Combined Notice of Filings #1, 43833-43835 [2020-15607]
Download as PDF
Federal Register / Vol. 85, No. 139 / Monday, July 20, 2020 / Notices
those facilities because they are directly
associated with natural gas deliveries to
the Mountain Valley Pipeline Project.
On March 5, 2020, the Commission
granted Equitrans’ request for a variance
to abandon-in-place several existing
facilities that were approved for removal
at the Pratt Compressor Station in order
to reduce ground disturbance.
Specifically, the variance permits
Equitrans to abandon-in-place the
H–117 pipeline receiver; the D–497
pipeline pig launcher and associated
appurtenances; five buildings, including
storage buildings, an office building, an
electronics building, and the main water
service building; a garage; and the
foundation floor of the building housing
the old Pratt compressor units.
Equitrans has experienced delays
related to extra safety precautions taken
due to the age of the building and
equipment, safeguards taken with
removal of the compressor building to
ensure safety in direct vicinity of
remaining equipment at the station, and
the inefficiencies directly related to the
newly developed processes as it relates
to the COVID–19 pandemic. To date, the
following facilities remain to be
removed from the site: (a) 2,200 linear
feet of piping; (b) six vessels; (c) five
coolers; (d) compressor building
basement; and (e) five compressors.
Thus, Equitrans seeks additional time
until December 1, 2020 to complete this
work.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Equitrans’ request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).2
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
2 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
VerDate Sep<11>2014
18:30 Jul 17, 2020
Jkt 250001
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFile’’ link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on July 29, 2020.
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
43833
Dated: July 14, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–15627 Filed 7–17–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC20–81–000.
Applicants: Fowler Ridge Wind Farm
LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Fowler
Ridge Wind Farm LLC.
Filed Date: 7/13/20.
Accession Number: 20200713–5225.
Comments Due: 5 p.m. ET 8/3/20.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG20–208–000.
Applicants: Reloj del Sol Wind Farm
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Reloj del Sol Wind
Farm LLC.
Filed Date: 7/14/20.
Accession Number: 20200714–5029.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20–209–000.
Applicants: Wildcat Creek Wind Farm
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Wildcat Creek Wind
Farm LLC.
Filed Date: 7/14/20.
Accession Number: 20200714–5030.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20–210–000.
Applicants: Copper Mountain Solar 5,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status.
Filed Date: 7/14/20.
Accession Number: 20200714–5077.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20–211–000.
Applicants: Battle Mountain SP, LLC.
Description: Self-Certification of EG of
Battle Mountain SP, LLC.
Filed Date: 7/14/20.
Accession Number: 20200714–5082.
Comments Due: 5 p.m. ET 8/4/20.
Take notice that the Commission
received the following electric rate
filings:
E:\FR\FM\20JYN1.SGM
20JYN1
43834
Federal Register / Vol. 85, No. 139 / Monday, July 20, 2020 / Notices
Docket Numbers: ER14–1421–005.
Applicants: Diamond State
Generation Partners, LLC.
Description: Report Filing: Refund
Report [ER14–1421 and EL19–74] to be
effective N/A.
Filed Date: 7/14/20.
Accession Number: 20200714–5090.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER19–1904–001.
Applicants: Nevada Power Company.
Description: Compliance filing: OATT
Revision Attachment N 07.13.20 to be
effective 5/22/2019.
Filed Date: 7/13/20.
Accession Number: 20200713–5240.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER19–2165–002.
Applicants: Western Interconnect
LLC.
Description: Compliance filing: Order
Nos. 845 and 845–A Compliance (ER19–
2165-) Filing to be effective 5/22/2019.
Filed Date: 7/13/20.
Accession Number: 20200713–5204.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–1683–001.
Applicants: Wabash Valley Power
Association, Inc.
Description: Tariff Amendment: Filing
of Distributed Generation Policy D–11—
Response to Deficiency Letter to be
effective 7/14/2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5028.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–1747–001.
Applicants: South Fork Wind, LLC.
Description: Compliance filing: South
Fork Compliance Filing to be effective
7/8/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5193.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–1748–001.
Applicants: Ewington Energy
Systems, LLC.
Description: Compliance filing:
Ewington Energys Compliance Filing to
be effective 7/8/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5201.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2403–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original WMPA, Service Agreement No.
