Northern Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Planned Northern Lights 2021 Expansion Project and Request for Comments on Environmental Issues, 44289-44291 [2020-15262]
Download as PDF
Federal Register / Vol. 85, No. 141 / Wednesday, July 22, 2020 / Notices
direct subsidiary of Dominion MLP
Holding.
DECP provides notification of a
planned transaction in which Berkshire
Hathaway Energy Company (BHE), an
Iowa corporation and a subsidiary of
Berkshire Hathaway Inc. (a Delaware
corporation), will acquire indirect
ownership and control of 100% of the
general partnership interests of DECP, as
well as 25% of DECP’s limited
partnership interests. DECP states that
50% of its limited partnership interest
will continue to be owned directly or
indirectly by DEI. Brookfield will
continue to own the remaining 25% of
DECP’s limited partnership interest
through Bowie Acquisitions LLC.
According to DECP, BHE is acquiring
these interests in DECP as part of a
larger transaction, with an enterprise
value of approximately $9.7 billion,
involving the acquisition by BHE of a
number of subsidiaries of DEI, pursuant
to a Purchase and Sale Agreement dated
as of July 3, 2020. DECP states that BHE
generally will have day-to-day
management and control of DECP. DECP
will remain the holder of the export
authorizations.
Additional details can be found in
DECP’s Notice, posted on the DOE/FE
website at: https://www.energy.gov/
sites/prod/files/2020/07/f76/DECP_
BHE_DOE_CIC_filing.pdf
DOE/FE Evaluation
DOE/FE will review DECP’s Notice in
accordance with its Procedures for
Changes in Control Affecting
Applications and Authorizations to
Import or Export Natural Gas (CIC
Procedures).1 Consistent with the CIC
Procedures, this notice addresses
DECP’s authorizations to export
liquefied natural gas (LNG) to non-free
trade agreement (non-FTA) countries,
granted in DOE/FE Order Nos. 3331–A 2
(FE Docket No. 11–128–LNG) and 4508
(FE Docket No. 19–156–LNG).3 If no
interested person protests the change in
control and DOE takes no action on its
own motion, the proposed change in
control will be deemed granted 30 days
after publication in the Federal
Register. If one or more protests are
submitted, DOE will review any
motions to intervene, protests, and
answers, and will issue a determination
1 79
FR 65541 (Nov. 5, 2014).
Order No. 3331 was subsequently
amended by DOE/FE Order Nos. 3331–B and 3331–
C.
3 DECP’s Notice also applies to its existing
authorizations to export LNG to FTA countries and
to import natural gas from various international
sources, but DOE/FE will respond to those portions
of the document separately pursuant to the CIC
Procedures, 79 FR 65542.
jbell on DSKJLSW7X2PROD with NOTICES
2 DOE/FE
VerDate Sep<11>2014
18:11 Jul 21, 2020
Jkt 250001
44289
as to whether the proposed change in
control has been demonstrated to render
the underlying authorization
inconsistent with the public interest.
intervention, and comments, will also
be available electronically by going to
the following DOE/FE Web address:
https://fossil.energy.gov/ng_regulation/.
Public Comment Procedures
Interested persons will be provided 15
days from the date of publication of this
notice in the Federal Register in order
to move to intervene, protest, and
answer DECP’s Notice.4 Protests,
motions to intervene, notices of
intervention, and written comments are
invited in response to this notice only
as to the change in control described in
DECP’s Notice. All protests, comments,
motions to intervene, or notices of
intervention must meet the
requirements specified by DOE’s
regulations in 10 CFR part 590.
Filings may be submitted using one of
the following methods: (1) Preferred
method: emailing the filing to fergas@
hq.doe.gov; (2) mailing an original and
three paper copies of the filing to the
Office of Regulation, Analysis, and
Engagement at the address listed in
ADDRESSES; or (3) hand delivering an
original and three paper copies of the
filing to the Office of Regulation,
Analysis, and Engagement at the
address listed in ADDRESSES. All filings
must include a reference to the
individual FE Docket Number(s) in the
title line, or Dominion Energy Cove
Point LNG, LP Change in Control in the
title line. Please Note: If submitting a
filing via email, please include all
related documents and attachments
(e.g., exhibits) in the original email
correspondence. Please do not include
any active hyperlinks or password
protection in any of the documents or
attachments related to the filing. All
electronic filings submitted to DOE
must follow these guidelines to ensure
that all documents are filed in a timely
manner. Any hardcopy filing submitted
greater in length than 50 pages must
also include, at the time of the filing, a
digital copy on disk of the entire
submission.
DECP’s Notice, and any filed protests,
motions to intervene, notices of
intervention, and comments, are
available for inspection and copying in
the Office of Regulation, Analysis, and
Engagement docket room, Room 3E–
042, 1000 Independence Avenue SW,
Washington, DC, 20585. The docket
room is open between the hours of 8:00
a.m. and 4:30 p.m., Monday through
Friday, except Federal holidays.
