Pick-Sloan Missouri Basin Program-Eastern Division-Rate Order No. WAPA-188, 42384-42397 [2020-15173]
Download as PDF
42384
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
five copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of meetings associated with the
Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
As of the February 27, 2018 date of
the Commission’s order in Docket No.
CP16–4–001, the Commission will
apply its revised practice concerning
out-of-time motions to intervene in any
new NGA section 3 or section 7
proceeding.1 Persons desiring to become
a party to a certificate proceeding are to
intervene in a timely manner. If seeking
to intervene out-of-time, the movant is
required to ‘‘show good cause why the
time limitation should be waived,’’ and
should provide justification by reference
to factors set forth in Rule 214(d)(1) of
the Commission’s Rules and
Regulations.2
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to U.S.
Department of Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on July 28, 2020.
Dated: July 7, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–15043 Filed 7–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER20–2179–000]
Baldwin Wind Energy, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Baldwin
Wind Energy, LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is July 28,
2020.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
1 Tennessee Gas Pipeline Company, L.L.C., 162
FERC ¶ 61,167 at ¶ 50 (2018).
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
PO 00000
2 18
CFR 385.214(d)(1).
Frm 00039
Fmt 4703
Sfmt 4703
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
may mail similar pleadings to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426. Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Dated: July 8, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–15157 Filed 7–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Pick-Sloan Missouri Basin Program—
Eastern Division-Rate Order No.
WAPA–188
Western Area Power
Administration, DOE.
ACTION: Notice of rate order concerning
transmission and ancillary services
formula rates.
AGENCY:
The Assistant Secretary for
Electricity confirms, approves, and
places into effect, on an interim basis,
the formula rates for the Pick-Sloan
Missouri Basin Program—Eastern
Division (P–SMBP—ED) transmission
SUMMARY:
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
and ancillary services (Provisional
Formula Rates). These rates will be used
by Western Area Power
Administration’s (WAPA) Upper Great
Plains Region (UGP) to provide rate data
to Southwest Power Pool, Inc. (SPP), the
Regional Transmission Organization of
which UGP is a member. These new
formula rates replace the existing
transmission and ancillary services
formula rates under Rate Order No.
WAPA–170 that expire on September
30, 2020.
The Provisional Formula Rates
under Rate Schedules WAUGP–ATRR,
WAUGP–AS1, WAUW–AS3, WAUW–
AS4, WAUW–AS5, WAUW–AS6 and
WAUW–AS7 are effective October 1,
2020, and will remain in effect through
September 30, 2025, pending
confirmation and approval by the
Federal Energy Regulatory Commission
(FERC) on a final basis or until
superseded.
DATES:
Mr.
Jody Sundsted, Regional Manager,
Upper Great Plains Region, Western
Area Power Administration, 2900 4th
Avenue North, Billings, MT 59101–
1266; (406) 255–2801; email: sundsted@
wapa.gov, or Linda Cady-Hoffman,
Rates Manager, Upper Great Plains
Region, telephone: (406) 255–2920;
email: cady@wapa.gov.
FOR FURTHER INFORMATION CONTACT:
On
November 19, 2015, FERC confirmed
and approved Rate Schedules WAUGP–
ATRR, WAUGP–AS1, WAUW–AS3,
WAUW–AS4, WAUW–AS5, WAUW–
AS6 and WAUW–AS7 under Rate Order
No. WAPA–170 on a final basis effective
for a 5-year period through September
30, 2020.1 Those schedules consisted of
separate formula-based rates for
transmission and ancillary services for
the transmission facilities in the P–
SMBP—ED that UGP transferred to the
functional control of SPP. The new rates
continue the formula-based
methodology that includes an annual
update to the financial data in the rate
formulas. The charges under these rates
will be annually updated January 1 of
each year beginning 2021 and thereafter.
The formula rates provide sufficient
revenue to recover annual expenses,
including interest expense, and repay
capital investments within the cost
SUPPLEMENTARY INFORMATION:
1 Order Confirming and Approving Rate
Schedules on a Final Basis, FERC Docket No. EF15–
8–000, 153 FERC ¶ 61213 (2015). FERC also
accepted the inclusion of UGP’s revenue
requirements for transmission and ancillary
services under the SPP Open Access Transmission
Tariff, FERC Docket No. ER15–2354–000, 152 FERC
¶ 61257 (2015).
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
recovery criteria set forth in Department
of Energy (DOE) Order RA 6120.2.
Legal Authority
By Delegation Order No. 00–037.00B,
effective November 19, 2016, the
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to WAPA’s
Administrator; (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy; and (3) the
authority to confirm, approve on a final
basis, remand, or disapprove such rates
to FERC. In Delegation Order No. 00–
002.00S, effective January 15, 2020, the
Secretary of Energy also delegated the
authority to confirm, approve, and place
such rates into effect on an interim basis
to the Under Secretary of Energy. By
Redelegation Order No. 00–002.10E,
effective February 14, 2020, the Under
Secretary of Energy further delegated
the authority to confirm, approve, and
place such rates into effect on an
interim basis to the Assistant Secretary
for Electricity. This rate action is issued
under the Redelegation Order and
DOE’s procedures for public
participation in rate adjustments set
forth at 10 CFR part 903.2
Following DOE’s review of WAPA’s
proposal, I hereby confirm, approve,
and place Rate Order No. WAPA–188,
which provides the formula rates for
transmission and ancillary services, into
effect on an interim basis. WAPA will
submit Rate Order No. WAPA–188 to
FERC for confirmation and approval on
a final basis.
Signing Authority
This document of the Department of
Energy was signed on July 9, 2020, by
Bruce J. Walker, Assistant Secretary for
Electricity, pursuant to delegated
authority from the Secretary of Energy.
That document, with the original
signature and date, is maintained by
DOE. For administrative purposes only,
and in compliance with requirements of
the Office of the Federal Register, the
undersigned DOE Federal Register
Liaison Officer has been authorized to
sign and submit the document in
electronic format for publication, as an
official document of the Department of
Energy. This administrative process in
no way alters the legal effect of this
document upon publication in the
Federal Register.
2 50 FR 37835 (September 18, 1985) and 84 FR
5347 (February 21, 2019).
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
42385
Signed in Washington, DC, on July 9, 2020.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
DEPARTMENT OF ENERGY
In the matter of:
Western Area Power Administration
Rate Adjustment for the Pick-Sloan
Missouri Basin Program—Eastern
Division Transmission and Ancillary
Services Formula Rates;
[Rate Order No. WAPA–188]
Order Confirming, Approving, and
Placing the Transmission and Ancillary
Services Formula Rates for the PickSloan Missouri Basin Program—Eastern
Division Into Effect on an Interim Basis
The formula rates in Rate Order No.
WAPA–188 are established following
section 302 of the Department of Energy
(DOE) Organization Act (42 U.S.C.
7152).3
By Delegation Order No. 00–037.00B,
effective November 19, 2016, the
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to the Western Area
Power Administration’s (WAPA)
Administrator; (2) the authority to
confirm, approve, and place into effect
such rates on an interim basis to the
Deputy Secretary of Energy; and (3) the
authority to confirm, approve on a final
basis, remand, or disapprove such rates
to the Federal Energy Regulatory
Commission (FERC). In Delegation
Order No. 00–002.00S, effective January
15, 2020, the Secretary of Energy also
delegated the authority to confirm,
approve, and place such rates into effect
on an interim basis to the Under
Secretary of Energy. By Redelegation
Order No. 00–002.10E, effective
February 14, 2020, the Under Secretary
of Energy further delegated the authority
to confirm, approve, and place such
rates into effect on an interim basis to
the Assistant Secretary for Electricity.
This rate action is issued under the
Redelegation Order and DOE’s
procedures for public participation in
rate adjustments set forth at 10 CFR part
903.4
3 This Act transferred to, and vested in, the
Secretary of Energy the power marketing functions
of the Secretary of the Department of the Interior
and the Bureau of Reclamation (Reclamation) under
the Reclamation Act of 1902 (ch. 1093, 32 Stat.
388), as amended and supplemented by subsequent
laws, particularly section 9(c) of the Reclamation
Project Act of 1939 (43 U.S.C. 485h(c)) and section
5 of the Flood Control Act of 1944 (16 U.S.C. 825s);
and other acts that specifically apply to the projects
involved.
4 50 FR 37835 (September 18, 1985) and 84 FR
5347 (February 21, 2019).
E:\FR\FM\14JYN1.SGM
14JYN1
42386
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
Acronyms, Terms, and Definitions
As used in this Rate Order, the
following acronyms, terms, and
definitions apply:
$/MW-year: Annual charge for
capacity (i.e., $ per megawatt (MW) per
year).
ATRR: Annual Transmission Revenue
Requirement is the net revenue
requirement for the Transmission
Services calculated in accordance with
the Formula Rate.
BA: Balancing Authority—The
responsible entity that integrates
resource plans ahead of time, maintains
load-interchange-generation balance
within a designated area, and supports
interconnection frequency in real-time.
Balancing Authority Area: An electric
system or systems, bounded by
interconnection metering and telemetry,
capable of controlling generation to
maintain its interchange schedule with
other Balancing Authorities and
contributing to frequency regulation of
the Interconnection.
Capacity: The electric capability of a
generator, transformer, transmission
circuit, or other equipment. It is
expressed in kilowatts (kW).
Corps: U.S. Army Corps of Engineers.
DOE: United States Department of
Energy.
Energy: Power produced or delivered
over a period of time. Measured in terms
of the work capacity over a period of
time. Electric energy is expressed in
kilowatt-hours.
Energy Imbalance Service: A service
that provides energy correction for any
hourly mismatch between a Southwest
Power Pool Transmission Customer’s
energy supply and the demand served.
FERC: Federal Energy Regulatory
Commission.
FRN: Federal Register notice.
Generator Imbalance Service: A
service that provides energy correction
for any hourly mismatch between
generator output and a delivery
schedule from that generator to another
Balancing Authority Area or to a load
within the same Balancing Authority
Area.
kW: Kilowatt—the electrical unit of
capacity that equals 1,000 watts.
kWh: Kilowatt-hour—the electrical
unit of energy that equals 1,000 watts in
1 hour.
Load: The amount of electric power or
energy delivered or required at any
specified point(s) on a system.
MW: Megawatt—the electrical unit of
capacity that equals 1 million watts or
1,000 kilowatts.
NEPA: National Environmental Policy
Act of 1969 (42 U.S.C. 4321–4347).
OASIS: Open Access Same-Time
Information System—An electronic
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
posting system that a service provider
maintains for transmission access data
that allows all customers to view
information simultaneously.
P–SMBP: Pick-Sloan Missouri Basin
Program.
P–SMBP—ED: Pick-Sloan Missouri
Basin Program—Eastern Division.
Provisional Formula Rate: A formula
rate that has been confirmed, approved,
and placed into effect on an interim
basis by the Assistant Secretary for
Electricity.
Rate Brochure: A document prepared
for public distribution explaining the
rationale and background for the rate
proposal contained in this rate order.
Regulation and Frequency Response
Service: A service that provides for
following the moment-to-moment
variations in the demand or supply in
a Balancing Authority Area and
maintaining scheduled interconnection
frequency.
Reserve Services: Spinning Reserve
Service and Supplemental Reserve
Service.
Revenue Requirement: The revenue
required to recover annual expenses
(such as operation and maintenance,
purchase power, transmission service
expenses, interest expense, and deferred
expenses) and repay Federal
investments, and other assigned costs.
Schedule: An agreed-upon transaction
size (megawatts), beginning and ending
ramp times and rate, and type of service
required for delivery and receipt of
power between the contracting parties
and the Balancing Authority(ies)
involved in the transaction.
Scheduling, System Control and
Dispatch Service: A service that
provides for (a) scheduling, (b)
confirming and implementing an
interchange schedule with other
balancing authorities, including
intermediary balancing authorities
providing transmission service, and (c)
ensuring operational security during the
interchange transaction.
Southwest Power Pool, Inc. (SPP): A
Regional Transmission Organization.
SPP’s Integrated Marketplace
(Integrated Marketplace): The SPP
Energy and Operating Reserve Markets
and the Transmission Congestion Rights
Markets.
Spinning Reserve Service: Generation
capacity needed to serve load
immediately in the event of a system
contingency. Spinning Reserve Service
may be provided by generating units
that are on-line and loaded at less than
maximum output.
Supplemental Reserve Service:
Generation capacity needed to serve
load in the event of a system
contingency; however, it is not available
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
immediately to serve load but rather
within a short period of time.
Supplemental Reserve Service may be
provided by generation units that are
on-line but unloaded, by quick start
generation or by interruptible load.
SPP Tariff: Southwest Power Pool,
Open Access Transmission Tariff,
approved by FERC.
SPP Transmission Customer: Any
eligible customer (or its designated
agent) that receives transmission service
under the SPP Tariff.
Transmission Provider: Any utility
that owns, operates, or controls facilities
used to transmit electric energy in
interstate commerce. SPP is the
Transmission Provider under the SPP
Tariff.
Transmission System: The facilities
owned, controlled, or operated by the
transmission owner or Transmission
Provider that are used by the
Transmission Provider to provide
transmission service.
UMZ: Upper Missouri Zone—Multiowner zone in SPP in which WAPA–
UGP participates as a Transmission
Owner; also defined as Zone 19 under
the SPP Tariff. The UMZ includes
transmission facilities located in both
the Eastern and Western
Interconnections.
WAUW: Western Area Power
Administration, Upper Great Plains
West Balancing Authority Area. WAUW
is located in the Western
Interconnection.
WAPA: United States Department of
Energy, Western Area Power
Administration.
Western Interconnection: A major
alternating current power grid in North
America. The Western Interconnection
stretches from Western Canada south to
Baja California in Mexico, reaching
eastward over the Rockies to the Great
Plains. Western Interconnection is
comprised of the states of Washington,
Oregon, California, Idaho, Nevada, Utah,
Arizona, Colorado, Wyoming, portions
of Montana, South Dakota, Nebraska,
New Mexico and Texas in the United
States, the Provinces of British
Columbia and Alberta in Canada, and a
portion of the Comisio´n Federal de
Electricidad’s system in Baja California
in Mexico.
WAPA–UGP: United States
Department of Energy, Western Area
Power Administration, Upper Great
Plains Region. Western-UGP is the
definition for WAPA’s Upper Great
Plains Region in the SPP Tariff.
Effective Date
The Provisional Formula Rate
Schedules WAUGP–ATRR, WAUGP–
AS1, WAUW–AS3, WAUW–AS4,
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
WAUW–AS5, WAUW–AS6 and
WAUW–AS7 are effective October 1,
2020, and will remain in effect through
September 30, 2025, pending approval
by FERC on a final basis or until
superseded.
Public Notice and Comment
WAPA followed the Procedures for
Public Participation in Power and
Transmission Rate Adjustments and
Extensions, 10 CFR part 903, in
developing these formula rates.
Following are the steps WAPA took to
involve interested parties in the rate
process:
1. On August 22, 2019, a Federal
Register notice (84 FR 43803) (Proposal
FRN) announced the proposed formula
rates and launched the 90-day public
consultation and comment period.
2. On August 23, 2019, WAPA
notified all P–SMBP—ED customers and
interested parties of the proposed rates
and provided a copy of the Proposal
FRN.
3. On September 24, 2019, WAPA
held a public information forum in
Omaha, Nebraska, and on September 25,
2019, WAPA held a public information
forum in Bismarck, North Dakota.
WAPA representatives explained the
proposed formula rates, answered
questions, and gave notice that more
information was available in the
customer Rate Brochure.
