastern Transmission, LP, P.O. Box 1642, Houston, Texas 77251–1642, by telephone at (713) 627–4102, by fax at (713) 627–5947, or by email at lisa.connolly@enbridge.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the E:\FR\FM\22JYN1.SGM 22JYN1 44294 Federal Register / Vol. 85, No. 141 / Wednesday, July 22, 2020 / Notices jbell on DSKJLSW7X2PROD with NOTICES Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters, will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFile link at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Dated: July 16, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–15878 Filed 7–21–20; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 18:11 Jul 21, 2020 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4428–011] Walden Hydro, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 4428–011. c. Date filed: May 29, 2020. d. Applicant: Walden Hydro, LLC. e. Name of Project: Walden Hydroelectric Project. f. Location: On the Wallkill River, in the Village of Walden, Orange County, New York. The project does not occupy any federal land. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)—825(r). h. Applicant Contact: Ms. Elise Anderson, Senior Environmental Permitting Specialist, Walden Hydro, LLC, Enel Green Power North America, Inc., 100 Brickstone Square, Suite 300, Andover, MA 01810; Phone at (978) 447–4408 or email at Elise.Anderson@ enel.com. i. FERC Contact: Samantha Pollak at (202) 502–6419, or samantha.pollak@ ferc.gov. j. Deadline for filing motions to intervene and protests: September 14, 2020. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted but is not ready for environmental analysis at this time. PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 l. The Walden Project consists of the following existing facilities: (1) A 417foot-long, V-shaped concrete dam topped with 2-foot-high flashboards; (2) an impoundment with a surface area of 69 acres at the normal pool elevation of 321.3 feet National Geodetic Vertical Datum of 1929 (NGVD29); (3) an intake structure consisting of a 252-foot-long, 56-foot-wide, 18-foot-deep canal forebay; (4) four 40-foot-long steel penstocks; (5) a 60-foot-long, 45-footwide, 29-foot-high powerhouse containing three horizontal doublerunner Francis turbine units with ratings of 980 kilowatts (kW), 630 kW, and 500 kW, respectively for a total rated capacity of 2,110 kW; (6) a 30-footlong, 37-foot-wide tailrace; (7) a 230foot-long bypassed reach consisting primarily of bedrock; (8) a transmission line; (9) a substation with a single-phase 12.5-kilovolt transformer; and (10) appurtenant facilities. The project operates in a run-of-river mode with a minimum flow of 31 cubic feet per second. The project has an average annual generation of 3,333 megawatt-hours between 2012 and 2019. m. The Commission provides all interested persons with an opportunity to view and/or print the EA via the internet through the Commission’s Home Page (https://www.ferc.gov) using the eLibrary link. Enter the docket number, excluding the last three digits in the docket number field, to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202) 502–8659. You may also register online at https://ferconline.ferc.gov/ eSubscription.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any protests or motions to intervene must be received E:\FR\FM\22JYN1.SGM 22JYN1

Agencies

[Federal Register Volume 85, Number 141 (Wednesday, July 22, 2020)]
[Notices]
[Pages 44293-44294]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15878]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP20-494-000]


Texas Eastern Transmission, LP; Notice of Request Under Blanket 
Authorization

    Take notice that on July 6, 2020, Texas Eastern Transmission, LP 
(Texas Eastern), 5400 Westheimer Court, Houston, Texas 77056, filed in 
Docket No. CP20-494-000 a prior notice request pursuant to sections 
157.205 and 157.216 of the Commission's regulations under the Natural 
Gas Act (NGA), and Texas Eastern's blanket certificate issued in Docket 
No. CP82-535-000, to abandon a supply lateral and related facilities 
located in offshore federal waters in the Gulf of Mexico near 
Louisiana. Specifically Texas Eastern intends to: (i) Abandon in place 
approximately 3.53 miles of its 12-inch Line 40-G-1 from milepost (MP) 
0.00 in West Delta Block 87 to approximately MP 3.53 in West Delta 
Block 86, and (ii) abandon by removal metering and regulating (M&R) 
station 72137 and approximately 0.07 miles of connecting 12-inch Line 
40-G-1 pipeline from MP 3.53 to MP 3.60 on Platform A, West Delta Block 
86. (Line 40-G-1 Abandonment Project).
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
eLibrary link. Enter the docket number excluding the last three digits 
in the docket number field to access the document. At this time, the 
Commission has suspended access to the Commission's Public Reference 
Room, due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions concerning this application may be directed to Lisa 
A. Connolly, Director, Rates & Certificates, Texas Eastern 
Transmission, LP, P.O. Box 1642, Houston, Texas 77251-1642, by 
telephone at (713) 627-4102, by fax at (713) 627-5947, or by email at 
[email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the

[[Page 44294]]

Commission staff's issuance of the final environmental impact statement 
(FEIS) or EA for this proposal. The filing of the EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commenters will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commenters, will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFile link at 
https://www.ferc.gov. Persons unable to file electronically may mail 
similar pleadings to the Federal Energy Regulatory Commission, 888 
First Street NE, Washington, DC 20426. Hand delivered submissions in 
docketed proceedings should be delivered to Health and Human Services, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.

    Dated: July 16, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-15878 Filed 7-21-20; 8:45 am]
BILLING CODE 6717-01-P