DECP’s Notice, and any filed protests,
motions to intervene, notices of
Signed in Washington, DC, on July 17,
2020.
Amy Sweeney,
Director, Office of Regulation, Analysis, and
Engagement, Office of Oil and Natural Gas.
4 Intervention, if granted, would constitute
intervention only in the change in control portion
of this proceeding, as described herein.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
[FR Doc. 2020–15894 Filed 7–21–20; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF20–1–000]
Northern Natural Gas Company; Notice
of Intent To Prepare an Environmental
Assessment for the Planned Northern
Lights 2021 Expansion Project and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Northern Lights 2021 Expansion
Project involving construction and
operation of facilities by Northern
Natural Gas Company (Northern) in
Dakota, Scott, Pine, Carleton, and
Morrison counties, Minnesota. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies about issues
regarding the project. The National
Environmental Policy Act (NEPA)
requires the Commission to take into
account the environmental impacts that
could result from its action whenever it
considers the issuance of a Certificate of
Public Convenience and Necessity.
NEPA also requires the Commission to
discover concerns the public may have
about proposals. This process is referred
to as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the EA on the important
environmental issues. By this notice, the
Commission requests public comments
on the scope of issues to address in the
EA. To ensure that your comments are
timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00 p.m.
Eastern Time on August 10, 2020.
You can make a difference by
submitting your specific comments or
E:\FR\FM\22JYN1.SGM
22JYN1
44290
Federal Register / Vol. 85, No. 141 / Wednesday, July 22, 2020 / Notices
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. Commission staff
will consider all filed comments during
the preparation of the EA.
If you sent comments on this project
to the Commission before the opening of
this docket on December 6, 2019, you
will need to file those comments in
Docket No. PF20–1 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, that approval conveys with
it the right of eminent domain.
Therefore, if you and the company do
not reach an easement agreement, the
pipeline company could initiate
condemnation proceedings in court. In
such instances, compensation would be
determined by a judge in accordance
with state law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC website (www.ferc.gov) under
the natural gas Landowner Topics link
(https://www.ferc.gov/industries-data/
natural-gas/natural-gas-projectlandownerstakeholder-topics-interest).
This fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
jbell on DSKJLSW7X2PROD with NOTICES
Public Participation
The Commission offers a free service
called eSubscription which makes it
easy to stay informed of all issuances
and submittals regarding the dockets/
projects to which you subscribe. These
instant email notifications are the fastest
way to receive notification and provide
a link to the document files which can
reduce the amount of time you spend
researching proceedings. Go to https://
VerDate Sep<11>2014
18:11 Jul 21, 2020
Jkt 250001
www.ferc.gov/ferc-online/
overviewtoregisterforeSubscription.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (PF20–1)
with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Summary of the Planned Project
Northern plans to construct a pipeline
loop 1 and a pipeline extension totaling
about 1.5 miles, replace a 425-foot-long
8-inch-diameter branch line with 12inch-diameter pipeline of the same
length, construct one new compressor
station, and add additional compression
at one existing compressor station, all
located in various counties in
Minnesota. According to Northern, the
planned facilities are required to serve
the firm transportation requirements of
its customers associated with increased
energy needs.
The Northern Lights 2021 Project
would consist of the following facilities:
• The Willmar D Branch Line
Extension (about 0.8 mile of 24-inchdiameter pipeline);
• the Carlton Interconnect Loop
(about 0.7 mile of 24-inch-diameter
pipeline);
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
• replacement of 425 feet of 8-inchdiameter pipeline on the Viking
Interconnect Branch Line with a 12inch-diameter branch line of the same
length;
• a new greenfield natural gas-fired
Hinckley Compressor Station, which
would include one 11,153-horsepower
natural gas-fired turbine, one gas
heating skid, and one natural gas-fired
backup electric generator;
• modifications of the Pierz
Compressor Station consisting of adding
an additional 1,100 horsepower electric
motor-driven compressor unit; and,
• appurtenant facilities including one
new pig 2 receiver and one new pig
launcher, and associated piping and
valves.
The general location of the project
facilities is shown in appendix 1.3
Land Requirements for Construction
Construction of the planned facilities
would disturb about 34.8 acres of land
for the aboveground facilities and the
pipeline. Following construction,
Northern would maintain about 14.4
acres for permanent operation of the
project facilities; the remaining acreage
would be restored and revert to former
uses. About 95 percent of the planned
pipeline routes parallel existing
pipeline, utility, or road rights-of-way.
The EA Process
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• socioeconomics;
• land use;
• air quality and noise;
• public safety; and
• cumulative impacts.
Commission staff will also evaluate
possible alternatives to the planned
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas.