4. On September 24, 2019, WAPA
held a public comment forum in
Omaha, Nebraska, and on September 25,
2019, WAPA held a public comment
forum in Bismarck, North Dakota. This
provided customers and other interested
parties with opportunity to comment for
the record.
5. WAPA posted information about
this rate process that contains all dates,
customer letters, presentations, FRNs,
customer Rate Brochure, and other
information about this rate process at
the following locations: (a) WAPA–
UGP’s OASIS at: https://
www.oasis.oati.com/wapa/;
(b) WAPA–UGP’s Rates web page at:
https://www.wapa.gov/regions/UGP/
rates/Pages/rates.aspx; and (c) the
‘‘Western Area Power Administration
UGP Information’’ link on SPP’s
Member Related Postings website at:
https://opsportal.spp.org/OASIS/
Directory/
Member%20Related%20Postings.
6. During the 90-day consultation and
comment period, which ended on
November 20, 2019, WAPA received
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
one oral comment (at the September
24th public comment forum) and one
written set of comments. The comments
and WAPA’s responses are addressed
below. All comments have been
considered in the preparation of this
Rate Order.
One representative of the following
organization made oral comments:
Missouri River Energy Services (MRES).
Written comments were received from
the following interested parties:
Missouri River Energy Services (MRES).
Project Description
The initial stages of the Missouri
River Basin Project were authorized by
section 9 of the Flood Control Act of
1944 (58 Stat. 887, 890, Pub. L. 78–534).
It was later renamed the P–SMBP. The
P–SMBP is a comprehensive program
with the following authorized functions:
Flood control, navigation improvement,
irrigation, municipal and industrial
water development, and hydroelectric
production for the entire Missouri River
Basin.
WAPA–UGP owns and operates an
extensive system of high-voltage
transmission facilities that it uses to
market significant quantities of
Federally-generated hydroelectric power
from the P–SMBP—ED.
WAPA–UGP is a Transmission Owner
member of SPP pursuant to negotiated
provisions in its SPP Membership
Agreement and the SPP Bylaws and SPP
Open Access Transmission Tariff (SPP
OATT). Transmission and ancillary
services are provided by SPP under the
SPP OATT for WAPA–UGP’s facilities
transferred to the functional control of
SPP. WAPA–UGP has transmission
facilities in both the Eastern and
Western Interconnections separated by
the Miles City direct current tie and the
Fort Peck Power Plant substation.
WAPA–UGP operates its Western Area
Power Administration, Upper Great
Plains West (WAUW) Balancing
Authority Area in the Western
Interconnection as the Balancing
Authority (BA), and has not placed the
portion of its transmission system
located in the Western Interconnection
into SPP’s Integrated Marketplace.
WAPA–UGP still provides ancillary
services associated with its WAUW in
the Western Interconnection as the BA.
WAPA–UGP’s formula rates for
transmission and ancillary services will
be applied so WAPA–UGP’s costs can
continue to be recovered under the SPP
OATT. WAPA–UGP’s revenue
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
42387
requirements are added to the annual
revenue requirements of other
transmission owners in the multi-owner
SPP pricing Zone 19, also identified as
the Upper Missouri Zone (UMZ), for
transmission service billed by SPP
within the UMZ. WAPA–UGP’s revenue
requirements under these proposed
rates also impact other costs for
transmission service within the broader
SPP footprint. The formula rates provide
WAPA–UGP sufficient revenue to pay
all annual costs, including interest
expenses, and repay investment.
P–SMBP—ED Transmission and
Ancillary Services Rate Studies
Existing Rate Schedules WAUGP–
ATRR, WAUGP–AS1, WAUW–AS3,
WAUW–AS4, WAUW–AS5, WAUW–
AS6 and WAUW–AS7 were approved
under Rate Order No. WAPA–170 for a
5-year period beginning on October 1,
2015, and ending September 30, 2020.
Those rate schedules consisted of
separate formula-based rates for
transmission service and ancillary
services for the transmission facilities in
the P–SMBP—ED that WAPA–UGP
transferred to the functional control of
SPP. The new rates continue the
formula-based methodology that
includes an annual update to the
financial data in the rate formulas with
only limited changes to: (1) The
Formula Rate Templates (Templates) to
increase transparency through addition
of financial data source detail; (2) the
Formula Rate Implementation Protocols
(Protocols) to clarify WAPA–UGP’s rate
implementation and annual update
procedures; (3) the Operating Reserves
formula rates to incorporate costs
associated with WAPA–UGP’s current
reserve sharing group membership; and
(4) the rate schedules for Energy
Imbalance and Generator Imbalance to
accommodate participation in a Western
Interconnection energy imbalance
service market.
WAPA prepared Transmission and
Ancillary Services rates studies to
ensure that the formula rates are based
on the cost of service of the WAPA–UGP
eligible transmission facilities that are
included in the UMZ and the associated
operation of the WAUW. These studies
included all applicable expenses and
associated offsetting revenues.
Provisional Rates
The revenue requirements for 2020 for
the individual services are outlined in
the following table.
E:\FR\FM\14JYN1.SGM
14JYN1
42388
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
PROVISIONAL WAPA–UGP TRANSMISSION AND ANCILLARY SERVICES FORMULA RATES
Service
Rate schedule No.
Provisional 2020 annual revenue requirement
Transmission .....................................................................
WAUGP–ATRR ..................
Scheduling, System Control, and Dispatch ......................
Regulation and Frequency Response ..............................
Operating Reserves—Spinning and Supplemental Reserves.
Energy Imbalance .............................................................
Generator Imbalance ........................................................
WAUGP–AS1 .....................
WAUW–AS3 .......................
WAUW–AS5 and WAUW–
AS6.
WAUW–AS4 .......................
WAUWA–AS7 ....................
$136,325,626—SPP Sched 9; $666,093—SPP Sched
11 (Zonal); $111,344—SPP Sched 11 (Regional).
$11,534,163.
$291,973.
$409,789.
Transmission and Ancillary Rate
Discussion
WAPA–UGP includes facilities in the
UMZ ATRR calculation that meet
Transmission Facility criteria as
identified in Attachment AI to SPP’s
OATT. WAPA–UGP identifies any
portion of the ATRR eligible for
recovery under SPP Schedule 11
pursuant to the SPP OATT in its Rate
Formula Template submitted under
Attachment H of the SPP OATT.
WAPA–UGP will true-up the cost
estimates with actual costs. Revenue
collected in excess of WAPA–UGP’s
actual net revenue requirement will be
returned to customers through a credit
against a revenue requirement in a
subsequent year. Actual revenues that
are less than the net revenue
requirement would likewise be
recovered in a subsequent year. The
true-up procedure will ensure that
WAPA–UGP will recover no more and
no less than the actual transmission
costs for the year.
Data used in the annual recalculation
of the formula rate effective on January
1 each year will be made available for
review and comment on or around
September 1 each year as described in
the Protocols. WAPA–UGP will provide
customers the opportunity to discuss
and comment on the recalculated rates
on or before November 15, 2020, and
annually by November 15 of subsequent
years as described in the Protocols. The
Protocols that describe the meetings
where customers have opportunity to
discuss and comment are available
online at the following locations: (1)
WAPA–UGP’s OASIS at: https://
www.oasis.oati.com/wapa/;
(2) WAPA–UGP’s Rates web page at:
https://www.wapa.gov/regions/UGP/
rates/Pages/rates.aspx; and (3) the
‘‘Western Area Power Administration
UGP Information’’ link on SPP’s
Member Related Postings website at:
https://opsportal.spp.org/OASIS/
Directory/
Member%20Related%20Postings. This
procedure ensures that interested
parties are aware of the data used to
calculate the rates. This also provides
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
N/A.
N/A.
interested parties the opportunity to
comment before the costs are collected
through the formula rate.
Formula Transmission Rate
WAPA–UGP will continue to use its
current formula rate calculation
methodology for its ATRR, provided
under Rate Schedule WAUGP–ATRR.
This rate schedule includes WAPA–
UGP’s transmission facilities in both the
Eastern and Western Interconnections
that are transferred to the functional
control of SPP and used by SPP in order
to provide transmission service in the
UMZ under the SPP OATT. Consistent
with WAPA–UGP’s existing formula
rate, WAPA–UGP will continue
recovering transmission system
expenses and investments on a forwardlooking basis by using projections to
estimate transmission costs for the
upcoming year, with a true-up of
incurred costs in a subsequent year.
Transmission-related annual costs
include operation and maintenance,
interest, administrative and general
costs, and depreciation. Cost data is
submitted to SPP in standard revenue
requirement templates and classified as
either ‘‘Zonal’’ or ‘‘Regional’’ costs as
defined under the SPP OATT. ‘‘Zonal’’
costs are recovered within the local
pricing zone while ‘‘Regional’’ costs are
recovered across the entire SPP
footprint. The ATRR Formula Rate
Template includes breakouts of the
annual revenue requirement for each
individual Base Plan Upgrade, as
defined under the SPP OATT, assigned
to and funded by WAPA–UGP, along
with ‘‘Regional’’ and ‘‘Zonal’’ allocation
of the total net annual revenue
requirement for each Project.
Formula Rate Implementation
Protocols
For transmission and ancillary
services provided under the SPP OATT,
WAPA–UGP will continue to provide
information relating to WAPA–UGP’s
rate implementation and annual updates
in Formula Rate Implementation
Protocols (Protocols), which together
with the Formula Rate Templates
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
(Templates), comprise the Formula
Rates that are submitted to SPP to be
incorporated in the SPP OATT. WAPA–
UGP changed its Protocols to clarify and
include additional detail regarding
WAPA–UGP’s rate implementation and
annual update procedures. WAPA–UGP
was one of the first transmission owners
in the UMZ to develop Protocols.
Therefore, WAPA–UGP updated its
Protocols to be more consistent with the
protocols of other transmission owners
in the UMZ that were developed and
approved after WAPA–UGP joined SPP.
Formula Rate for Scheduling, System
Control, and Dispatch Service
WAPA–UGP will continue to use a
formula-based rate methodology to
calculate its annual revenue
requirement for Scheduling, System
Control, and Dispatch Service (SSCD),
provided under Rate Schedule
WAUGP–AS1 for the SPP UMZ. This
rate schedule also includes transmission
facilities in the WAUW.
SSCD is required to schedule the
movement of power through, out of,
within, or into the SPP and/or WAUW
Balancing Authority Area(s). WAPA–
UGP’s annual revenue requirement for
SSCD is utilized by SPP to calculate the
regional SPP Schedule 1 rate for the
UMZ. WAPA–UGP’s annual revenue
requirement for SSCD is derived by
annualizing WAPA–UGP’s applicable
transmission-related annual costs
associated with the provision of SSCD
service, including operation and
maintenance, interest, administrative
and general costs, and depreciation.
Estimates are calculated on a forwardlooking basis by using projections to
determine applicable transmissionrelated costs associated with SSCD for
the upcoming year, with a true-up in a
subsequent year, to be provided to SPP
for inclusion in Schedule 1 under the
SPP Tariff.
WAPA–UGP will true-up the cost
estimates with WAPA–UGP’s actual
costs. Revenue collected in excess of
WAPA–UGP’s actual net revenue
requirement will be returned to
customers through a credit against a
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
revenue requirement in a subsequent
year. Actual revenues that are less than
the net revenue requirement would
likewise be recovered in a subsequent
year. The true-up procedure will ensure
that WAPA–UGP will recover no more
and no less than the actual costs for the
year. WAPA–UGP included additional
information regarding implementation
and annual updates for SSCD in its
revised Protocols.
Formula Rate for Regulation and
Frequency Response Service
WAPA–UGP will continue to use a
formula-based rate methodology for
Regulation and Frequency Response
Service (Regulation) for the WAUW,
provided under Rate Schedule WAUW–
AS3. WAPA–UGP provides Regulation
and Frequency Response Service in the
WAUW as the BA. Regulation and
Frequency Response Service in the
WAUW is provided primarily by Corps
facilities. Under the formula rate
methodology, the Corps’ generation
fixed charge rate (in percent) is applied
to the net plant investment of the Corps
generation to derive an annual Corps
generation cost. This cost is divided by
the capacity at the plants to derive a
dollar-per-megawatt amount for Corpsinstalled capacity ($/MW-year). This
dollar-per-megawatt amount is applied
to the capacity of Corps generation
reserved for Regulation and Frequency
Response Service in the WAUW,
producing the annual Corps generation
cost for this service. WAPA–UGP’s
annual revenue requirement is
recovered under the SPP Tariff under
Rate Schedule WAUW–AS3.
Regulation and Frequency Response
Service is necessary to provide for the
continuous balancing of resources,
generation, and interchange with load
and for maintaining scheduled
interconnection frequency at 60 cycles
per second (60 Hz). Regulation is
accomplished by committing on-line
generation whose output is raised or
lowered, predominantly through the use
of automatic generating control
equipment, as necessary, to follow the
moment-by-moment changes in load.
The obligation to maintain this balance
between resources and load lies with
the WAPA–UGP as the WAUW
operator. The SPP Transmission
Customer must either purchase this
service from SPP or make alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Regulation
obligation. WAPA–UGP’s annual
revenue requirement for Regulation will
be used by SPP to calculate the WAUW
charges for Regulation. WAPA–UGP
included additional information
regarding implementation and annual
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
updates for Regulation in its revised
Protocols.
WAPA–UGP will true-up the cost
estimates with WAPA–UGP’s actual
costs. Revenue collected in excess of
WAPA–UGP’s actual net revenue
requirement will be returned through a
credit in a subsequent year. Actual
revenues that are less than the net
revenue requirement would likewise be
recovered in a subsequent year. The
true-up procedure will ensure that
WAPA–UGP will recover no more and
no less than the actual costs for the year.
WAPA–UGP supports the installation
of renewable sources of energy but
recognizes that certain operational
constraints exist in managing the
significant fluctuations that are a normal
part of their operation. When WAPA–
UGP purchases power resources to
provide Regulation to intermittent
resources serving load within WAPA–
UGP’s WAUW, costs for these regulation
resources will become part of WAPA’s
Regulation revenue requirement, which
will be billed by SPP, as the
Transmission Provider, to a SPP
Transmission Customer along with the
associated transmission service
provided by SPP under the SPP Tariff.
However, WAPA–UGP will not regulate
for the difference between the output of
an intermittent resource located within
WAPA–UGP’s WAUW and a delivery
schedule from that generator serving
load located outside of WAPA–UGP’s
WAUW. Intermittent resources serving
load outside WAPA–UGP’s WAUW will
be required to be pseudo-tied or
dynamically scheduled to another
Balancing Authority Area.
An intermittent resource, for the
limited purpose of this rate schedule, is
an electric generator that is not
dispatchable and cannot store its fuel
source and, therefore, cannot respond to
changes in demand or respond to
transmission security constraints.
Formula Rate for Energy Imbalance
Service
WAPA–UGP will continue to use its
current formula rate calculation
methodology for Energy Imbalance
Service (Energy Imbalance), which is
provided under Rate Schedule WAUW–
AS4. This rate schedule addresses
Energy Imbalance associated with UGP’s
WAUW in the Western Interconnection.
WAPA–UGP also revised Rate Schedule
WAUW–AS4 to accommodate
participation in a Western
Interconnection energy imbalance
service market by WAPA–UGP as the
BA. WAPA–UGP is providing additional
information regarding implementation
and annual updates for Energy
Imbalance in its revised Protocols.
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
42389
Energy Imbalance Service is provided
when a difference occurs between the
scheduled and the actual delivery of
energy to a load located within WAPA–
UGP’s WAUW over a single hour (or
different dispatch interval for energy
imbalance service market, if applicable).