5694; Queue No. AF1–022 to be
effective 6/11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5215.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2404–000.
Applicants: Midwest Generation, LLC.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 7/14/2020.
VerDate Sep<11>2014
18:30 Jul 17, 2020
Jkt 250001
Filed Date: 7/13/20.
Accession Number: 20200713–5219.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2405–000.
Applicants: Oswego Harbor Power
LLC.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 7/14/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5221.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2406–000.
Applicants: Vienna Power LLC.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 7/14/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5223.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2407–000.
Applicants: Puget Sound Energy, Inc.
Description: § 205(d) Rate Filing: City
of Seattle Tolt River Agreements to be
effective 7/1/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5224.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2408–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2020–
07–13 SA 3524 Ameren-Broadlands
Wind Farm FSA for FCA (J468) to be
effective 10/1/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5227.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2409–000.
Applicants: Louisville Gas and
Electric Company.
Description: § 205(d) Rate Filing:
Interconnection Agreement with OVEC
to be effective 9/11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5235.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2410–000.
Applicants: Kentucky Utilities
Company.
Description: § 205(d) Rate Filing: KU
Concurrence OVEC IA to be effective 9/
11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713–5244.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20–2411–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2020–
07–14_SA 2959 NSP-Stoneray Power
Partners 2nd Rev GIA (J426) to be
effective 12/31/9998.
Filed Date: 7/14/20.
Accession Number: 20200714–5037.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–2412–000.
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2020–
07–14_SA 3513 NSP-Stoneray Power
Partners FSA (J426) to be effective 6/30/
2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5038.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–2413–000.
Applicants: Ohio Valley Electric
Corporation.
Description: § 205(d) Rate Filing:
Certificate of Concurrence for
Transmission Interconnection
Agreement to be effective 9/11/2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5039.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–2414–000.
Applicants: Moss Landing Energy
Storage 1, LLC.
Description: Baseline eTariff Filing:
Baseline New to be effective 9/13/2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5045.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–2415–000.
Applicants: Moss Landing Energy
Storage 2, LLC.
Description: Baseline eTariff Filing:
Baseline New to be effective 9/13/2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5046.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20–2416–000.
Applicants: Northern States Power
Company, a Minnesota corporation.
Description: § 205(d) Rate Filing:
2020–07–14 NSP–SHKP–SISA–678–
0.0.0 to be effective 7/15/2020.
Filed Date: 7/14/20.
Accession Number: 20200714–5068.
Comments Due: 5 p.m. ET 8/4/20.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
E:\FR\FM\20JYN1.SGM
20JYN1
Federal Register / Vol. 85, No. 139 / Monday, July 20, 2020 / Notices
Dated: July 14, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–15607 Filed 7–17–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14851–001]
White Pine Waterpower, LLC; Notice of
Intent To File License Application,
Filing of Pre-Application Document,
and Approving Use of The Traditional
Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 14851–001.
c. Date Filed: May 15, 2020.
d. Submitted By: White Pine
Waterpower, LLC.
e. Name of Project: White Pine
Pumped Storage Project.
f. Location: About 8 miles northeast of
the city of Ely, in White Pine County,
Nevada. The project would occupy
approximately 916.33 acres of Bureau of
Land Management land.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Applicant Contact: Matthew
Shapiro, Chief Executive Officer, White
Pine Waterpower, LLC, c/o rPlus
Energies, 800 W. Main St., Ste. 1220,
Boise, ID 83702; (208) 246–9925;
mshapiro@gridflexenergy.com.
i. FERC Contact: Shannon Boyle at
(202) 502–8417 or shannon.boyle@
ferc.gov.
j. White Pine Waterpower, LLC (White
Pine) filed its request to use the
Traditional Licensing Process on May
15, 2020. White Pine provided public
notice of its request on May 15, 2020.
