Tennessee Gas Pipeline Company, LLC, Southern Natural Gas Company, LLC; Notice of Revised Schedule for Environmental Review of the Evangeline Pass Expansion Project, 42851 [2020-15266]
Download as PDF
Federal Register / Vol. 85, No. 136 / Wednesday, July 15, 2020 / Notices
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: July 7, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–15042 Filed 7–14–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP20–50–000; CP20–51–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Tennessee Gas Pipeline Company,
LLC, Southern Natural Gas Company,
LLC; Notice of Revised Schedule for
Environmental Review of the
Evangeline Pass Expansion Project
This notice identifies the Federal
Energy Regulatory Commission staff’s
revised schedule for the completion of
the environmental assessment (EA) for
Tennessee Gas Pipeline Company LLC’s
(Tennessee) and Southern Natural Gas
Company LLC’s (SNG) Evangeline Pass
Expansion Project. The first notice of
schedule, issued on April 3, 2020,
identified July 27, 2020 as the EA
issuance date. On April 13, 2020 and
June 12, 2020, FERC staff requested
additional environmental information to
assist in its EA analysis regarding pile
driving and associated noise and
vibration impacts on aquatic species,
including essential fish habitat and
threatened and endangered species;
floodplain development; and horizontal
directional drilling. Tennessee filed a
portion of the requested information on
June 30, 2020 and stated that the
additional information would be filed
on July 14, 2020. To provide appropriate
time to review and complete the
analysis of the necessary supplemental
information, Commission staff has
revised the schedule for issuance of the
EA, as described below.
Schedule for Environmental Review
Issuance of EA—August 24, 2020
VerDate Sep<11>2014
17:59 Jul 14, 2020
Jkt 250001
90-day Federal Authorization Decision
Deadline—November 23, 2020
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
ferc-online/overview to register for
eSubscription.
Additional information about the
project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, enter the ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP20–50 or CP20–51), select a date
range, and follow the instructions. For
assistance with access to eLibrary, the
helpline can be reached at (866) 208–
3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: July 9, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–15266 Filed 7–14–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–490–000]
Columbia Gulf Transmission, LLC;
Notice of Application
Take notice that on June 30, 2020,
Columbia Gulf Transmission, LLC, 700
Louisiana Street, Suite 700, Houston,
Texas 77002, filed an application
pursuant to section 7(c) and 7(b) of the
Natural Gas Act (NGA) and, Part 157 of
the Commission’s regulations for
authority to implement its Mainline 300
Replacement Project (Replacement
Project). The Replacement Project
consists of the abandonment and
replacement of two segments of the 36-
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
42851
inch-diameter Mainline 300 totaling
approximately 775 feet. The
Replacement Project is located in
(Menifee and Montgomery Counties,
Kentucky), all as more fully set forth in
the application which is on file with the
Commission and open to public
inspection. The filing is available for
review on the Commission’s website
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TYY, (202)
502–8659. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020.
Any questions concerning this
application may be directed to Dave
Hammel, Columbia Gulf Transmission,
LLC, 700 Louisiana Street, Suite 700,
Houston, TX 77002–2700, 832.320.5861,
dave_hammel@tcenergy.com
Pursuant to section 157.9 of the
Commission’s rules (18 CFR 157.9),
within 90 days of this Notice, the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
E:\FR\FM\15JYN1.SGM
15JYN1
Agencies
[Federal Register Volume 85, Number 136 (Wednesday, July 15, 2020)]
[Notices]
[Page 42851]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15266]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP20-50-000; CP20-51-000]
Tennessee Gas Pipeline Company, LLC, Southern Natural Gas
Company, LLC; Notice of Revised Schedule for Environmental Review of
the Evangeline Pass Expansion Project
This notice identifies the Federal Energy Regulatory Commission
staff's revised schedule for the completion of the environmental
assessment (EA) for Tennessee Gas Pipeline Company LLC's (Tennessee)
and Southern Natural Gas Company LLC's (SNG) Evangeline Pass Expansion
Project. The first notice of schedule, issued on April 3, 2020,
identified July 27, 2020 as the EA issuance date. On April 13, 2020 and
June 12, 2020, FERC staff requested additional environmental
information to assist in its EA analysis regarding pile driving and
associated noise and vibration impacts on aquatic species, including
essential fish habitat and threatened and endangered species;
floodplain development; and horizontal directional drilling. Tennessee
filed a portion of the requested information on June 30, 2020 and
stated that the additional information would be filed on July 14, 2020.
To provide appropriate time to review and complete the analysis of the
necessary supplemental information, Commission staff has revised the
schedule for issuance of the EA, as described below.
Schedule for Environmental Review
Issuance of EA--August 24, 2020
90-day Federal Authorization Decision Deadline--November 23, 2020
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Additional information about the project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the eLibrary link, enter the
``Docket Number'' excluding the last three digits (i.e., CP20-50 or
CP20-51), select a date range, and follow the instructions. For
assistance with access to eLibrary, the helpline can be reached at
(866) 208-3676, TTY (202) 502-8659, or at [email protected].
The eLibrary link on the FERC website also provides access to the texts
of formal documents issued by the Commission, such as orders, notices,
and rule makings.
Dated: July 9, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-15266 Filed 7-14-20; 8:45 am]
BILLING CODE 6717-01-P