Given the SPP Integrated Marketplace
does not extend into the Western
Interconnection, WAPA–UGP as the BA,
will offer to provide Energy Imbalance
Service in the WAUW at the request of
SPP, if it is capable of doing so, from its
own resources or from resources
available to it including possible
participation in a Western
Interconnection energy imbalance
market. SPP is the Transmission
Provider for the eligible WAPA–UGP
facilities transferred to the functional
control of SPP in the WAUW. Energy
Imbalance Service is needed when
transmission service is provided by SPP
and used to serve load within the
WAUW, or when a difference occurs
between the expected and actual
delivery of energy to/from the WAUW
over a single hour (or different dispatch
interval for energy imbalance service
market, if applicable) in the event that
WAPA–UGP participates in a Western
Interconnection energy imbalance
service market in the WAUW as the BA.
Energy Imbalance Service in the WAUW
will be billed by SPP to the SPP
Transmission Customer along with the
associated transmission service
provided by SPP. The SPP Transmission
Customer must either purchase this
service from SPP, or make alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Energy
Imbalance Service Obligation.
The SPP Transmission Customer will
incur a charge for either hourly energy
imbalances under this Schedule,
WAUW–AS4, or hourly generator
imbalances under Rate Schedule
WAUW–AS7 for imbalances occurring
during the same hour, but not both,
unless the imbalances aggravate rather
than offset each other.
This Rate Order puts in place two
options for how Energy Imbalance
Service in the WAUW may be provided:
(A) In the event that WAPA–UGP
does not participate in a Western
Interconnection energy imbalance
market in the WAUW as the BA, or such
energy imbalance market is unable to
provide the total energy imbalance
requirements for certain loads and
generation within the Balancing
Authority Area:
The rate for service will be based up
deviation bands as follows: (i)
Deviations within +/¥1.5 percent (with
a minimum of 2 MW) of the scheduled
transaction to be applied hourly to any
E:\FR\FM\14JYN1.SGM
14JYN1
42390
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
energy imbalance that occurs as a result
of the SPP Transmission Customer’s
scheduled transaction(s) will be netted
on a monthly basis and settled
financially, at the end of the month, at
100 percent of the average incremental
cost for the month; (ii) deviations
greater than +/¥1.5 percent up to 7.5
percent (or greater than 2 MW up to 10
MW) of the scheduled transaction(s) to
be applied hourly to any energy
imbalance that occurs as a result of the
SPP Transmission Customer’s
scheduled transaction(s) will be settled
financially, at the end of each month, at
a charge of 110 percent of incremental
cost when energy taken by the SPP
Transmission Customer in a schedule
hour is greater than the energy
scheduled or a credit of 90 percent of
incremental cost when energy taken by
a SPP Transmission Customer in a
schedule hour is less than the scheduled
amount; and (iii) deviations greater than
+/¥7.5 percent (or 10 MW) of the
scheduled transaction to be applied
hourly to any energy imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be settled at 125
percent of WAPA–UGP’s incremental
cost when energy taken by the SPP
Transmission Customer in a schedule
hour that is greater than the energy
scheduled, or 75 percent of WAPA–
UGP’s incremental cost when energy
taken by a SPP Transmission Customer
is less than the scheduled amount.
WAPA–UGP’s incremental cost will
be based on a representative hourly
energy index or combination of indexes.
The index to be used, or any change to
the index, will be posted on the
applicable SPP website and WAPA–
UGP’s OASIS at least 30 days before use
for determining the WAPA–UGP
incremental cost and will not be
changed more often than once per year
unless WAPA–UGP determines that the
existing index is no longer a reliable
price index.
(B) In the event that WAPA–UGP
participates in a Western
Interconnection energy imbalance
market in the WAUW as the BA:
Charges to the SPP Transmission
Customer will reflect only the passthrough of the applicable charges
associated with the Western
Interconnection energy imbalance
service market assessed to WAPA–UGP
as the WAUW BA for embedded load
and/or generation in the WAUW of such
SPP Transmission Customer that does
not make adequate alternate
arrangements in such Western
Interconnection energy imbalance
service market or other alternative
comparable arrangements pursuant to
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
the SPP Tariff to satisfy its Energy
Imbalance Service obligation.
WAPA–UGP will post notice on the
applicable SPP website and WAPA–
UGP’s OASIS, and also notify existing
SPP Transmission Customers, at least 30
days before WAPA–UGP participates in
a Western Interconnection energy
imbalance service market, as the BA.
WAPA–UGP will also post information
related to the charges assessed by the
market operator for Energy Imbalance
Service in the WAUW under such
Western Interconnection energy
imbalance service market.
WAPA–UGP will follow Option A
above beginning on October 1, 2020.
WAPA–UGP will follow Option B above
in the event that WAPA–UGP
participates in a Western
Interconnection energy imbalance
market.
Formula Rate for Generator Imbalance
Service
WAPA–UGP will continue to use its
current formula rate calculation
methodology for Generator Imbalance
Service (Generator Imbalance), which is
provided under Rate Schedule WAUW–
AS7. This rate schedule addresses
Generator Imbalance associated with
WAPA–UGP’s WAUW in the Western
Interconnection. WAPA–UGP also
changed Rate Schedule WAUW–AS7 to
accommodate participation in a Western
Interconnection energy imbalance
market by WAPA–UGP as the BA.
WAPA–UGP is providing additional
information regarding implementation
and annual updates for Generator
Imbalance in its revised Protocols.
Generator Imbalance Service is
provided when a difference occurs
between the output of a generator
located within WAPA–UGP’s WAUW
and a delivery schedule from that
generator to: (1) Another Balancing
Authority Area or (2) a load within
WAPA–UGP’S WAUW over a single
hour (or different dispatch interval for
energy imbalance service market, if
applicable). Given the SPP Integrated
Marketplace does not extend into the
Western Interconnection, WAPA–UGP,
as the BA, will offer to provide this
service at the request of SPP, if it is
capable of doing so, from its own
resources or resources available to it,
including possible participation in a
Western Interconnection energy
imbalance service market. SPP is the
Transmission Provider for the eligible
WAPA–UGP facilities transferred to the
functional control of SPP in the WAUW.
Generator Imbalance Service is needed
when transmission service is provided
by SPP and used to deliver energy from
a generator located within the WAUW,
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
or when a difference occurs between the
expected and actual delivery of energy
to/from the WAUW over a single hour
(or different dispatch interval for energy
imbalance service market, if applicable)
in the event that WAPA–UGP
participates in a Western
Interconnection energy imbalance
service market in the WAUW as the BA.
Generator Imbalance Service in the
WAUW will be billed by SPP to the SPP
Transmission Customer along with the
associated transmission service. The
SPP Transmission Customer must either
purchase this service from SPP, or make
alternative comparable arrangements
pursuant to the SPP Tariff, to satisfy its
Generator Imbalance Service obligation.
The SPP Transmission Customer will
incur a charge for either hourly
generator imbalances under this rate
schedule, WAUW–AS7, or hourly
energy imbalances under Rate Schedule
WAUW–AS4 for imbalances occurring
during the same hour, but not both,
unless the imbalances aggravate rather
than offset each other.
WAPA–UGP supports the installation
of renewable sources of energy but
recognizes that certain operational
constraints exist in managing the
significant fluctuations that are a normal
part of their operation. WAPA–UGP has
marketed the maximum practical
amount of power from each of its
projects, leaving little or no flexibility
for provision of additional power
services. Consequently, WAPA–UGP
will not regulate for the difference
between the output of an intermittent
generator located within the WAUW
and a delivery schedule from that
generator serving load located outside of
the WAUW. Intermittent resources
serving load outside WAPA–UGP’s
WAUW will be required to be pseudotied or dynamically scheduled to
another Balancing Authority Area.
An intermittent resource, for the
limited purpose of this rate schedule, is
an electric generator that is not
dispatchable and cannot store its fuel
source and, therefore, cannot respond to
changes in system demand or respond
to transmission security constraints.
This Rate Order puts in place two
options for how Generator Imbalance
Service in the WAUW may be provided:
(A) In the event that WAPA–UGP
does not participate in a Western
Interconnection energy imbalance
service market in the WAUW as the BA,
or such energy imbalance market is
unable to provide the total energy
imbalance requirements for certain
loads and generation within the
Balancing Authority Area:
The rate for service will be based on
deviation bands as follows: (i) For
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
deviations within +/¥1.5 percent (with
a minimum of 2 MW) of the scheduled
transaction to be applied hourly to any
generator imbalance that occurs as a
result of the SPP Transmission
Customer’s scheduled transaction(s)
will be netted on a monthly basis and
settled financially, at the end of the
month, at 100 percent of the average
incremental cost; (ii) deviations greater
than +/¥1.5 percent up to 7.5 percent
(or greater than 2 MW up to 10 MW) of
the scheduled transaction to be applied
hourly to any generator imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be settled financially,
at the end of each month, as a charge of
110 percent of incremental cost when
energy delivered in a schedule hour
from the generation resource is less than
the energy scheduled or a credit of 90
percent of the incremental cost when
energy delivered from the generation
resource is greater than the scheduled
amount; and (iii) deviations greater than
+/¥7.5 percent (or 10 MW) of the
scheduled transaction to be applied
hourly to any generator imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be settled at 125
percent of WAPA–UGP’s highest
incremental cost for the day when
energy delivered in a schedule hour is
less than the energy scheduled or 75
percent of WAPA–UGP’s lowest daily
incremental cost when energy delivered
from the generation resource is greater
than the scheduled amount. An
intermittent resource will be exempt
from this deviation band and will pay
the deviation band charges for all
deviations greater than the larger of 1.5
percent or 2 MW.
Deviations from scheduled
transactions responding to directives by
the Transmission Provider, a BA, or a
reliability coordinator will not be
subject to the deviation bands identified
above and, instead, will be settled
financially at the end of the month at
100 percent of incremental cost. Such
directives may include instructions to
correct frequency decay, respond to a
reserve sharing event, or change output
to relieve congestion.
WAPA–UGP’s incremental cost will
be based on a representative hourly
energy index or combination of indexes.
The index to be used, or any change to
the index, will be posted on the
applicable SPP website and WAPA–
UGP’s OASIS at least 30 days before use
for determining the WAPA–UGP
incremental cost and will not be
changed more often than once per year
unless WAPA–UGP determines that the
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
existing index is no longer a reliable
price index.
(B) In the event that WAPA–UGP
participates in a Western
Interconnection energy imbalance
service market in the WAUW as the BA:
Charges to the SPP Transmission
Customer will reflect only the passthrough of the applicable charges
associated with the Western
Interconnection energy imbalance
service market assessed to WAPA–UGP
as the WAUW BA for embedded load
and/or generation in the WAUW of such
SPP Transmission Customer that does
not make adequate alternate
arrangements in such Western
Interconnection energy imbalance
service market or other alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Generator
Imbalance Service Obligation.
WAPA–UGP will post notice on the
applicable SPP website and WAPA–
UGP’s OASIS, and also notify existing
Transmission Customers, at least 30
days before WAPA–UGP participates in
a Western Interconnection energy
imbalance service market, as the BA.
WAPA–UGP will also post information
related to the charges assessed by the
market operator for Generator Imbalance
Service in the WAUW under such
Western Interconnection energy
imbalance service market.
WAPA–UGP will follow Option A
above beginning on October 1, 2020.
WAPA–UGP will follow Option B above
in the event that WAPA–UGP
participates in a Western
Interconnection energy imbalance
service market.
Formula Rates for Operating Reserves
Service—Spinning and Supplemental
WAPA–UGP will continue to use its
current formula rate calculation
methodologies for Operating Reserve—
Spinning Reserve Service and Operating
Reserve—Supplemental Reserve Service
(collectively, Operating Reserves)
provided under Rate Schedules
WAUW–AS5 and WAUW–AS6,
respectively, with changes to the rate
formulas to incorporate costs associated
with its current reserve sharing group
membership. These rate schedules
address Operating Reserves associated
with WAPA–UGP’s WAUW in the
Western Interconnection. WAPA–UGP
changed the rate formulas to incorporate
costs associated with its current reserve
sharing group membership. In addition,
WAPA–UGP included additional
information regarding implementation
and annual updates for Operating
Reserves in its revised Protocols. Given
the SPP Integrated Marketplace does not
extend into the Western
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
42391
Interconnection, WAPA–UGP will
continue to provide Operating Reserves
in the WAUW as the BA. WAPA–UGP
utilizes the reserve requirement of the
reserve sharing group of which WAPA–
UGP is currently a member for its
transmission system in the Western
Interconnection.
WAPA–UGP’s annual cost of
generation for Reserve Services is
determined by multiplying the Corps’
generation fixed charge rate (in percent)
by the net plant investment of the Corps
generation producing an annual Corps
generation cost. This cost is divided by
the capacity at the plants to derive a
dollar-per-megawatt amount for Corps
installed capacity ($/MW-year). This
dollar-per-megawatt amount is then
applied to the capacity of Corps
generation reserved for Reserve Services
in the WAUW, producing the annual
Corps generation cost to provide this
service. WAPA–UGP’s annual revenue
requirement for Reserve Services is then
determined by taking the annual Corps
generation cost to provide this service
and adding costs associated with the
current reserve sharing group, if
applicable. WAPA–UGP’s annual
revenue requirement will be recovered
under the SPP Tariff. This rate design
recovers only WAPA–UGP’s revenue
requirement associated with Reserve
Services. The Reserve Services will
apply to both load and generation in the
WAUW (i.e., transmission service for
loads in the WAUW and transmission
service for generation deliveries out of
the WAUW).
WAPA–UGP will true-up the cost
estimates with WAPA–UGP’s actual
costs. Revenue collected in excess of
WAPA–UGP’s actual net revenue
requirement will be returned through a
credit in a subsequent year. Actual
revenues that are less than the net
revenue requirement would likewise be
recovered in a subsequent year. The
true-up procedure will ensure that
WAPA–UGP will recover no more and
no less than the actual costs for the year.
Spinning Reserves
Operating Reserve-Spinning Reserve
Service (Spinning Reserves) is needed to
serve load immediately in the event of
a system contingency. Spinning
Reserves may be provided by generating
units that are on-line and loaded at less
than maximum output. Given the SPP
Integrated Marketplace does not extend
into the Western Interconnection,
WAPA–UGP, as the BA, will offer to
provide Spinning Reserves, if available,
at the request of SPP as the
Transmission Provider in the WAUW.
Spinning Reserves in the WAUW will
be billed by SPP to the SPP
E:\FR\FM\14JYN1.SGM
14JYN1
42392
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
Transmission Customer along with the
associated transmission service
provided by SPP. The SPP Transmission
Customer must either purchase this
service from SPP or make alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Spinning
Reserves obligation. WAPA–UGP’s
annual revenue requirement for
Spinning Reserves will be utilized by
SPP to calculate the WAUW charges for
Spinning Reserves.
If resources are not available from a
WAPA–UGP resource, WAPA–UGP, at
the request of SPP as the Transmission
Provider, will offer to purchase the
Spinning Reserves and pass through the
costs, plus an amount for
administration, to SPP for the SPP
Transmission Customer.
In the event that Spinning Reserves
are called upon for emergency use, the
SPP Transmission Customer will be
assessed a charge for energy used at the
prevailing market energy rate in the
WAUW. The prevailing market energy
rate will be based upon a representative
hourly energy index or combination of
indexes. The index to be used, or any
change to the index, will be posted on
the applicable SPP website and WAPA–
UGP’s OASIS at least 30 days before use
for determining the prevailing market
energy rate and will not be changed
more often than once per year unless
WAPA–UGP determines that the
existing index is no longer a reliable
price index. The SPP Transmission
Customer would be responsible for
providing transmission service to get the
Spinning Reserves to its destination.
the SPP Tariff to satisfy its
Supplemental Reserves obligation.