In a letter dated July 13, 2020, the
Director of the Division of Hydropower
Licensing approved White Pine’s
request to use the Traditional Licensing
Process.
k. With this notice, we are designating
White Pine Waterpower, LLC as the
Commission’s non-federal
representative for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act, and section
106 of the National Historic
Preservation Act.
l. White Pine filed a Pre-Application
Document (PAD; including a proposed
process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
m. A copy of the PAD may be viewed
on the Commission’s website (https://
VerDate Sep<11>2014
18:30 Jul 17, 2020
Jkt 250001
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
n. The applicant states its
unequivocal intent to submit an
application for an original license for
Project No. 14851–001.
o. Register online at https://
ferconline.ferc.gov/eSubscription.aspx
to be notified via email of new filing
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
Dated: July 13, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–15576 Filed 7–17–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–193–000]
Columbia Gulf Transmission, LLC;
Notice of Request for Extension of
Time
Take notice that on July 7, 2020,
Columbia Gulf Transmission, LLC
(Columbia Gulf) requested that the
Federal Energy Regulatory Commission
(Commission) grant an extension of
time, until November 15, 2021, in order
to place the replacement facilities of the
Mainline 100 and Mainline 200
Replacement Project (Project) into
service, in Menifee and Montgomery
Counties, Kentucky, as authorized as
part of Columbia Gulf’s Project in the
November 15, 2019 Order Granting
Certificate and Approving
Abandonment 1 (November 15 Order).
The November 15 Order required
Columbia Gulf to complete construction
and make the facilities available for
service within one year of the order
date. Columbia Gulf states that, due to
increased population density in the area
along certain discrete sections of
Mainline 100 and Mainline 200,
1 Columbia Gulf Transmission, LLC, 169 FERC
¶ 62,084 (2019).
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
43835
Columbia Gulf is required, pursuant to
Part 192 of the U.S. Department of
Transportation (DOT) regulations,2 to
remediate the pipelines to allow
continued operation at the current
maximum allowable operating pressures
(MAOP). Columbia Gulf states that, as
provided by 49 CFR 190.341 Special
Permit, an operator of a pipeline may
submit an application for a special
permit, and provided that certain
conditions are met, the DOT may waive
compliance from the regulations for
specific natural gas transmission
pipeline segments. If granted, the
special permit allows the operator to
continue to operate each special permit
segment at its current MAOP without
first performing remediation work.
Columbia Gulf states that, on October
15, 2019, Columbia Gulf applied for a
special permit under the circumstances
that the class location changed due to
development usage of land near the
pipeline. Columbia Gulf anticipates that
a determination from DOT on its special
permit application may not be received
until after the November 15, 2020 inservice deadline stipulated in the
November 15 Order. If the Commissions
grants Columbia Gulf’s request for an
extension of time, Columbia would take
one of the following actions based on
whether it receives a special permit
from DOT. If Columbia Gulf received
the special permit, Columbia Gulf
would submit a motion to vacate the
authorization granted in the November
15 Order. If Columbia Gulf doesn’t
obtain the special permit, Columbia
Gulf would notify the Commission of its
intent to begin construction of the
Project and submit a revision to its
Implementation Plan reflecting an
updated construction schedule.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Columbia Gulf’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).3
As a matter of practice, the
Commission itself generally acts on
2 49
CFR 192.611 (2020).
motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
3 Only
E:\FR\FM\20JYN1.SGM
20JYN1
Agencies
[Federal Register Volume 85, Number 139 (Monday, July 20, 2020)]
[Notices]
[Pages 43833-43835]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15607]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC20-81-000.
Applicants: Fowler Ridge Wind Farm LLC.
Description: Application for Authorization Under Section 203 of the
Federal Power Act, et al. of Fowler Ridge Wind Farm LLC.
Filed Date: 7/13/20.
Accession Number: 20200713-5225.
Comments Due: 5 p.m. ET 8/3/20.
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG20-208-000.
Applicants: Reloj del Sol Wind Farm LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Reloj del Sol Wind Farm LLC.
Filed Date: 7/14/20.
Accession Number: 20200714-5029.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20-209-000.
Applicants: Wildcat Creek Wind Farm LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Wildcat Creek Wind Farm LLC.
Filed Date: 7/14/20.
Accession Number: 20200714-5030.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20-210-000.
Applicants: Copper Mountain Solar 5, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status.
Filed Date: 7/14/20.
Accession Number: 20200714-5077.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: EG20-211-000.
Applicants: Battle Mountain SP, LLC.
Description: Self-Certification of EG of Battle Mountain SP, LLC.
Filed Date: 7/14/20.
Accession Number: 20200714-5082.
Comments Due: 5 p.m. ET 8/4/20.
Take notice that the Commission received the following electric
rate filings:
[[Page 43834]]
Docket Numbers: ER14-1421-005.
Applicants: Diamond State Generation Partners, LLC.