2 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
3 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
E:\FR\FM\22JYN1.SGM
22JYN1
Federal Register / Vol. 85, No. 141 / Wednesday, July 22, 2020 / Notices
Although no formal application has
been filed, Commission staff has already
initiated a NEPA review under the
Commission’s pre-filing process. The
purpose of the pre-filing process is to
encourage early involvement of
interested stakeholders and to identify
and resolve issues before the
Commission receives an application. As
part of the pre-filing review,
Commission staff will contact Federal
and state agencies to discuss their
involvement in the scoping process and
the preparation of the EA.
The EA will present Commission
staff’s independent analysis of the
issues. The EA will be available in
electronic format in the public record
through eLibrary 4 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the EA is
issued. The EA may be issued for an
allotted public comment period.
Commission staff will consider all
comments on the EA before making
recommendations to the Commission.
To ensure Commission staff has the
opportunity to consider and address
your comments, please carefully follow
the instructions in the Public
Participation section, beginning on page
2.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues related to this
project to formally cooperate in the
preparation of the EA.5 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
jbell on DSKJLSW7X2PROD with NOTICES
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
4 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
5 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at title 40, Code of Federal
Regulations, § 1501.6.
VerDate Sep<11>2014
18:11 Jul 21, 2020
Jkt 250001
potential effects on historic properties.6
The EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
Environmental Mailing List
The environmental mailing list
includes Federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. Commission
staff will update the environmental
mailing list as the analysis proceeds to
ensure that Commission notices related
to this environmental review are sent to
all individuals, organizations, and
government entities interested in and/or
potentially affected by the planned
project.
If the Commission issues the EA for
an allotted public comment period, a
Notice of Availability of the EA will be
sent to the environmental mailing list
and will provide instructions to access
the electronic document on the FERC’s
website (www.ferc.gov). If you need to
make changes to your name/address, or
if you would like to remove your name
from the mailing list, please return the
attached ‘‘Mailing List Update Form’’
(appendix 2).
Becoming an Intervenor
Once Northern files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Only intervenors have the
right to seek rehearing of the
Commission’s decision and be heard by
the courts if they choose to appeal the
Commission’s final ruling. An
intervenor formally participates in the
proceeding by filing a request to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR 385.214). Motions
to intervene are more fully described at
https://www.ferc.gov/resources/guides/
how-to.asp. Please note that the
6 The Advisory Council on Historic Preservation
regulations are at title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
44291
Commission will not accept requests for
intervenor status at this time. You must
wait until the Commission receives a
formal application for the project, after
which the Commission will issue a
public notice that establishes an
intervention deadline.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field, excluding the last three digits (i.e.,
PF20–1). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/eventsalong with other related
information.
Dated: July 9, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–15262 Filed 7–21–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–455–000]
Freeport LNG Development, L.P., FLNG
Liquefaction, LLC, FLNG Liquefaction
2, LLC, FLNG Liquefaction 3, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Noble Gas Project, and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Noble Gas Project involving
construction and operation of facilities
by Freeport LNG Development, L.P.,
FLNG Liquefaction, LLC, FLNG
Liquefaction 2, LLC, and FLNG
Liquefaction 3, LLC (together referred to
as Freeport LNG) in Brazoria County,
Texas. The Commission will use this EA
E:\FR\FM\22JYN1.SGM
22JYN1
Agencies
[Federal Register Volume 85, Number 141 (Wednesday, July 22, 2020)]
[Notices]
[Pages 44289-44291]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15262]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF20-1-000]
Northern Natural Gas Company; Notice of Intent To Prepare an
Environmental Assessment for the Planned Northern Lights 2021 Expansion
Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Northern Lights 2021 Expansion
Project involving construction and operation of facilities by Northern
Natural Gas Company (Northern) in Dakota, Scott, Pine, Carleton, and
Morrison counties, Minnesota. The Commission will use this EA in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies about issues regarding the project. The National Environmental
Policy Act (NEPA) requires the Commission to take into account the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. NEPA also requires the Commission to discover concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of issues
to address in the EA. To ensure that your comments are timely and
properly recorded, please submit your comments so that the Commission
receives them in Washington, DC on or before 5:00 p.m. Eastern Time on
August 10, 2020.
You can make a difference by submitting your specific comments or
[[Page 44290]]
concerns about the project. Your comments should focus on the potential
environmental effects, reasonable alternatives, and measures to avoid
or lessen environmental impacts. Your input will help the Commission
staff determine what issues they need to evaluate in the EA. Commission
staff will consider all filed comments during the preparation of the
EA.
If you sent comments on this project to the Commission before the
opening of this docket on December 6, 2019, you will need to file those
comments in Docket No. PF20-1 to ensure they are considered as part of
this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, that approval conveys with it the right of
eminent domain. Therefore, if you and the company do not reach an
easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC website (www.ferc.gov) under the natural gas
Landowner Topics link (https://www.ferc.gov/industries-data/natural-gas/natural-gas-project-landownerstakeholder-topics-interest). This
fact sheet addresses a number of typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings.