WAPA–UGP’s annual revenue
requirement for Supplemental Reserves
will be utilized by SPP to calculate the
WAUW charges for Supplemental
Reserves.
Supplemental Reserves
Operating Reserve-Supplemental
Reserve Service (Supplemental
Reserves) is needed to serve load in the
event of a system contingency; however,
it is not available immediately to serve
load but rather within a short period of
time.
Supplemental Reserves may be
provided by generating units that are
on-line but unloaded, by quick-start
generation, or by interruptible load.
Given the SPP Integrated Marketplace
does not extend into the Western
Interconnection, WAPA–UGP, as the
BA, will offer to provide Supplemental
Reserves, if available, at the request of
SPP as the Transmission Provider, in
the WAUW. Operating ReserveSupplemental Reserve Service in the
WAUW will be billed by SPP to the SPP
Transmission Customer along with the
associated transmission service
provided by SPP. The SPP Transmission
Customer must either purchase this
service from SPP or make alternative
comparable arrangements pursuant to
Certification of Rates
WAPA’s Administrator certified that
the Provisional Formula Rates for P–
SMB—ED under Rate Schedules
WAUGP–ATRR, WAUGP–AS1,
WAUW–AS3, WAUW–AS4, WAUW–
AS5, WAUW–AS6, and WAUW–AS7
are the lowest possible rates, consistent
with sound business principles. The
Provisional Formula Rates were
developed following administrative
policies and applicable laws.
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
Comments
WAPA received one oral comment
and one comment letter during the
public consultation and comment
period. The comments have been
paraphrased, where appropriate,
without compromising the meaning of
the comments.
Comment: The customer notes its
appreciation of the efforts WAPA is
making to increase transparency of the
formula rate template, and that its
comments are generally centered on
transparency. As such, the customer
requests WAPA adjust the formula rate
template to ensure transparency for all
stakeholders. Specifically, this includes
financial and source document data
transparency and transparency on the
website.
Response: WAPA has reviewed the
Formula Rate Templates and all
suggestions provided by the customer
regarding transparency. WAPA has
updated the Formula Rate Templates to
address the customer’s comments.
These template changes include
additional footnotes, links, references,
and other suggestions provided by the
customer. WAPA has included the
additional financial and source
document data on OASIS at: https://
www.oasis.oati.com/wapa/.
Availability of Information
Information about this rate
adjustment, including the customer Rate
Brochure, comments, letters,
memorandums, and other supporting
materials that were used to develop the
Provisional Formula Rates, is available
for inspection and copying at the Upper
Great Plains Regional Office, located at
2900 4th Avenue North, Billings,
Montana. Many of these documents are
also available online at the following
locations: (1) WAPA–UGP’s OASIS at:
https://www.oasis.oati.com/wapa/
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
index.html; (2) WAPA–UGP’s Rates web
page at: https://www.wapa.gov/regions/
UGP/rates/Pages/rates.aspx; and (3) the
‘‘Western Area Power Administration
UGP Information’’ link on SPP’s
Member Related Postings website at:
https://opsportal.spp.org/OASIS/
Directory/Member%20Related
%20Postings.
RATEMAKING PROCEDURE
REQUIREMENTS
Environmental Compliance
WAPA has determined that this
action is categorically excluded from the
preparation of an environmental
assessment or an environmental impact
statement.5 A copy of the categorical
exclusion determination is available on
WAPA’s website at: https://
www.wapa.gov/regions/UGP/
Environment/Pages/environment.aspx.
Determination Under Executive Order
12866
WAPA has an exemption from
centralized regulatory review under
Executive Order 12866; accordingly, no
clearance of this notice by the Office of
Management and Budget is required.
Submission to the Federal Energy
Regulatory Commission
The Provisional Formula Rates herein
confirmed, approved, and placed into
effect on an interim basis, together with
supporting documents, will be
submitted to FERC for confirmation and
final approval.
ORDER
In view of the above and under the
authority delegated to me, I hereby
confirm, approve, and place into effect,
on an interim basis, Rate Order No.
WAPA–188. The rates will remain in
effect on an interim basis until: (1) FERC
confirms and approves them on a final
basis; (2) subsequent rates are confirmed
and approved; or (3) such rates are
superseded.
Dated: July 9, 2020.
Bruce J. Walker,
Assistant Secretary for Electricity.
Rate Schedule WAUGP–ATRR
October 1, 2020
(Supersedes Rate Schedule WAUGP–
ATRR dated October 1, 2015, through
September 30, 2020)
5 The determination was done in compliance with
the National Environmental Policy Act (NEPA) of
1969, as amended, 42 U.S.C. 4321–4347; the
Council on Environmental Quality Regulations for
implementing NEPA (40 CFR parts 1500–1508); and
DOE NEPA Implementing Procedures and
Guidelines (10 CFR part 1021).
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
ANNUAL TRANSMISSION
REVENUE REQUIREMENT FOR
TRANSMISSION SERVICE
SCHEDULING, SYSTEM CONTROL,
AND DISPATCH SERVICE
Effective
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Applicable
Western Area Power AdministrationUpper Great Plains Region’s (WesternUGP) formula based Annual
Transmission Revenue Requirement
(ATRR) for its eligible transmission
related facilities included under the
Southwest Power Pool, Inc. (SPP) Tariff
will be calculated using the formula
outlined below.
Formula Rate
Define:
A = Operation & Maintenance allocated to
transmission ($)
B = Depreciation allocated to transmission ($)
C = Interest Expense allocated to
transmission ($)
D = Revenue Credits ($)
E = Scheduling, System Control, and
Dispatch costs ($)
F = Prior Period True-up ($)
ATRR = A + B + C¥D¥E + F
Note: Western-UGP will identify any
portion(s) of the ATRR eligible for recovery
under SPP Schedule 11 pursuant to the SPP
Tariff in its Rate Formula Template
submitted under Attachment H of the SPP
Tariff.
A recalculated annual revenue
requirement will go into effect every
January 1 based on the above formula
and updated financial data. WesternUGP will annually notify SPP and make
data and information available to
interested parties for review and
comment related to the recalculated
annual revenue requirement on or
shortly after September 1 of the
preceding year. Data used and the
charges resulting from using this
formula will be posted on the applicable
SPP website and Western-UGP’s Open
Access Same-Time Information System
(OASIS).
Rate Schedule WAUGP–AS1
October 1, 2020
(Supersedes Rate Schedule WAUGP–
AS1 dated October 1, 2015, through
September 30, 2020)
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
Effective
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Applicable
Scheduling, System Control, and
Dispatch Service (SSCD) is required to
schedule the movement of power
through, out of, within, or into the
Southwest Power Pool, Inc. (SPP)
Balancing Authority Area and/or the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Western Area
Power Administration-Upper Great
Plains Region’s (Western-UGP) annual
revenue requirement for SSCD will be
used by SPP to calculate the regional
SPP Schedule 1 rate for SPP through
and out transactions, and also to
calculate the zonal SPP Schedule 1 rate
for the Upper Missouri Zone (UMZ or
Zone 19). This rate will also be charged
by SPP for SPP Transmission Service
provided within the UMZ in the
Western Interconnection.
Formula Rate
Define:
A = Operation & Maintenance for SSCD ($)
B = Administrative and General Expense for
SSCD ($)
C = Depreciation for SSCD ($)
D = Taxes Other than Income Taxes for
Transmission ($)
E = Allocation of General Plant for SSCD ($)
F = Cost of Capital for SSCD ($)
G = SSCD Revenue from non-Transmission
facilities ($)
H = Prior Period True-up ($)
SSCD Annual Revenue Requirement = A + B
+ C + D + E + F¥G + H
A recalculated annual revenue
requirement will go into effect every
January 1 based on the above formula
and updated financial data. WesternUGP will annually notify SPP and make
data and information available to
interested parties for review and
comment related to the recalculated
annual revenue requirement on or
shortly after September 1 of the
preceding year. Data used and the
charges resulting from using this
formula will be posted on the applicable
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
42393
SPP website and Western-UGP’s Open
Access Same-Time Information System
(OASIS).
Rate Schedule WAUW–AS3
October 1, 2020
(Supersedes Rate Schedule WAUW–
AS3 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
REGULATION AND FREQUENCY
RESPONSE SERVICE—WAUW
Effective
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Applicable
This Rate Schedule applies to the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Regulation
and Frequency Response Service
(Regulation) is necessary to provide for
the continuous balancing of resources,
generation, and interchange with load
and for maintaining scheduled
interconnection frequency at 60 cycles
per second (60 Hz). Regulation is
accomplished by committing on-line
generation whose output is raised or
lowered, predominantly through the use
of automatic generating control
equipment, as necessary, to follow the
moment-by-moment changes in load.
The obligation to maintain this balance
between resources and load lies with
the Western Area Power
Administration-Upper Great Plains
Region (Western-UGP) as the WAUW
operator. The SPP Transmission
Customer must either purchase this
service from SPP or make alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Regulation
obligation. Western-UGP’s annual
revenue requirement for Regulation
(outlined below) will be used by SPP to
calculate the WAUW charges for
Regulation.
Western-UGP supports the
installation of renewable sources of
energy but recognizes that certain
operational constraints exist in
managing the significant fluctuations
that are a normal part of their operation.
When Western-UGP purchases power
resources to provide Regulation to
E:\FR\FM\14JYN1.SGM
14JYN1
42394
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
intermittent resources serving load
within Western-UGP’s WAUW, costs for
these regulation resources will become
part of Western’s Regulation revenue
requirement, which will be billed by
SPP, as the Transmission Provider, to a
SPP Transmission Customer along with
the associated transmission service
provided by SPP under the SPP Tariff.
However, Western-UGP will not
regulate for the difference between the
output of an intermittent resource
located within Western-UGP’s WAUW
and a delivery schedule from that
generator serving load located outside of
Western-UGP’s WAUW. Intermittent
resources serving load outside WesternUGP’s WAUW will be required to be
pseudo-tied or dynamically scheduled
to another Balancing Authority Area.
An intermittent resource, for the
limited purpose of this Rate Schedule,
is an electric generator that is not
dispatchable and cannot store its fuel
source and, therefore, cannot respond to
changes in demand or respond to
transmission security constraints.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps)
Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Capacity Used for Regulation (kW-year)
E = Capacity Purchases for Regulation ($)
F = Prior Period True-up
Regulation Annual Revenue Requirement =
(A * B / C) * D + E + F
A recalculated revenue requirement
will go into effect every January 1 based
on the above formula and updated
financial data. Western-UGP will
annually notify SPP and make data and
information available to interested
parties for review and comment related
to the recalculated annual revenue
requirement on or shortly after
September 1 of the preceding year. Data
used and the charges resulting from
using this formula will be posted on the
applicable SPP website and WesternUGP’s Open Access Same-Time
Information System (OASIS).
Rate Schedule WAUW–AS4
October 1, 2020
(Supersedes Rate Schedule WAUW–
AS4 dated October 1, 2015, through
September 30, 2020)
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
ENERGY IMBALANCE SERVICE—
WAUW
Effective
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Applicable
This Rate Schedule applies to the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Energy
Imbalance Service is provided when a
difference occurs between scheduled
and actual delivery of energy to a load
located within Western Area Power
Administration-Upper Great Plains
Region’s (Western-UGP) WAUW over a
single hour (or different dispatch
interval for energy imbalance service
market, if applicable). Given the
Southwest Power Pool, Inc. (SPP)
Integrated Marketplace does not extend
into the Western Interconnection,
Western-UGP, as the Balancing
Authority, will offer to provide Energy
Imbalance Service in the WAUW at the
request of SPP, if it is capable of doing
so, from its own resources or from
resources available to it including
possible participation in a Western
Interconnection energy imbalance
service market. SPP is the Transmission
Provider for the eligible Western-UGP
facilities transferred to the functional
control of SPP in the WAUW. Energy
Imbalance Service is needed when
transmission service is provided by SPP
and used to serve load within the
WAUW, or when a difference occurs
between the expected and actual
delivery of energy to/from the WAUW
over a single hour (or different dispatch
interval for energy imbalance service
market, if applicable) in the event that
Western-UGP participates in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority. Energy Imbalance
Service in the WAUW will be billed by
SPP to the SPP Transmission Customer
along with the associated transmission
service provided by SPP. The SPP
Transmission Customer must either
purchase this service from SPP, or make
alternative comparable arrangements
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
pursuant to the SPP Tariff to satisfy its
Energy Imbalance Service obligation.
The SPP Transmission Customer will
incur a charge for either hourly energy
imbalances under this Schedule,
WAUW–AS4, or hourly generator
imbalances under Rate Schedule
WAUW–AS7 for imbalances occurring
during the same hour, but not both,
unless the imbalances aggravate rather
than offset each other.
Formula Rate
(A) In the event that Western-UGP
does not participate in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority, or such energy
imbalance market is unable to provide
the total energy imbalance requirements
for certain loads and generation within
the Balancing Authority Area:
For deviations within +/¥1.5 percent
(with a minimum of 2 MW) of the
scheduled transaction to be applied
hourly to any energy imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be netted on a
monthly basis and settled financially, at
the end of the month, at 100 percent of
the average incremental cost.
Deviations greater than +/¥1.5
percent up to 7.5 percent (or greater
than 2 MW up to 10 MW) of the
scheduled transaction to be applied
hourly to any energy imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be settled financially,
at the end of each month. When energy
taken in a schedule hour is greater than
the energy scheduled, the charge is 110
percent of incremental cost. When
energy taken is less than the scheduled
amount, the credit is 90 percent of the
incremental cost.
Deviations greater than +/¥7.5
percent (or 10 MW) of the scheduled
transaction to be applied hourly to any
energy imbalance that occurs as a result
of the SPP Transmission Customer’s
scheduled transaction(s) will be settled
at 125 percent of Western-UGP’s
incremental cost when energy taken in
a schedule hour is greater than the
energy scheduled or 75 percent of
Western- UGP’s incremental cost when
energy taken by a SPP Transmission
Customer is less than the scheduled
amount.
Western-UGP’s incremental cost will
be based upon a representative hourly
energy index or combination of indexes.
The index to be used will be posted on
the applicable SPP website and
Western-UGP’s Open Access Same-Time
Information System (OASIS) at least 30
days before use for determining the
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
Western-UGP incremental cost and will
not be changed more often than once
per year unless Western-UGP
determines that the existing index is no
longer a reliable price index.
The pricing and charge for deviations
in the above deviation bandwidths is as
specified above. Data used and the
charges resulting from using this
formula will be posted on the applicable
SPP website and Western-UGP’s OASIS.
(B) In the event that Western-UGP
participates in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority:
Charges to the SPP Transmission
Customer will reflect only the passthrough of the applicable charges
associated with the Western
Interconnection energy imbalance
service market assessed to Western-UGP
as the WAUW Balancing Authority for
embedded load and/or generation in the
WAUW of such SPP Transmission
Customer that does not make adequate
alternate arrangements in such Western
Interconnection energy imbalance
service market or other alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Energy
Imbalance Service obligation.
Western-UGP will post notice on the
applicable SPP website and WesternUGP’s OASIS, and also notify existing
SPP Transmission Customers, at least 30
days before Western-UGP participates in
a Western Interconnection energy
imbalance service market, as the
Balancing Authority. Western-UGP will
also post information related to the
charges assessed by the market operator
for Energy Imbalance Service in the
WAUW under such Western
Interconnection energy imbalance
service market.
Data used and the charges resulting
from using this formula will be posted
on the applicable SPP website and
Western-UGP’s OASIS.