Description: Report Filing: Refund Report [ER14-1421 and EL19-74]
to be effective N/A.
Filed Date: 7/14/20.
Accession Number: 20200714-5090.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER19-1904-001.
Applicants: Nevada Power Company.
Description: Compliance filing: OATT Revision Attachment N 07.13.20
to be effective 5/22/2019.
Filed Date: 7/13/20.
Accession Number: 20200713-5240.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER19-2165-002.
Applicants: Western Interconnect LLC.
Description: Compliance filing: Order Nos. 845 and 845-A Compliance
(ER19-2165-) Filing to be effective 5/22/2019.
Filed Date: 7/13/20.
Accession Number: 20200713-5204.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-1683-001.
Applicants: Wabash Valley Power Association, Inc.
Description: Tariff Amendment: Filing of Distributed Generation
Policy D-11--Response to Deficiency Letter to be effective 7/14/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5028.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-1747-001.
Applicants: South Fork Wind, LLC.
Description: Compliance filing: South Fork Compliance Filing to be
effective 7/8/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5193.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-1748-001.
Applicants: Ewington Energy Systems, LLC.
Description: Compliance filing: Ewington Energys Compliance Filing
to be effective 7/8/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5201.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2403-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original WMPA, Service
Agreement No. 5694; Queue No. AF1-022 to be effective 6/11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5215.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2404-000.
Applicants: Midwest Generation, LLC.
Description: Sec. 205(d) Rate Filing: Market-Based Rate Tariff
Revisions to be effective 7/14/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5219.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2405-000.
Applicants: Oswego Harbor Power LLC.
Description: Sec. 205(d) Rate Filing: Market-Based Rate Tariff
Revisions to be effective 7/14/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5221.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2406-000.
Applicants: Vienna Power LLC.
Description: Sec. 205(d) Rate Filing: Market-Based Rate Tariff
Revisions to be effective 7/14/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5223.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2407-000.
Applicants: Puget Sound Energy, Inc.
Description: Sec. 205(d) Rate Filing: City of Seattle Tolt River
Agreements to be effective 7/1/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5224.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2408-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Compliance filing: 2020-07-13 SA 3524 Ameren-
Broadlands Wind Farm FSA for FCA (J468) to be effective 10/1/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5227.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2409-000.
Applicants: Louisville Gas and Electric Company.
Description: Sec. 205(d) Rate Filing: Interconnection Agreement
with OVEC to be effective 9/11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5235.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2410-000.
Applicants: Kentucky Utilities Company.
Description: Sec. 205(d) Rate Filing: KU Concurrence OVEC IA to be
effective 9/11/2020.
Filed Date: 7/13/20.
Accession Number: 20200713-5244.
Comments Due: 5 p.m. ET 8/3/20.
Docket Numbers: ER20-2411-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Compliance filing: 2020-07-14_SA 2959 NSP-Stoneray
Power Partners 2nd Rev GIA (J426) to be effective 12/31/9998.
Filed Date: 7/14/20.
Accession Number: 20200714-5037.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-2412-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Compliance filing: 2020-07-14_SA 3513 NSP-Stoneray
Power Partners FSA (J426) to be effective 6/30/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5038.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-2413-000.
Applicants: Ohio Valley Electric Corporation.
Description: Sec. 205(d) Rate Filing: Certificate of Concurrence
for Transmission Interconnection Agreement to be effective 9/11/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5039.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-2414-000.
Applicants: Moss Landing Energy Storage 1, LLC.
Description: Baseline eTariff Filing: Baseline New to be effective
9/13/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5045.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-2415-000.
Applicants: Moss Landing Energy Storage 2, LLC.
Description: Baseline eTariff Filing: Baseline New to be effective
9/13/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5046.
Comments Due: 5 p.m. ET 8/4/20.
Docket Numbers: ER20-2416-000.
Applicants: Northern States Power Company, a Minnesota corporation.
Description: Sec. 205(d) Rate Filing: 2020-07-14 NSP-SHKP-SISA-
678-0.0.0 to be effective 7/15/2020.
Filed Date: 7/14/20.
Accession Number: 20200714-5068.
Comments Due: 5 p.m. ET 8/4/20.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
[[Page 43835]]
Dated: July 14, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-15607 Filed 7-17-20; 8:45 am]
BILLING CODE 6717-01-P