Tennessee Gas Pipeline Company, LLC, Southern Natural Gas Company, LLC; Notice of Revised Schedule for Environmental Review of the Evangeline Pass Expansion Project, 42851 [2020-15266]

Download as PDF Federal Register / Vol. 85, No. 136 / Wednesday, July 15, 2020 / Notices Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified date(s). Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 7, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–15042 Filed 7–14–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP20–50–000; CP20–51–000] khammond on DSKJM1Z7X2PROD with NOTICES Tennessee Gas Pipeline Company, LLC, Southern Natural Gas Company, LLC; Notice of Revised Schedule for Environmental Review of the Evangeline Pass Expansion Project This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for Tennessee Gas Pipeline Company LLC’s (Tennessee) and Southern Natural Gas Company LLC’s (SNG) Evangeline Pass Expansion Project. The first notice of schedule, issued on April 3, 2020, identified July 27, 2020 as the EA issuance date. On April 13, 2020 and June 12, 2020, FERC staff requested additional environmental information to assist in its EA analysis regarding pile driving and associated noise and vibration impacts on aquatic species, including essential fish habitat and threatened and endangered species; floodplain development; and horizontal directional drilling. Tennessee filed a portion of the requested information on June 30, 2020 and stated that the additional information would be filed on July 14, 2020. To provide appropriate time to review and complete the analysis of the necessary supplemental information, Commission staff has revised the schedule for issuance of the EA, as described below. Schedule for Environmental Review Issuance of EA—August 24, 2020 VerDate Sep<11>2014 17:59 Jul 14, 2020 Jkt 250001 90-day Federal Authorization Decision Deadline—November 23, 2020 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. Additional information about the project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, enter the ‘‘Docket Number’’ excluding the last three digits (i.e., CP20–50 or CP20–51), select a date range, and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208– 3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: July 9, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–15266 Filed 7–14–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP20–490–000] Columbia Gulf Transmission, LLC; Notice of Application Take notice that on June 30, 2020, Columbia Gulf Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, Texas 77002, filed an application pursuant to section 7(c) and 7(b) of the Natural Gas Act (NGA) and, Part 157 of the Commission’s regulations for authority to implement its Mainline 300 Replacement Project (Replacement Project). The Replacement Project consists of the abandonment and replacement of two segments of the 36- PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 42851 inch-diameter Mainline 300 totaling approximately 775 feet. The Replacement Project is located in (Menifee and Montgomery Counties, Kentucky), all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review on the Commission’s website web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TYY, (202) 502–8659. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. Any questions concerning this application may be directed to Dave Hammel, Columbia Gulf Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, TX 77002–2700, 832.320.5861, dave_hammel@tcenergy.com Pursuant to section 157.9 of the Commission’s rules (18 CFR 157.9), within 90 days of this Notice, the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 E:\FR\FM\15JYN1.SGM 15JYN1

Agencies

[Federal Register Volume 85, Number 136 (Wednesday, July 15, 2020)]
[Notices]
[Page 42851]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15266]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP20-50-000; CP20-51-000]


Tennessee Gas Pipeline Company, LLC, Southern Natural Gas 
Company, LLC; Notice of Revised Schedule for Environmental Review of 
the Evangeline Pass Expansion Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Tennessee Gas Pipeline Company LLC's (Tennessee) 
and Southern Natural Gas Company LLC's (SNG) Evangeline Pass Expansion 
Project. The first notice of schedule, issued on April 3, 2020, 
identified July 27, 2020 as the EA issuance date. On April 13, 2020 and 
June 12, 2020, FERC staff requested additional environmental 
information to assist in its EA analysis regarding pile driving and 
associated noise and vibration impacts on aquatic species, including 
essential fish habitat and threatened and endangered species; 
floodplain development; and horizontal directional drilling. Tennessee 
filed a portion of the requested information on June 30, 2020 and 
stated that the additional information would be filed on July 14, 2020. 
To provide appropriate time to review and complete the analysis of the 
necessary supplemental information, Commission staff has revised the 
schedule for issuance of the EA, as described below.

Schedule for Environmental Review

Issuance of EA--August 24, 2020
90-day Federal Authorization Decision Deadline--November 23, 2020

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    Additional information about the project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, enter the 
``Docket Number'' excluding the last three digits (i.e., CP20-50 or 
CP20-51), select a date range, and follow the instructions. For 
assistance with access to eLibrary, the helpline can be reached at 
(866) 208-3676, TTY (202) 502-8659, or at [email protected]. 
The eLibrary link on the FERC website also provides access to the texts 
of formal documents issued by the Commission, such as orders, notices, 
and rule makings.

    Dated: July 9, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-15266 Filed 7-14-20; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.