Rate Schedule WAUW–AS5
October 1, 2020
(Supersedes Rate Schedule WAUW–
AS5 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
OPERATING RESERVE—
SPINNING RESERVE SERVICE—
WAUW
Effective
Beginning on October 1, 2020, and
remaining in effect through September
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Applicable
This Rate Schedule applies to the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Operating
Reserve-Spinning Reserve Service
(Spinning Reserves) is needed to serve
load immediately in the event of a
system contingency. Spinning Reserves
may be provided by generating units
that are on-line and loaded at less than
maximum output. Given the Southwest
Power Pool, Inc. (SPP) Integrated
Marketplace does not extend into the
Western Interconnection, Western Area
Power Administration-Upper Great
Plains Region (Western-UGP), as the
Balancing Authority, will offer to
provide Spinning Reserves, if available,
at the request of SPP as the
Transmission Provider in the WAUW.
Operating Reserve-Spinning Reserve
Service in the WAUW will be billed by
SPP to the SPP Transmission Customer
along with the associated transmission
service provided by SPP. The SPP
Transmission Customer must either
purchase this service from SPP or make
alternative comparable arrangements
pursuant to the SPP Tariff to satisfy its
Spinning Reserves obligation. WesternUGP’s annual revenue requirement for
Spinning Reserves (outlined below) will
be utilized by SPP to calculate the
WAUW charges for Spinning Reserves.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps)
Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Maximum Load in the WAUW (kW)
E = Maximum Generation in the WAUW
(kW)
F = Reserve Sharing Program Requirement
based upon Load (%)—See Note 1
G = Reserve Sharing Program Requirement
based upon Generation (%)—See Note 2
H = Prior Period True-up
I = Annual cost associated with WesternUGP’s current reserve sharing group
membership
Note 1: Currently 3% in the Northwest
Power Pool (NWPP) Reserve Sharing
Program.
Note 2: Currently 3% in the NWPP Reserve
Sharing Program.
Spinning Reserves Annual Revenue
Requirement = (A * B/C) * ((D * F)
+ (E * G)) + H + I
A recalculated revenue requirement
will go into effect every January 1 based
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
42395
on the above formula and updated
financial, load/generation, and Reserve
Sharing Program requirements data.
Western-UGP will annually notify SPP
and make data and information
available to interested parties for review
and comment related to the recalculated
annual revenue requirement on or
shortly after September 1 of the
preceding year. Data used and the
charges resulting from using this
formula will be posted on the applicable
SPP website and Western-UGP’s Open
Access Same-Time Information System
(OASIS).
If resources are not available from a
Western-UGP resource, Western-UGP, at
the request of SPP as the Transmission
Provider, will offer to purchase the
Spinning Reserves and pass through the
costs, plus an amount for
administration, to SPP for the SPP
Transmission Customer.
In the event that Spinning Reserves
are called upon for emergency use, the
SPP Transmission Customer will be
assessed a charge for energy used at the
prevailing market energy rate in the
WAUW. The prevailing market energy
rate will be based upon a representative
hourly energy index or combination of
indexes. The index to be used will be
posted on the applicable SPP website
and Western UGP’s OASIS at least 30
days before use for determining the
prevailing market energy rate and will
not be changed more often than once
per year unless Western-UGP
determines that the existing index is no
longer a reliable price index. The SPP
Transmission Customer would be
responsible for providing transmission
service to get the Spinning Reserves to
its destination.
Rate Schedule WAUW–AS6
October 1, 2020
(Supersedes Rate Schedule WAUW–
AS6 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
OPERATING RESERVE—
SUPPLEMENTAL RESERVE
SERVICE—WAUW
Effective
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
E:\FR\FM\14JYN1.SGM
14JYN1
42396
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
Applicable
This Rate Schedule applies to the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Operating
Reserve-Supplemental Reserve Service
(Supplemental Reserves) is needed to
serve load in the event of a system
contingency; however, it is not available
immediately to serve load but rather
within a short period of time.
Supplemental Reserves may be
provided by generating units that are
on-line but unloaded, by quick-start
generation, or by interruptible load.
Given the Southwest Power Pool, Inc.
(SPP) Integrated Marketplace does not
extend into the Western
Interconnection, Western Area Power
Administration-Upper Great Plains
Region (Western-UGP), as the Balancing
Authority, will offer to provide
Supplemental Reserves, if available, at
the request of SPP as the Transmission
Provider, in the WAUW. Operating
Reserve-Supplemental Reserve Service
in the WAUW will be billed by SPP to
the SPP Transmission Customer along
with the associated transmission service
provided by SPP. The SPP Transmission
Customer must either purchase this
service from SPP or make alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its
Supplemental Reserves obligation.
Western-UGP’s annual revenue
requirement for Supplemental Reserves
(outlined below) will be utilized by SPP
to calculate the WAUW charges for
Supplemental Reserves.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps)
Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Maximum Load in the WAUW (kW)
E = Maximum Generation in the WAUW
(kW)
F = Reserve Sharing Program Requirement
based upon Load (%)—See Note 1
G = Reserve Sharing Program Requirement
based upon Generation (%)—See Note 2
H = Prior Period True-up
I = Annual cost associated with WesternUGP’s current reserve sharing group
membership
on the above formula and updated
financial, load/generation, and Reserve
Sharing Program requirements data.
Western-UGP will annually notify SPP
and make data and information
available to interested parties for review
and comment related to the recalculated
annual revenue requirement on or
shortly after September 1 of the
preceding year. Data used and the
charges resulting from using this
formula will be posted on the applicable
SPP website and Western-UGP’s Open
Access Same-Time Information System
(OASIS).
If resources are not available from a
Western-UGP resource, Western-UGP, at
the request of SPP as the Transmission
Provider, will offer to purchase the
Supplemental Reserves and pass
through the costs, plus an amount for
administration, to SPP for the SPP
Transmission Customer.
In the event Supplemental Reserves
are called upon for emergency use, the
SPP Transmission Customer will be
assessed a charge for energy used at the
prevailing market energy rate in the
WAUW. The prevailing market energy
rate will be based upon a representative
hourly energy index or combination of
indexes. The index to be used will be
posted on the applicable SPP website
and Western-UGP’s OASIS at least 30
days before use for determining the
prevailing market energy rate and will
not be changed more often than once
per year unless Western-UGP
determines that the existing index is no
longer a reliable price index. The SPP
Transmission Customer would be
responsible for providing transmission
service to get the Supplemental
Reserves to its destination.
Rate Schedule WAUW–AS7
October 1, 2020
(Supersedes Rate Schedule WAUW–
AS7 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF
ENERGY WESTERN AREA POWER
ADMINISTRATION
UPPER GREAT PLAINS REGION PICKSLOAN MISSOURI BASIN
PROGRAM—EASTERN DIVISION
Note 1: Currently 3% in the Northwest
Power Pool (NWPP) Reserve Sharing
Program.
GENERATOR IMBALANCE
SERVICE—WAUW
Note 2: Currently 3% in the NWPP Reserve
Sharing Program.
Beginning on October 1, 2020, and
remaining in effect through September
30, 2025, or until superseded by another
rate schedule, whichever occurs earlier.
Notification of the effective date of the
formula rates will be published in the
Federal Register.
Effective
Supplemental Reserves Annual Revenue
Requirement = (A * B/C) * ((D * F)
+ (E * G)) + H + I
A recalculated revenue requirement
will go into effect every January 1 based
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
Applicable
This Rate Schedule applies to the
Western Area Power Administration,
Upper Great Plains West Balancing
Authority Area (WAUW). Generator
Imbalance Service is provided when a
difference occurs between the output of
a generator located within Western Area
Power Administration-Upper Great
Plains Region’s (Western-UGP) WAUW
and a delivery schedule from that
generator to (1) another Balancing
Authority Area or (2) a load within
Western-UGP’s WAUW over a single
hour (or different dispatch interval for
energy imbalance service market, if
applicable). Given the Southwest Power
Pool, Inc. (SPP) Integrated Marketplace
does not extend into the Western
Interconnection, Western-UGP, as the
Balancing Authority, will offer to
provide this service at the request of
SPP, if it is capable of doing so, from its
own resources or from resources
available to it including possible
participation in a Western
Interconnection energy imbalance
service market. SPP is the Transmission
Provider for the eligible Western-UGP
facilities transferred to the functional
control of SPP in the WAUW. Generator
Imbalance Service is needed when
transmission service is provided by SPP
and used to deliver energy from a
generator located within the WAUW, or
when a difference occurs between the
expected and actual delivery of energy
to/from the WAUW over a single hour
(or different dispatch interval for energy
imbalance service market, if applicable)
in the event that Western-UGP
participates in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority. Generator
Imbalance Service in the WAUW will be
billed by SPP to the SPP Transmission
Customer along with the associated
transmission service provided by SPP.
The SPP Transmission Customer must
either purchase this service from SPP or
make alternative comparable
arrangements pursuant to the SPP Tariff,
to satisfy its Generator Imbalance
Service obligation. The SPP
Transmission Customer will incur a
charge for either hourly generator
imbalances under this Schedule,
WAUW–AS7, or hourly energy
imbalances under Rate Schedule
WAUW–AS4 for imbalances occurring
during the same hour, but not both,
unless the imbalances aggravate rather
than offset each other.
Western-UGP supports the
installation of renewable sources of
energy but recognizes that certain
operational constraints exist in
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 85, No. 135 / Tuesday, July 14, 2020 / Notices
managing the significant fluctuations
that are a normal part of their operation.
Western-UGP has marketed the
maximum practical amount of power
from each of its projects, leaving little or
no flexibility for provision of additional
power services. Consequently, WesternUGP will not regulate for the difference
between the output of an intermittent
resource located within the WAUW and
a delivery schedule from that generator
serving load located outside of the
WAUW. Intermittent resources serving
load outside Western-UGP’s WAUW
will be required to be pseudo-tied or
dynamically scheduled to another
Balancing Authority Area.
An intermittent resource, for the
limited purpose of this Rate Schedule,
is an electric generator that is not
dispatchable and cannot store its fuel
source and, therefore, cannot respond to
changes in demand or respond to
transmission security constraints.
Formula Rate
(A) In the event that Western-UGP
does not participate in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority, or such energy
imbalance market is unable to provide
the total energy imbalance requirements
for certain loads and generation within
the Balancing Authority Area:
For deviations within +/¥1.5 percent
(with a minimum of 2 MW) of the
scheduled transaction to be applied
hourly to any generator imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be netted on a
monthly basis and settled financially, at
the end of the month, at 100 percent of
the average incremental cost.
Deviations greater than +/¥1.5
percent up to 7.5 percent (or greater
than 2 MW up to 10 MW) of the
scheduled transaction to be applied
hourly to any generator imbalance that
occurs as a result of the SPP
Transmission Customer’s scheduled
transaction(s) will be settled financially,
at the end of each month. When energy
delivered in a schedule hour from the
generation resource is less than the
energy scheduled, the charge is 110
percent of incremental cost. When
energy delivered from the generation
resource is greater than the scheduled
amount, the credit is 90 percent of the
incremental cost.
Deviations greater than +/¥7.5
percent (or 10 MW) of the scheduled
transaction to be applied hourly to any
generator imbalance that occurs as a
result of the SPP Transmission
Customer’s scheduled transaction(s)
will be settled at 125 percent of
VerDate Sep<11>2014
17:58 Jul 13, 2020
Jkt 250001
Western-UGP’s highest incremental cost
for the day when energy delivered in a
schedule hour is less than the energy
scheduled or 75 percent of WesternUGP’s lowest daily incremental cost
when energy delivered from the
generation resource is greater than the
scheduled amount. As an exception, an
intermittent resource will be exempt
from this deviation band and will pay
the deviation band charges for all
deviations greater than the larger of 1.5
percent or 2 MW.
Deviations from scheduled
transactions responding to directives by
the Transmission Provider, a Balancing
Authority, or a reliability coordinator
will not be subject to the deviation
bands identified above and, instead,
will be settled financially, at the end of
the month, at 100 percent of
incremental cost. Such directives may
include instructions to correct
frequency decay, respond to a reserve
sharing event, or change output to
relieve congestion.
Western-UGP’s incremental cost will
be based upon a representative hourly
energy index or combination of indexes.
The index to be used will be posted on
the applicable SPP website and
Western-UGP’s Open Access Same-Time
Information System (OASIS) at least 30
days before use for determining the
Western-UGP incremental cost and will
not be changed more often than once
per year unless Western-UGP
determines that the existing index is no
longer a reliable price index.
The pricing and charge for deviations
in the deviation bandwidths is as
specified above. Data used and the
charges resulting from using this
formula will be posted on the applicable
SPP website and Western-UGP’s OASIS.
(B) In the event that Western-UGP
participates in a Western
Interconnection energy imbalance
service market in the WAUW as the
Balancing Authority:
Charges to the SPP Transmission
Customer will reflect only the passthrough of the applicable charges
associated with the Western
Interconnection energy imbalance
service market assessed to Western-UGP
as the WAUW Balancing Authority for
embedded load and/or generation in the
WAUW of such SPP Transmission
Customer that does not make adequate
alternate arrangements in such Western
Interconnection energy imbalance
service market or other alternative
comparable arrangements pursuant to
the SPP Tariff to satisfy its Generator
Imbalance Service obligation.
Western-UGP will post notice on the
applicable SPP website and WesternUGP’s OASIS, and also notify existing
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
42397
Transmission Customers, at least 30
days before Western-UGP participates in
a Western Interconnection energy
imbalance service market, as the
Balancing Authority. Western-UGP will
also post information related to the
charges assessed by the market operator
for Generator Imbalance Service in the
WAUW under such Western
Interconnection energy imbalance
service market.
Data used and the charges resulting
from using this formula will be posted
on the applicable SPP website and
Western-UGP’s OASIS.
[FR Doc. 2020–15173 Filed 7–13–20; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–10010–06–Region 9]
El Centro Residential Lead Removal
Site, El Centro, CA; Notice of Proposed
CERCLA Settlement Agreement for
Recovery of Past Response Costs
Environmental Protection
Agency (EPA).
ACTION: Notice; request for comment.
AGENCY:
In accordance with the
Comprehensive Environmental
Response, Compensation and Liability
Act of 1980, as amended (CERCLA),
notice is hereby given of a proposed
administrative settlement for recovery of
response costs concerning the El Centro
Residential Lead Removal Site in El
Centro, California. The settlement is
entered into pursuant to Section
122(h)(1) of CERCLA, and it requires the
settling party to reimburse the
Environmental Protection Agency (EPA)
$50,000 in response costs that EPA
incurred at the Site.
DATES: EPA will receive written
comments relating to this proposed
settlement until 30 days after
publication in the Federal Register.
ADDRESSES: Please contact Craig
Whitenack at whitenack.craig@epa.gov
or (213) 244–1820 to request a copy of
the Settlement Agreement. Comments
on the Settlement Agreement should be
submitted in writing to Mr. Whitenack
at whitenack.craig@epa.gov. Comments
should reference the El Centro
Residential Lead Removal Site, El
Centro, California and the EPA Docket
Number for the Settlement Agreement,
EPA R9–20–004. If for any reason you
are not able to submit a comment by
email, please contact Mr. Whitenack at
(213) 244–1820 to make alternative
arrangements for submitting your
comment.
SUMMARY:
E:\FR\FM\14JYN1.SGM
14JYN1
Agencies
[Federal Register Volume 85, Number 135 (Tuesday, July 14, 2020)]
[Notices]
[Pages 42384-42397]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15173]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Western Area Power Administration
Pick-Sloan Missouri Basin Program--Eastern Division-Rate Order
No. WAPA-188
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of rate order concerning transmission and ancillary
services formula rates.
