Download as PDF 44066 Federal Register / Vol. 85, No. 140 / Tuesday, July 21, 2020 / Notices Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Dated: July 15, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–15716 Filed 7–20–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AC20–150–000] jbell on DSKJLSW7X2PROD with NOTICES Pacific Gas and Electric Company; Notice of Filing Take notice that on July 10, 2020, Pacific Gas and Electric Company submitted a request for authorization to modify the Allowance for Funds Used During Construction (AFUDC) rate in a manner that incorporates certain adjustments related to financing wildfire liability claims and contributions to California’s Wildfire Fund. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 or 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as VerDate Sep<11>2014 17:42 Jul 20, 2020 Jkt 250001 appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the eFilinglink at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Comment Date: 5 p.m. Eastern Time on August 5, 2020. Dated: July 15, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–15734 Filed 7–20–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–80–000] Columbia Gas Transmission, LLC; Notice of Request for Extension of Time Take notice that on July 8, 2020, Columbia Gas Transmission, LLC (Columbia) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time, until July 18, 2023, to complete the construction of the Eastern PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 Panhandle Expansion Project, as authorized in the July 19, 2018 Order Issuing Certificate (July 19 Order).1 The July 19 Order required Columbia to complete construction and make the facilities available for service within two years of the Order date. Columbia states that, due to unforeseen delays in acquiring an easement from the government of Maryland across the Western Maryland Rail Trail, additional time is now required in order to complete the construction of the authorized Project facilities. This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on Columbia’s request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).2 As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,3 the Commission will aim to issue an order acting on the request within 45 days.4 The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.5 The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission’s environmental analysis for the certificate complied with the National Environmental Policy Act.6 At the time 1 Columbia Gas Transmission, LLC, 164 FERC 61,036 (2018). 2 Only motions to intervene from entities that were party to the underlying proceeding will be accepted. Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 39 (2020). 3 Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2019). 4 Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40 (2020). 5 Id. at P 40. 6 Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether E:\FR\FM\21JYN1.SGM 21JYN1 Federal Register / Vol. 85, No. 140 / Tuesday, July 21, 2020 / Notices a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.7 The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the e-File link at https://www.ferc.gov. Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Comment Date: 5:00 p.m. Eastern Time on July 30, 2020. Dated: July 15, 2020. Kimberly D. Bose, Secretary. jbell on DSKJLSW7X2PROD with NOTICES [FR Doc. 2020–15732 Filed 7–20–20; 8:45 am] BILLING CODE 6717–01–P the Commission’s environmental analysis for the permit order complied with NEPA. 7 Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40 (2020). VerDate Sep<11>2014 17:42 Jul 20, 2020 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP20–493–000] Tennessee Gas Pipeline Company, L.L.C.; Notice of Application Take notice that on June 30, 2020, Tennessee Gas Pipeline Company, L.L.C. (Tennessee), 1001 Louisiana Street, Suite 1000, Houston, Texas 77002, filed in the above referenced docket an application pursuant to section 7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission’s regulations requesting authorization to (1) install one 11,107 horsepower (HP) gas-turbine driven compressor unit at its existing Compressor Station 321 in Susquehanna County, Pennsylvania; (2) install one 20,500 HP gas-turbine driven compressor unit at its existing Compressor Station 325 in Sussex County, New Jersey; and (3) construct the new 19,000 HP electric-driven Compressor Station 327 in Passaic County, New Jersey (East 300 Upgrade Project). The East 300 Upgrade Project would create 115,000 dekatherms per day of firm transportation service. Tennessee estimates the cost of the project to be approximately $246.3 million, all as more fully described in the application which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding this application should be directed to Ben Carranza, Director, Regulatory, Tennessee Gas Pipeline Company, L.L.C., 1001 Louisiana Street, Suite 1000, Houston, Texas 77002, by telephone at (713) 420–5535, or by emailing ben_carranza@ kindermorgan.com. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 44067 Pursuant to section 157.9 of the Commission’s rules (18 CFR 157.9), within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit five copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. E:\FR\FM\21JYN1.SGM 21JYN1

Agencies

[Federal Register Volume 85, Number 140 (Tuesday, July 21, 2020)]
[Notices]
[Pages 44066-44067]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15732]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-80-000]


Columbia Gas Transmission, LLC; Notice of Request for Extension 
of Time

    Take notice that on July 8, 2020, Columbia Gas Transmission, LLC 
(Columbia) requested that the Federal Energy Regulatory Commission 
(Commission) grant an extension of time, until July 18, 2023, to 
complete the construction of the Eastern Panhandle Expansion Project, 
as authorized in the July 19, 2018 Order Issuing Certificate (July 19 
Order).\1\ The July 19 Order required Columbia to complete construction 
and make the facilities available for service within two years of the 
Order date.
---------------------------------------------------------------------------

    \1\ Columbia Gas Transmission, LLC, 164 FERC 61,036 (2018).
---------------------------------------------------------------------------

    Columbia states that, due to unforeseen delays in acquiring an 
easement from the government of Maryland across the Western Maryland 
Rail Trail, additional time is now required in order to complete the 
construction of the authorized Project facilities.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on Columbia's request 
for an extension of time may do so. No reply comments or answers will 
be considered. If you wish to obtain legal status by becoming a party 
to the proceedings for this request, you should, on or before the 
comment date stated below, file a motion to intervene in accordance 
with the requirements of the Commission's Rules of Practice and 
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (18 CFR 157.10).\2\
---------------------------------------------------------------------------

    \2\ Only motions to intervene from entities that were party to 
the underlying proceeding will be accepted. Algonquin Gas 
Transmission, LLC, 170 FERC 61,144, at P 39 (2020).
---------------------------------------------------------------------------

    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for Natural 
Gas Act facilities when such requests are contested before order 
issuance. For those extension requests that are contested,\3\ the 
Commission will aim to issue an order acting on the request within 45 
days.\4\ The Commission will address all arguments relating to whether 
the applicant has demonstrated there is good cause to grant the 
extension.\5\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the 
Commission properly found the project to be in the public convenience 
and necessity and whether the Commission's environmental analysis for 
the certificate complied with the National Environmental Policy Act.\6\ 
At the time

[[Page 44067]]

a pipeline requests an extension of time, orders on certificates of 
public convenience and necessity are final and the Commission will not 
re-litigate their issuance.\7\ The OEP Director, or his or her 
designee, will act on all of those extension requests that are 
uncontested.
---------------------------------------------------------------------------

    \3\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
    \4\ Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40 
(2020).
    \5\ Id. at P 40.
    \6\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \7\ Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://www.ferc.gov) using 
the eLibrary link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to Commission's Public Reference 
Room, due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the e-File link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and three copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.
    Comment Date: 5:00 p.m. Eastern Time on July 30, 2020.

    Dated: July 15, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-15732 Filed 7-20-20; 8:45 am]
BILLING CODE 6717-01-P