Public Participation
The Commission offers a free service called eSubscription which
makes it easy to stay informed of all issuances and submittals
regarding the dockets/projects to which you subscribe. These instant
email notifications are the fastest way to receive notification and
provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overviewtoregisterforeSubscription.
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(PF20-1) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426.
Summary of the Planned Project
Northern plans to construct a pipeline loop \1\ and a pipeline
extension totaling about 1.5 miles, replace a 425-foot-long 8-inch-
diameter branch line with 12-inch-diameter pipeline of the same length,
construct one new compressor station, and add additional compression at
one existing compressor station, all located in various counties in
Minnesota. According to Northern, the planned facilities are required
to serve the firm transportation requirements of its customers
associated with increased energy needs.
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
The Northern Lights 2021 Project would consist of the following
facilities:
The Willmar D Branch Line Extension (about 0.8 mile of 24-
inch-diameter pipeline);
the Carlton Interconnect Loop (about 0.7 mile of 24-inch-
diameter pipeline);
replacement of 425 feet of 8-inch-diameter pipeline on the
Viking Interconnect Branch Line with a 12-inch-diameter branch line of
the same length;
a new greenfield natural gas-fired Hinckley Compressor
Station, which would include one 11,153-horsepower natural gas-fired
turbine, one gas heating skid, and one natural gas-fired backup
electric generator;
modifications of the Pierz Compressor Station consisting
of adding an additional 1,100 horsepower electric motor-driven
compressor unit; and,
appurtenant facilities including one new pig \2\ receiver
and one new pig launcher, and associated piping and valves.
---------------------------------------------------------------------------
\2\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
The general location of the project facilities is shown in appendix
1.\3\
---------------------------------------------------------------------------
\3\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE, Washington,
DC 20426, or call (202) 502-8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 34.8
acres of land for the aboveground facilities and the pipeline.
Following construction, Northern would maintain about 14.4 acres for
permanent operation of the project facilities; the remaining acreage
would be restored and revert to former uses. About 95 percent of the
planned pipeline routes parallel existing pipeline, utility, or road
rights-of-way.
The EA Process
The EA will discuss impacts that could occur as a result of the
construction and operation of the planned project under these general
headings:
Geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
socioeconomics;
land use;
air quality and noise;
public safety; and
cumulative impacts.
Commission staff will also evaluate possible alternatives to the
planned project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas.
[[Page 44291]]
Although no formal application has been filed, Commission staff has
already initiated a NEPA review under the Commission's pre-filing
process. The purpose of the pre-filing process is to encourage early
involvement of interested stakeholders and to identify and resolve
issues before the Commission receives an application. As part of the
pre-filing review, Commission staff will contact Federal and state
agencies to discuss their involvement in the scoping process and the
preparation of the EA.
The EA will present Commission staff's independent analysis of the
issues. The EA will be available in electronic format in the public
record through eLibrary \4\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the EA is issued. The EA
may be issued for an allotted public comment period. Commission staff
will consider all comments on the EA before making recommendations to
the Commission. To ensure Commission staff has the opportunity to
consider and address your comments, please carefully follow the
instructions in the Public Participation section, beginning on page 2.
---------------------------------------------------------------------------
\4\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues related to this project to formally cooperate in
the preparation of the EA.\5\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\5\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at title 40, Code of Federal
Regulations, Sec. 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\6\ The EA for this project will
document our findings on the impacts on historic properties and
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\6\ The Advisory Council on Historic Preservation regulations
are at title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes Federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. Commission staff will update the environmental
mailing list as the analysis proceeds to ensure that Commission notices
related to this environmental review are sent to all individuals,
organizations, and government entities interested in and/or potentially
affected by the planned project.
If the Commission issues the EA for an allotted public comment
period, a Notice of Availability of the EA will be sent to the
environmental mailing list and will provide instructions to access the
electronic document on the FERC's website (www.ferc.gov). If you need
to make changes to your name/address, or if you would like to remove
your name from the mailing list, please return the attached ``Mailing
List Update Form'' (appendix 2).
Becoming an Intervenor
Once Northern files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Only intervenors have the right to seek
rehearing of the Commission's decision and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene pursuant to Rule 214 of the Commission's Rules of Practice
and Procedures (18 CFR 385.214). Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to.asp. Please
note that the Commission will not accept requests for intervenor status
at this time. You must wait until the Commission receives a formal
application for the project, after which the Commission will issue a
public notice that establishes an intervention deadline.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field, excluding the last three digits (i.e.,
PF20-1). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/eventsalong with
other related information.
Dated: July 9, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-15262 Filed 7-21-20; 8:45 am]