-----------------------------------------------------------------------
SUMMARY: The Assistant Secretary for Electricity confirms, approves,
and places into effect, on an interim basis, the formula rates for the
Pick-Sloan Missouri Basin Program--Eastern Division (P-SMBP--ED)
transmission
[[Page 42385]]
and ancillary services (Provisional Formula Rates). These rates will be
used by Western Area Power Administration's (WAPA) Upper Great Plains
Region (UGP) to provide rate data to Southwest Power Pool, Inc. (SPP),
the Regional Transmission Organization of which UGP is a member. These
new formula rates replace the existing transmission and ancillary
services formula rates under Rate Order No. WAPA-170 that expire on
September 30, 2020.
DATES: The Provisional Formula Rates under Rate Schedules WAUGP-ATRR,
WAUGP-AS1, WAUW-AS3, WAUW-AS4, WAUW-AS5, WAUW-AS6 and WAUW-AS7 are
effective October 1, 2020, and will remain in effect through September
30, 2025, pending confirmation and approval by the Federal Energy
Regulatory Commission (FERC) on a final basis or until superseded.
FOR FURTHER INFORMATION CONTACT: Mr. Jody Sundsted, Regional Manager,
Upper Great Plains Region, Western Area Power Administration, 2900 4th
Avenue North, Billings, MT 59101-1266; (406) 255-2801; email:
[email protected], or Linda Cady-Hoffman, Rates Manager, Upper Great
Plains Region, telephone: (406) 255-2920; email: [email protected].
SUPPLEMENTARY INFORMATION: On November 19, 2015, FERC confirmed and
approved Rate Schedules WAUGP-ATRR, WAUGP-AS1, WAUW-AS3, WAUW-AS4,
WAUW-AS5, WAUW-AS6 and WAUW-AS7 under Rate Order No. WAPA-170 on a
final basis effective for a 5-year period through September 30,
2020.\1\ Those schedules consisted of separate formula-based rates for
transmission and ancillary services for the transmission facilities in
the P-SMBP--ED that UGP transferred to the functional control of SPP.
The new rates continue the formula-based methodology that includes an
annual update to the financial data in the rate formulas. The charges
under these rates will be annually updated January 1 of each year
beginning 2021 and thereafter. The formula rates provide sufficient
revenue to recover annual expenses, including interest expense, and
repay capital investments within the cost recovery criteria set forth
in Department of Energy (DOE) Order RA 6120.2.
---------------------------------------------------------------------------
\1\ Order Confirming and Approving Rate Schedules on a Final
Basis, FERC Docket No. EF15-8-000, 153 FERC ] 61213 (2015). FERC
also accepted the inclusion of UGP's revenue requirements for
transmission and ancillary services under the SPP Open Access
Transmission Tariff, FERC Docket No. ER15-2354-000, 152 FERC ] 61257
(2015).
---------------------------------------------------------------------------
Legal Authority
By Delegation Order No. 00-037.00B, effective November 19, 2016,
the Secretary of Energy delegated: (1) The authority to develop power
and transmission rates to WAPA's Administrator; (2) the authority to
confirm, approve, and place such rates into effect on an interim basis
to the Deputy Secretary of Energy; and (3) the authority to confirm,
approve on a final basis, remand, or disapprove such rates to FERC. In
Delegation Order No. 00-002.00S, effective January 15, 2020, the
Secretary of Energy also delegated the authority to confirm, approve,
and place such rates into effect on an interim basis to the Under
Secretary of Energy. By Redelegation Order No. 00-002.10E, effective
February 14, 2020, the Under Secretary of Energy further delegated the
authority to confirm, approve, and place such rates into effect on an
interim basis to the Assistant Secretary for Electricity. This rate
action is issued under the Redelegation Order and DOE's procedures for
public participation in rate adjustments set forth at 10 CFR part
903.\2\
---------------------------------------------------------------------------
\2\ 50 FR 37835 (September 18, 1985) and 84 FR 5347 (February
21, 2019).
---------------------------------------------------------------------------
Following DOE's review of WAPA's proposal, I hereby confirm,
approve, and place Rate Order No. WAPA-188, which provides the formula
rates for transmission and ancillary services, into effect on an
interim basis. WAPA will submit Rate Order No. WAPA-188 to FERC for
confirmation and approval on a final basis.
Signing Authority
This document of the Department of Energy was signed on July 9,
2020, by Bruce J. Walker, Assistant Secretary for Electricity, pursuant
to delegated authority from the Secretary of Energy. That document,
with the original signature and date, is maintained by DOE. For
administrative purposes only, and in compliance with requirements of
the Office of the Federal Register, the undersigned DOE Federal
Register Liaison Officer has been authorized to sign and submit the
document in electronic format for publication, as an official document
of the Department of Energy. This administrative process in no way
alters the legal effect of this document upon publication in the
Federal Register.
Signed in Washington, DC, on July 9, 2020.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
DEPARTMENT OF ENERGY
In the matter of:
Western Area Power Administration Rate Adjustment for the Pick-Sloan
Missouri Basin Program--Eastern Division Transmission and Ancillary
Services Formula Rates;
[Rate Order No. WAPA-188]
Order Confirming, Approving, and Placing the Transmission and Ancillary
Services Formula Rates for the Pick-Sloan Missouri Basin Program--
Eastern Division Into Effect on an Interim Basis
The formula rates in Rate Order No. WAPA-188 are established
following section 302 of the Department of Energy (DOE) Organization
Act (42 U.S.C. 7152).\3\
---------------------------------------------------------------------------
\3\ This Act transferred to, and vested in, the Secretary of
Energy the power marketing functions of the Secretary of the
Department of the Interior and the Bureau of Reclamation
(Reclamation) under the Reclamation Act of 1902 (ch. 1093, 32 Stat.
388), as amended and supplemented by subsequent laws, particularly
section 9(c) of the Reclamation Project Act of 1939 (43 U.S.C.
485h(c)) and section 5 of the Flood Control Act of 1944 (16 U.S.C.
825s); and other acts that specifically apply to the projects
involved.
---------------------------------------------------------------------------
By Delegation Order No. 00-037.00B, effective November 19, 2016,
the Secretary of Energy delegated: (1) The authority to develop power
and transmission rates to the Western Area Power Administration's
(WAPA) Administrator; (2) the authority to confirm, approve, and place
into effect such rates on an interim basis to the Deputy Secretary of
Energy; and (3) the authority to confirm, approve on a final basis,
remand, or disapprove such rates to the Federal Energy Regulatory
Commission (FERC). In Delegation Order No. 00-002.00S, effective
January 15, 2020, the Secretary of Energy also delegated the authority
to confirm, approve, and place such rates into effect on an interim
basis to the Under Secretary of Energy. By Redelegation Order No. 00-
002.10E, effective February 14, 2020, the Under Secretary of Energy
further delegated the authority to confirm, approve, and place such
rates into effect on an interim basis to the Assistant Secretary for
Electricity. This rate action is issued under the Redelegation Order
and DOE's procedures for public participation in rate adjustments set
forth at 10 CFR part 903.\4\
---------------------------------------------------------------------------
\4\ 50 FR 37835 (September 18, 1985) and 84 FR 5347 (February
21, 2019).
---------------------------------------------------------------------------
[[Page 42386]]
Acronyms, Terms, and Definitions
As used in this Rate Order, the following acronyms, terms, and
definitions apply:
$/MW-year: Annual charge for capacity (i.e., $ per megawatt (MW)
per year).
ATRR: Annual Transmission Revenue Requirement is the net revenue
requirement for the Transmission Services calculated in accordance with
the Formula Rate.
BA: Balancing Authority--The responsible entity that integrates
resource plans ahead of time, maintains load-interchange-generation
balance within a designated area, and supports interconnection
frequency in real-time.
Balancing Authority Area: An electric system or systems, bounded by
interconnection metering and telemetry, capable of controlling
generation to maintain its interchange schedule with other Balancing
Authorities and contributing to frequency regulation of the
Interconnection.
Capacity: The electric capability of a generator, transformer,
transmission circuit, or other equipment. It is expressed in kilowatts
(kW).
Corps: U.S. Army Corps of Engineers.
DOE: United States Department of Energy.
Energy: Power produced or delivered over a period of time. Measured
in terms of the work capacity over a period of time. Electric energy is
expressed in kilowatt-hours.
Energy Imbalance Service: A service that provides energy correction
for any hourly mismatch between a Southwest Power Pool Transmission
Customer's energy supply and the demand served.
FERC: Federal Energy Regulatory Commission.
FRN: Federal Register notice.
Generator Imbalance Service: A service that provides energy
correction for any hourly mismatch between generator output and a
delivery schedule from that generator to another Balancing Authority
Area or to a load within the same Balancing Authority Area.
kW: Kilowatt--the electrical unit of capacity that equals 1,000
watts.
kWh: Kilowatt-hour--the electrical unit of energy that equals 1,000
watts in 1 hour.
Load: The amount of electric power or energy delivered or required
at any specified point(s) on a system.
MW: Megawatt--the electrical unit of capacity that equals 1 million
watts or 1,000 kilowatts.
NEPA: National Environmental Policy Act of 1969 (42 U.S.C. 4321-
4347).
OASIS: Open Access Same-Time Information System--An electronic
posting system that a service provider maintains for transmission
access data that allows all customers to view information
simultaneously.
P-SMBP: Pick-Sloan Missouri Basin Program.
P-SMBP--ED: Pick-Sloan Missouri Basin Program--Eastern Division.
Provisional Formula Rate: A formula rate that has been confirmed,
approved, and placed into effect on an interim basis by the Assistant
Secretary for Electricity.
Rate Brochure: A document prepared for public distribution
explaining the rationale and background for the rate proposal contained
in this rate order.
Regulation and Frequency Response Service: A service that provides
for following the moment-to-moment variations in the demand or supply
in a Balancing Authority Area and maintaining scheduled interconnection
frequency.
Reserve Services: Spinning Reserve Service and Supplemental Reserve
Service.
Revenue Requirement: The revenue required to recover annual
expenses (such as operation and maintenance, purchase power,
transmission service expenses, interest expense, and deferred expenses)
and repay Federal investments, and other assigned costs.
Schedule: An agreed-upon transaction size (megawatts), beginning
and ending ramp times and rate, and type of service required for
delivery and receipt of power between the contracting parties and the
Balancing Authority(ies) involved in the transaction.
Scheduling, System Control and Dispatch Service: A service that
provides for (a) scheduling, (b) confirming and implementing an
interchange schedule with other balancing authorities, including
intermediary balancing authorities providing transmission service, and
(c) ensuring operational security during the interchange transaction.
Southwest Power Pool, Inc. (SPP): A Regional Transmission
Organization.
SPP's Integrated Marketplace (Integrated Marketplace): The SPP
Energy and Operating Reserve Markets and the Transmission Congestion
Rights Markets.
Spinning Reserve Service: Generation capacity needed to serve load
immediately in the event of a system contingency. Spinning Reserve
Service may be provided by generating units that are on-line and loaded
at less than maximum output.
Supplemental Reserve Service: Generation capacity needed to serve
load in the event of a system contingency; however, it is not available
immediately to serve load but rather within a short period of time.
Supplemental Reserve Service may be provided by generation units that
are on-line but unloaded, by quick start generation or by interruptible
load.
SPP Tariff: Southwest Power Pool, Open Access Transmission Tariff,
approved by FERC.
SPP Transmission Customer: Any eligible customer (or its designated
agent) that receives transmission service under the SPP Tariff.
Transmission Provider: Any utility that owns, operates, or controls
facilities used to transmit electric energy in interstate commerce. SPP
is the Transmission Provider under the SPP Tariff.
Transmission System: The facilities owned, controlled, or operated
by the transmission owner or Transmission Provider that are used by the
Transmission Provider to provide transmission service.
UMZ: Upper Missouri Zone--Multi-owner zone in SPP in which WAPA-UGP
participates as a Transmission Owner; also defined as Zone 19 under the
SPP Tariff. The UMZ includes transmission facilities located in both
the Eastern and Western Interconnections.
WAUW: Western Area Power Administration, Upper Great Plains West
Balancing Authority Area. WAUW is located in the Western
Interconnection.
WAPA: United States Department of Energy, Western Area Power
Administration.
Western Interconnection: A major alternating current power grid in
North America. The Western Interconnection stretches from Western
Canada south to Baja California in Mexico, reaching eastward over the
Rockies to the Great Plains. Western Interconnection is comprised of
the states of Washington, Oregon, California, Idaho, Nevada, Utah,
Arizona, Colorado, Wyoming, portions of Montana, South Dakota,
Nebraska, New Mexico and Texas in the United States, the Provinces of
British Columbia and Alberta in Canada, and a portion of the
Comisi[oacute]n Federal de Electricidad's system in Baja California in
Mexico.
WAPA-UGP: United States Department of Energy, Western Area Power
Administration, Upper Great Plains Region. Western-UGP is the
definition for WAPA's Upper Great Plains Region in the SPP Tariff.
Effective Date
The Provisional Formula Rate Schedules WAUGP-ATRR, WAUGP-AS1, WAUW-
AS3, WAUW-AS4,
[[Page 42387]]
WAUW-AS5, WAUW-AS6 and WAUW-AS7 are effective October 1, 2020, and will
remain in effect through September 30, 2025, pending approval by FERC
on a final basis or until superseded.
Public Notice and Comment
WAPA followed the Procedures for Public Participation in Power and
Transmission Rate Adjustments and Extensions, 10 CFR part 903, in
developing these formula rates. Following are the steps WAPA took to
involve interested parties in the rate process:
1. On August 22, 2019, a Federal Register notice (84 FR 43803)
(Proposal FRN) announced the proposed formula rates and launched the
90-day public consultation and comment period.
2. On August 23, 2019, WAPA notified all P-SMBP--ED customers and
interested parties of the proposed rates and provided a copy of the
Proposal FRN.
3. On September 24, 2019, WAPA held a public information forum in
Omaha, Nebraska, and on September 25, 2019, WAPA held a public
information forum in Bismarck, North Dakota. WAPA representatives
explained the proposed formula rates, answered questions, and gave
notice that more information was available in the customer Rate
Brochure.
4. On September 24, 2019, WAPA held a public comment forum in
Omaha, Nebraska, and on September 25, 2019, WAPA held a public comment
forum in Bismarck, North Dakota. This provided customers and other
interested parties with opportunity to comment for the record.
5. WAPA posted information about this rate process that contains
all dates, customer letters, presentations, FRNs, customer Rate
Brochure, and other information about this rate process at the
following locations: (a) WAPA-UGP's OASIS at: https://www.oasis.oati.com/wapa/; (b) WAPA-UGP's Rates web page at:
https://www.wapa.gov/regions/UGP/rates/Pages/rates.aspx; and (c) the
``Western Area Power Administration UGP Information'' link on SPP's
Member Related Postings website at: https://opsportal.spp.org/OASIS/Directory/Member%20Related%20Postings.
6. During the 90-day consultation and comment period, which ended
on November 20, 2019, WAPA received one oral comment (at the September
24th public comment forum) and one written set of comments. The
comments and WAPA's responses are addressed below. All comments have
been considered in the preparation of this Rate Order.
One representative of the following organization made oral
comments: Missouri River Energy Services (MRES).
Written comments were received from the following interested
parties: Missouri River Energy Services (MRES).
Project Description
The initial stages of the Missouri River Basin Project were
authorized by section 9 of the Flood Control Act of 1944 (58 Stat. 887,
890, Pub. L. 78-534). It was later renamed the P-SMBP. The P-SMBP is a
comprehensive program with the following authorized functions: Flood
control, navigation improvement, irrigation, municipal and industrial
water development, and hydroelectric production for the entire Missouri
River Basin.
WAPA-UGP owns and operates an extensive system of high-voltage
transmission facilities that it uses to market significant quantities
of Federally-generated hydroelectric power from the P-SMBP--ED.
WAPA-UGP is a Transmission Owner member of SPP pursuant to
negotiated provisions in its SPP Membership Agreement and the SPP
Bylaws and SPP Open Access Transmission Tariff (SPP OATT). Transmission
and ancillary services are provided by SPP under the SPP OATT for WAPA-
UGP's facilities transferred to the functional control of SPP. WAPA-UGP
has transmission facilities in both the Eastern and Western
Interconnections separated by the Miles City direct current tie and the
Fort Peck Power Plant substation. WAPA-UGP operates its Western Area
Power Administration, Upper Great Plains West (WAUW) Balancing
Authority Area in the Western Interconnection as the Balancing
Authority (BA), and has not placed the portion of its transmission
system located in the Western Interconnection into SPP's Integrated
Marketplace. WAPA-UGP still provides ancillary services associated with
its WAUW in the Western Interconnection as the BA.
WAPA-UGP's formula rates for transmission and ancillary services
will be applied so WAPA-UGP's costs can continue to be recovered under
the SPP OATT. WAPA-UGP's revenue requirements are added to the annual
revenue requirements of other transmission owners in the multi-owner
SPP pricing Zone 19, also identified as the Upper Missouri Zone (UMZ),
for transmission service billed by SPP within the UMZ. WAPA-UGP's
revenue requirements under these proposed rates also impact other costs
for transmission service within the broader SPP footprint. The formula
rates provide WAPA-UGP sufficient revenue to pay all annual costs,
including interest expenses, and repay investment.
P-SMBP--ED Transmission and Ancillary Services Rate Studies
Existing Rate Schedules WAUGP-ATRR, WAUGP-AS1, WAUW-AS3, WAUW-AS4,
WAUW-AS5, WAUW-AS6 and WAUW-AS7 were approved under Rate Order No.
WAPA-170 for a 5-year period beginning on October 1, 2015, and ending
September 30, 2020. Those rate schedules consisted of separate formula-
based rates for transmission service and ancillary services for the
transmission facilities in the P-SMBP--ED that WAPA-UGP transferred to
the functional control of SPP. The new rates continue the formula-based
methodology that includes an annual update to the financial data in the
rate formulas with only limited changes to: (1) The Formula Rate
Templates (Templates) to increase transparency through addition of
financial data source detail; (2) the Formula Rate Implementation
Protocols (Protocols) to clarify WAPA-UGP's rate implementation and
annual update procedures; (3) the Operating Reserves formula rates to
incorporate costs associated with WAPA-UGP's current reserve sharing
group membership; and (4) the rate schedules for Energy Imbalance and
Generator Imbalance to accommodate participation in a Western
Interconnection energy imbalance service market.
WAPA prepared Transmission and Ancillary Services rates studies to
ensure that the formula rates are based on the cost of service of the
WAPA-UGP eligible transmission facilities that are included in the UMZ
and the associated operation of the WAUW. These studies included all
applicable expenses and associated offsetting revenues.
Provisional Rates
The revenue requirements for 2020 for the individual services are
outlined in the following table.
[[Page 42388]]
Provisional WAPA-UGP Transmission and Ancillary Services Formula Rates
------------------------------------------------------------------------
Provisional 2020
Service Rate schedule No. annual revenue
requirement
------------------------------------------------------------------------
Transmission.................. WAUGP-ATRR....... $136,325,626--SPP
Sched 9; $666,093--
SPP Sched 11
(Zonal); $111,344--
SPP Sched 11
(Regional).
Scheduling, System Control, WAUGP-AS1........ $11,534,163.
and Dispatch.
Regulation and Frequency WAUW-AS3......... $291,973.
Response.
Operating Reserves--Spinning WAUW-AS5 and WAUW- $409,789.
and Supplemental Reserves. AS6.
Energy Imbalance.............. WAUW-AS4......... N/A.
Generator Imbalance........... WAUWA-AS7........ N/A.
------------------------------------------------------------------------
Transmission and Ancillary Rate Discussion
WAPA-UGP includes facilities in the UMZ ATRR calculation that meet
Transmission Facility criteria as identified in Attachment AI to SPP's
OATT. WAPA-UGP identifies any portion of the ATRR eligible for recovery
under SPP Schedule 11 pursuant to the SPP OATT in its Rate Formula
Template submitted under Attachment H of the SPP OATT.
WAPA-UGP will true-up the cost estimates with actual costs. Revenue
collected in excess of WAPA-UGP's actual net revenue requirement will
be returned to customers through a credit against a revenue requirement
in a subsequent year. Actual revenues that are less than the net
revenue requirement would likewise be recovered in a subsequent year.
The true-up procedure will ensure that WAPA-UGP will recover no more
and no less than the actual transmission costs for the year.
Data used in the annual recalculation of the formula rate effective
on January 1 each year will be made available for review and comment on
or around September 1 each year as described in the Protocols. WAPA-UGP
will provide customers the opportunity to discuss and comment on the
recalculated rates on or before November 15, 2020, and annually by
November 15 of subsequent years as described in the Protocols. The
Protocols that describe the meetings where customers have opportunity
to discuss and comment are available online at the following locations:
(1) WAPA-UGP's OASIS at: https://www.oasis.oati.com/wapa/; (2)
WAPA-UGP's Rates web page at: https://www.wapa.gov/regions/UGP/rates/Pages/rates.aspx; and (3) the ``Western Area Power Administration UGP
Information'' link on SPP's Member Related Postings website at: https://opsportal.spp.org/OASIS/Directory/Member%20Related%20Postings. This
procedure ensures that interested parties are aware of the data used to
calculate the rates. This also provides interested parties the
opportunity to comment before the costs are collected through the
formula rate.
Formula Transmission Rate
WAPA-UGP will continue to use its current formula rate calculation
methodology for its ATRR, provided under Rate Schedule WAUGP-ATRR. This
rate schedule includes WAPA-UGP's transmission facilities in both the
Eastern and Western Interconnections that are transferred to the
functional control of SPP and used by SPP in order to provide
transmission service in the UMZ under the SPP OATT. Consistent with
WAPA-UGP's existing formula rate, WAPA-UGP will continue recovering
transmission system expenses and investments on a forward-looking basis
by using projections to estimate transmission costs for the upcoming
year, with a true-up of incurred costs in a subsequent year.
Transmission-related annual costs include operation and maintenance,
interest, administrative and general costs, and depreciation. Cost data
is submitted to SPP in standard revenue requirement templates and
classified as either ``Zonal'' or ``Regional'' costs as defined under
the SPP OATT. ``Zonal'' costs are recovered within the local pricing
zone while ``Regional'' costs are recovered across the entire SPP
footprint. The ATRR Formula Rate Template includes breakouts of the
annual revenue requirement for each individual Base Plan Upgrade, as
defined under the SPP OATT, assigned to and funded by WAPA-UGP, along
with ``Regional'' and ``Zonal'' allocation of the total net annual
revenue requirement for each Project.
Formula Rate Implementation Protocols
For transmission and ancillary services provided under the SPP
OATT, WAPA-UGP will continue to provide information relating to WAPA-
UGP's rate implementation and annual updates in Formula Rate
Implementation Protocols (Protocols), which together with the Formula
Rate Templates (Templates), comprise the Formula Rates that are
submitted to SPP to be incorporated in the SPP OATT. WAPA-UGP changed
its Protocols to clarify and include additional detail regarding WAPA-
UGP's rate implementation and annual update procedures. WAPA-UGP was
one of the first transmission owners in the UMZ to develop Protocols.
Therefore, WAPA-UGP updated its Protocols to be more consistent with
the protocols of other transmission owners in the UMZ that were
developed and approved after WAPA-UGP joined SPP.
Formula Rate for Scheduling, System Control, and Dispatch Service
WAPA-UGP will continue to use a formula-based rate methodology to
calculate its annual revenue requirement for Scheduling, System
Control, and Dispatch Service (SSCD), provided under Rate Schedule
WAUGP-AS1 for the SPP UMZ. This rate schedule also includes
transmission facilities in the WAUW.
SSCD is required to schedule the movement of power through, out of,
within, or into the SPP and/or WAUW Balancing Authority Area(s). WAPA-
UGP's annual revenue requirement for SSCD is utilized by SPP to
calculate the regional SPP Schedule 1 rate for the UMZ. WAPA-UGP's
annual revenue requirement for SSCD is derived by annualizing WAPA-
UGP's applicable transmission-related annual costs associated with the
provision of SSCD service, including operation and maintenance,
interest, administrative and general costs, and depreciation. Estimates
are calculated on a forward-looking basis by using projections to
determine applicable transmission-related costs associated with SSCD
for the upcoming year, with a true-up in a subsequent year, to be
provided to SPP for inclusion in Schedule 1 under the SPP Tariff.
WAPA-UGP will true-up the cost estimates with WAPA-UGP's actual
costs. Revenue collected in excess of WAPA-UGP's actual net revenue
requirement will be returned to customers through a credit against a
[[Page 42389]]
revenue requirement in a subsequent year. Actual revenues that are less
than the net revenue requirement would likewise be recovered in a
subsequent year. The true-up procedure will ensure that WAPA-UGP will
recover no more and no less than the actual costs for the year. WAPA-
UGP included additional information regarding implementation and annual
updates for SSCD in its revised Protocols.
Formula Rate for Regulation and Frequency Response Service
WAPA-UGP will continue to use a formula-based rate methodology for
Regulation and Frequency Response Service (Regulation) for the WAUW,
provided under Rate Schedule WAUW-AS3. WAPA-UGP provides Regulation and
Frequency Response Service in the WAUW as the BA. Regulation and
Frequency Response Service in the WAUW is provided primarily by Corps
facilities. Under the formula rate methodology, the Corps' generation
fixed charge rate (in percent) is applied to the net plant investment
of the Corps generation to derive an annual Corps generation cost. This
cost is divided by the capacity at the plants to derive a dollar-per-
megawatt amount for Corps-installed capacity ($/MW-year). This dollar-
per-megawatt amount is applied to the capacity of Corps generation
reserved for Regulation and Frequency Response Service in the WAUW,
producing the annual Corps generation cost for this service. WAPA-UGP's
annual revenue requirement is recovered under the SPP Tariff under Rate
Schedule WAUW-AS3.
Regulation and Frequency Response Service is necessary to provide
for the continuous balancing of resources, generation, and interchange
with load and for maintaining scheduled interconnection frequency at 60
cycles per second (60 Hz). Regulation is accomplished by committing on-
line generation whose output is raised or lowered, predominantly
through the use of automatic generating control equipment, as
necessary, to follow the moment-by-moment changes in load. The
obligation to maintain this balance between resources and load lies
with the WAPA-UGP as the WAUW operator. The SPP Transmission Customer
must either purchase this service from SPP or make alternative
comparable arrangements pursuant to the SPP Tariff to satisfy its
Regulation obligation. WAPA-UGP's annual revenue requirement for
Regulation will be used by SPP to calculate the WAUW charges for
Regulation. WAPA-UGP included additional information regarding
implementation and annual updates for Regulation in its revised
Protocols.
WAPA-UGP will true-up the cost estimates with WAPA-UGP's actual
costs. Revenue collected in excess of WAPA-UGP's actual net revenue
requirement will be returned through a credit in a subsequent year.
Actual revenues that are less than the net revenue requirement would
likewise be recovered in a subsequent year. The true-up procedure will
ensure that WAPA-UGP will recover no more and no less than the actual
costs for the year.
WAPA-UGP supports the installation of renewable sources of energy
but recognizes that certain operational constraints exist in managing
the significant fluctuations that are a normal part of their operation.
When WAPA-UGP purchases power resources to provide Regulation to
intermittent resources serving load within WAPA-UGP's WAUW, costs for
these regulation resources will become part of WAPA's Regulation
revenue requirement, which will be billed by SPP, as the Transmission
Provider, to a SPP Transmission Customer along with the associated
transmission service provided by SPP under the SPP Tariff. However,
WAPA-UGP will not regulate for the difference between the output of an
intermittent resource located within WAPA-UGP's WAUW and a delivery
schedule from that generator serving load located outside of WAPA-UGP's
WAUW. Intermittent resources serving load outside WAPA-UGP's WAUW will
be required to be pseudo-tied or dynamically scheduled to another
Balancing Authority Area.
An intermittent resource, for the limited purpose of this rate
schedule, is an electric generator that is not dispatchable and cannot
store its fuel source and, therefore, cannot respond to changes in
demand or respond to transmission security constraints.
Formula Rate for Energy Imbalance Service
WAPA-UGP will continue to use its current formula rate calculation
methodology for Energy Imbalance Service (Energy Imbalance), which is
provided under Rate Schedule WAUW-AS4. This rate schedule addresses
Energy Imbalance associated with UGP's WAUW in the Western
Interconnection. WAPA-UGP also revised Rate Schedule WAUW-AS4 to
accommodate participation in a Western Interconnection energy imbalance
service market by WAPA-UGP as the BA. WAPA-UGP is providing additional
information regarding implementation and annual updates for Energy
Imbalance in its revised Protocols.
Energy Imbalance Service is provided when a difference occurs
between the scheduled and the actual delivery of energy to a load
located within WAPA-UGP's WAUW over a single hour (or different
dispatch interval for energy imbalance service market, if applicable).
Given the SPP Integrated Marketplace does not extend into the Western
Interconnection, WAPA-UGP as the BA, will offer to provide Energy
Imbalance Service in the WAUW at the request of SPP, if it is capable
of doing so, from its own resources or from resources available to it
including possible participation in a Western Interconnection energy
imbalance market. SPP is the Transmission Provider for the eligible
WAPA-UGP facilities transferred to the functional control of SPP in the
WAUW. Energy Imbalance Service is needed when transmission service is
provided by SPP and used to serve load within the WAUW, or when a
difference occurs between the expected and actual delivery of energy
to/from the WAUW over a single hour (or different dispatch interval for
energy imbalance service market, if applicable) in the event that WAPA-
UGP participates in a Western Interconnection energy imbalance service
market in the WAUW as the BA. Energy Imbalance Service in the WAUW will
be billed by SPP to the SPP Transmission Customer along with the
associated transmission service provided by SPP. The SPP Transmission
Customer must either purchase this service from SPP, or make
alternative comparable arrangements pursuant to the SPP Tariff to
satisfy its Energy Imbalance Service Obligation.
The SPP Transmission Customer will incur a charge for either hourly
energy imbalances under this Schedule, WAUW-AS4, or hourly generator
imbalances under Rate Schedule WAUW-AS7 for imbalances occurring during
the same hour, but not both, unless the imbalances aggravate rather
than offset each other.
This Rate Order puts in place two options for how Energy Imbalance
Service in the WAUW may be provided:
(A) In the event that WAPA-UGP does not participate in a Western
Interconnection energy imbalance market in the WAUW as the BA, or such
energy imbalance market is unable to provide the total energy imbalance
requirements for certain loads and generation within the Balancing
Authority Area:
The rate for service will be based up deviation bands as follows:
(i) Deviations within +/-1.5 percent (with a minimum of 2 MW) of the
scheduled transaction to be applied hourly to any
[[Page 42390]]
energy imbalance that occurs as a result of the SPP Transmission
Customer's scheduled transaction(s) will be netted on a monthly basis
and settled financially, at the end of the month, at 100 percent of the
average incremental cost for the month; (ii) deviations greater than +/
-1.5 percent up to 7.5 percent (or greater than 2 MW up to 10 MW) of
the scheduled transaction(s) to be applied hourly to any energy
imbalance that occurs as a result of the SPP Transmission Customer's
scheduled transaction(s) will be settled financially, at the end of
each month, at a charge of 110 percent of incremental cost when energy
taken by the SPP Transmission Customer in a schedule hour is greater
than the energy scheduled or a credit of 90 percent of incremental cost
when energy taken by a SPP Transmission Customer in a schedule hour is
less than the scheduled amount; and (iii) deviations greater than +/-
7.5 percent (or 10 MW) of the scheduled transaction to be applied
hourly to any energy imbalance that occurs as a result of the SPP
Transmission Customer's scheduled transaction(s) will be settled at 125
percent of WAPA-UGP's incremental cost when energy taken by the SPP
Transmission Customer in a schedule hour that is greater than the
energy scheduled, or 75 percent of WAPA-UGP's incremental cost when
energy taken by a SPP Transmission Customer is less than the scheduled
amount.
WAPA-UGP's incremental cost will be based on a representative
hourly energy index or combination of indexes. The index to be used, or
any change to the index, will be posted on the applicable SPP website
and WAPA-UGP's OASIS at least 30 days before use for determining the
WAPA-UGP incremental cost and will not be changed more often than once
per year unless WAPA-UGP determines that the existing index is no
longer a reliable price index.
(B) In the event that WAPA-UGP participates in a Western
Interconnection energy imbalance market in the WAUW as the BA: Charges
to the SPP Transmission Customer will reflect only the pass-through of
the applicable charges associated with the Western Interconnection
energy imbalance service market assessed to WAPA-UGP as the WAUW BA for
embedded load and/or generation in the WAUW of such SPP Transmission
Customer that does not make adequate alternate arrangements in such
Western Interconnection energy imbalance service market or other
alternative comparable arrangements pursuant to the SPP Tariff to
satisfy its Energy Imbalance Service obligation.
WAPA-UGP will post notice on the applicable SPP website and WAPA-
UGP's OASIS, and also notify existing SPP Transmission Customers, at
least 30 days before WAPA-UGP participates in a Western Interconnection
energy imbalance service market, as the BA. WAPA-UGP will also post
information related to the charges assessed by the market operator for
Energy Imbalance Service in the WAUW under such Western Interconnection
energy imbalance service market.
WAPA-UGP will follow Option A above beginning on October 1, 2020.
WAPA-UGP will follow Option B above in the event that WAPA-UGP
participates in a Western Interconnection energy imbalance market.
Formula Rate for Generator Imbalance Service
WAPA-UGP will continue to use its current formula rate calculation
methodology for Generator Imbalance Service (Generator Imbalance),
which is provided under Rate Schedule WAUW-AS7. This rate schedule
addresses Generator Imbalance associated with WAPA-UGP's WAUW in the
Western Interconnection. WAPA-UGP also changed Rate Schedule WAUW-AS7
to accommodate participation in a Western Interconnection energy
imbalance market by WAPA-UGP as the BA. WAPA-UGP is providing
additional information regarding implementation and annual updates for
Generator Imbalance in its revised Protocols.
Generator Imbalance Service is provided when a difference occurs
between the output of a generator located within WAPA-UGP's WAUW and a
delivery schedule from that generator to: (1) Another Balancing
Authority Area or (2) a load within WAPA-UGP'S WAUW over a single hour
(or different dispatch interval for energy imbalance service market, if
applicable). Given the SPP Integrated Marketplace does not extend into
the Western Interconnection, WAPA-UGP, as the BA, will offer to provide
this service at the request of SPP, if it is capable of doing so, from
its own resources or resources available to it, including possible
participation in a Western Interconnection energy imbalance service
market. SPP is the Transmission Provider for the eligible WAPA-UGP
facilities transferred to the functional control of SPP in the WAUW.
Generator Imbalance Service is needed when transmission service is
provided by SPP and used to deliver energy from a generator located
within the WAUW, or when a difference occurs between the expected and
actual delivery of energy to/from the WAUW over a single hour (or
different dispatch interval for energy imbalance service market, if
applicable) in the event that WAPA-UGP participates in a Western
Interconnection energy imbalance service market in the WAUW as the BA.
Generator Imbalance Service in the WAUW will be billed by SPP to the
SPP Transmission Customer along with the associated transmission
service. The SPP Transmission Customer must either purchase this
service from SPP, or make alternative comparable arrangements pursuant
to the SPP Tariff, to satisfy its Generator Imbalance Service
obligation. The SPP Transmission Customer will incur a charge for
either hourly generator imbalances under this rate schedule, WAUW-AS7,
or hourly energy imbalances under Rate Schedule WAUW-AS4 for imbalances
occurring during the same hour, but not both, unless the imbalances
aggravate rather than offset each other.
WAPA-UGP supports the installation of renewable sources of energy
but recognizes that certain operational constraints exist in managing
the significant fluctuations that are a normal part of their operation.
WAPA-UGP has marketed the maximum practical amount of power from each
of its projects, leaving little or no flexibility for provision of
additional power services. Consequently, WAPA-UGP will not regulate for
the difference between the output of an intermittent generator located
within the WAUW and a delivery schedule from that generator serving
load located outside of the WAUW. Intermittent resources serving load
outside WAPA-UGP's WAUW will be required to be pseudo-tied or
dynamically scheduled to another Balancing Authority Area.
An intermittent resource, for the limited purpose of this rate
schedule, is an electric generator that is not dispatchable and cannot
store its fuel source and, therefore, cannot respond to changes in
system demand or respond to transmission security constraints.
This Rate Order puts in place two options for how Generator
Imbalance Service in the WAUW may be provided:
(A) In the event that WAPA-UGP does not participate in a Western
Interconnection energy imbalance service market in the WAUW as the BA,
or such energy imbalance market is unable to provide the total energy
imbalance requirements for certain loads and generation within the
Balancing Authority Area:
The rate for service will be based on deviation bands as follows:
(i) For
[[Page 42391]]
deviations within +/-1.5 percent (with a minimum of 2 MW) of the
scheduled transaction to be applied hourly to any generator imbalance
that occurs as a result of the SPP Transmission Customer's scheduled
transaction(s) will be netted on a monthly basis and settled
financially, at the end of the month, at 100 percent of the average
incremental cost; (ii) deviations greater than +/-1.5 percent up to 7.5
percent (or greater than 2 MW up to 10 MW) of the scheduled transaction
to be applied hourly to any generator imbalance that occurs as a result
of the SPP Transmission Customer's scheduled transaction(s) will be
settled financially, at the end of each month, as a charge of 110
percent of incremental cost when energy delivered in a schedule hour
from the generation resource is less than the energy scheduled or a
credit of 90 percent of the incremental cost when energy delivered from
the generation resource is greater than the scheduled amount; and (iii)
deviations greater than +/-7.5 percent (or 10 MW) of the scheduled
transaction to be applied hourly to any generator imbalance that occurs
as a result of the SPP Transmission Customer's scheduled transaction(s)
will be settled at 125 percent of WAPA-UGP's highest incremental cost
for the day when energy delivered in a schedule hour is less than the
energy scheduled or 75 percent of WAPA-UGP's lowest daily incremental
cost when energy delivered from the generation resource is greater than
the scheduled amount. An intermittent resource will be exempt from this
deviation band and will pay the deviation band charges for all
deviations greater than the larger of 1.5 percent or 2 MW.
Deviations from scheduled transactions responding to directives by
the Transmission Provider, a BA, or a reliability coordinator will not
be subject to the deviation bands identified above and, instead, will
be settled financially at the end of the month at 100 percent of
incremental cost. Such directives may include instructions to correct
frequency decay, respond to a reserve sharing event, or change output
to relieve congestion.
WAPA-UGP's incremental cost will be based on a representative
hourly energy index or combination of indexes. The index to be used, or
any change to the index, will be posted on the applicable SPP website
and WAPA-UGP's OASIS at least 30 days before use for determining the
WAPA-UGP incremental cost and will not be changed more often than once
per year unless WAPA-UGP determines that the existing index is no
longer a reliable price index.
(B) In the event that WAPA-UGP participates in a Western
Interconnection energy imbalance service market in the WAUW as the BA:
Charges to the SPP Transmission Customer will reflect only the pass-
through of the applicable charges associated with the Western
Interconnection energy imbalance service market assessed to WAPA-UGP as
the WAUW BA for embedded load and/or generation in the WAUW of such SPP
Transmission Customer that does not make adequate alternate
arrangements in such Western Interconnection energy imbalance service
market or other alternative comparable arrangements pursuant to the SPP
Tariff to satisfy its Generator Imbalance Service Obligation.
WAPA-UGP will post notice on the applicable SPP website and WAPA-
UGP's OASIS, and also notify existing Transmission Customers, at least
30 days before WAPA-UGP participates in a Western Interconnection
energy imbalance service market, as the BA. WAPA-UGP will also post
information related to the charges assessed by the market operator for
Generator Imbalance Service in the WAUW under such Western
Interconnection energy imbalance service market.
WAPA-UGP will follow Option A above beginning on October 1, 2020.
WAPA-UGP will follow Option B above in the event that WAPA-UGP
participates in a Western Interconnection energy imbalance service
market.
Formula Rates for Operating Reserves Service--Spinning and Supplemental
WAPA-UGP will continue to use its current formula rate calculation
methodologies for Operating Reserve--Spinning Reserve Service and
Operating Reserve--Supplemental Reserve Service (collectively,
Operating Reserves) provided under Rate Schedules WAUW-AS5 and WAUW-
AS6, respectively, with changes to the rate formulas to incorporate
costs associated with its current reserve sharing group membership.
These rate schedules address Operating Reserves associated with WAPA-
UGP's WAUW in the Western Interconnection. WAPA-UGP changed the rate
formulas to incorporate costs associated with its current reserve
sharing group membership. In addition, WAPA-UGP included additional
information regarding implementation and annual updates for Operating
Reserves in its revised Protocols. Given the SPP Integrated Marketplace
does not extend into the Western Interconnection, WAPA-UGP will
continue to provide Operating Reserves in the WAUW as the BA. WAPA-UGP
utilizes the reserve requirement of the reserve sharing group of which
WAPA-UGP is currently a member for its transmission system in the
Western Interconnection.
WAPA-UGP's annual cost of generation for Reserve Services is
determined by multiplying the Corps' generation fixed charge rate (in
percent) by the net plant investment of the Corps generation producing
an annual Corps generation cost. This cost is divided by the capacity
at the plants to derive a dollar-per-megawatt amount for Corps
installed capacity ($/MW-year). This dollar-per-megawatt amount is then
applied to the capacity of Corps generation reserved for Reserve
Services in the WAUW, producing the annual Corps generation cost to
provide this service. WAPA-UGP's annual revenue requirement for Reserve
Services is then determined by taking the annual Corps generation cost
to provide this service and adding costs associated with the current
reserve sharing group, if applicable. WAPA-UGP's annual revenue
requirement will be recovered under the SPP Tariff. This rate design
recovers only WAPA-UGP's revenue requirement associated with Reserve
Services. The Reserve Services will apply to both load and generation
in the WAUW (i.e., transmission service for loads in the WAUW and
transmission service for generation deliveries out of the WAUW).
WAPA-UGP will true-up the cost estimates with WAPA-UGP's actual
costs. Revenue collected in excess of WAPA-UGP's actual net revenue
requirement will be returned through a credit in a subsequent year.
Actual revenues that are less than the net revenue requirement would
likewise be recovered in a subsequent year. The true-up procedure will
ensure that WAPA-UGP will recover no more and no less than the actual
costs for the year.
Spinning Reserves
Operating Reserve-Spinning Reserve Service (Spinning Reserves) is
needed to serve load immediately in the event of a system contingency.
Spinning Reserves may be provided by generating units that are on-line
and loaded at less than maximum output. Given the SPP Integrated
Marketplace does not extend into the Western Interconnection, WAPA-UGP,
as the BA, will offer to provide Spinning Reserves, if available, at
the request of SPP as the Transmission Provider in the WAUW. Spinning
Reserves in the WAUW will be billed by SPP to the SPP
[[Page 42392]]
Transmission Customer along with the associated transmission service
provided by SPP. The SPP Transmission Customer must either purchase
this service from SPP or make alternative comparable arrangements
pursuant to the SPP Tariff to satisfy its Spinning Reserves obligation.
WAPA-UGP's annual revenue requirement for Spinning Reserves will be
utilized by SPP to calculate the WAUW charges for Spinning Reserves.
If resources are not available from a WAPA-UGP resource, WAPA-UGP,
at the request of SPP as the Transmission Provider, will offer to
purchase the Spinning Reserves and pass through the costs, plus an
amount for administration, to SPP for the SPP Transmission Customer.
In the event that Spinning Reserves are called upon for emergency
use, the SPP Transmission Customer will be assessed a charge for energy
used at the prevailing market energy rate in the WAUW. The prevailing
market energy rate will be based upon a representative hourly energy
index or combination of indexes. The index to be used, or any change to
the index, will be posted on the applicable SPP website and WAPA-UGP's
OASIS at least 30 days before use for determining the prevailing market
energy rate and will not be changed more often than once per year
unless WAPA-UGP determines that the existing index is no longer a
reliable price index. The SPP Transmission Customer would be
responsible for providing transmission service to get the Spinning
Reserves to its destination.
Supplemental Reserves
Operating Reserve-Supplemental Reserve Service (Supplemental
Reserves) is needed to serve load in the event of a system contingency;
however, it is not available immediately to serve load but rather
within a short period of time.
Supplemental Reserves may be provided by generating units that are
on-line but unloaded, by quick-start generation, or by interruptible
load. Given the SPP Integrated Marketplace does not extend into the
Western Interconnection, WAPA-UGP, as the BA, will offer to provide
Supplemental Reserves, if available, at the request of SPP as the
Transmission Provider, in the WAUW. Operating Reserve-Supplemental
Reserve Service in the WAUW will be billed by SPP to the SPP
Transmission Customer along with the associated transmission service
provided by SPP. The SPP Transmission Customer must either purchase
this service from SPP or make alternative comparable arrangements
pursuant to the SPP Tariff to satisfy its Supplemental Reserves
obligation. WAPA-UGP's annual revenue requirement for Supplemental
Reserves will be utilized by SPP to calculate the WAUW charges for
Supplemental Reserves.
Comments
WAPA received one oral comment and one comment letter during the
public consultation and comment period. The comments have been
paraphrased, where appropriate, without compromising the meaning of the
comments.
Comment: The customer notes its appreciation of the efforts WAPA is
making to increase transparency of the formula rate template, and that
its comments are generally centered on transparency. As such, the
customer requests WAPA adjust the formula rate template to ensure
transparency for all stakeholders. Specifically, this includes
financial and source document data transparency and transparency on the
website.
Response: WAPA has reviewed the Formula Rate Templates and all
suggestions provided by the customer regarding transparency. WAPA has
updated the Formula Rate Templates to address the customer's comments.
These template changes include additional footnotes, links, references,
and other suggestions provided by the customer. WAPA has included the
additional financial and source document data on OASIS at: https://www.oasis.oati.com/wapa/.
Certification of Rates
WAPA's Administrator certified that the Provisional Formula Rates
for P-SMB--ED under Rate Schedules WAUGP-ATRR, WAUGP-AS1, WAUW-AS3,
WAUW-AS4, WAUW-AS5, WAUW-AS6, and WAUW-AS7 are the lowest possible
rates, consistent with sound business principles. The Provisional
Formula Rates were developed following administrative policies and
applicable laws.
Availability of Information
Information about this rate adjustment, including the customer Rate
Brochure, comments, letters, memorandums, and other supporting
materials that were used to develop the Provisional Formula Rates, is
available for inspection and copying at the Upper Great Plains Regional
Office, located at 2900 4th Avenue North, Billings, Montana. Many of
these documents are also available online at the following locations:
(1) WAPA-UGP's OASIS at: https://www.oasis.oati.com/wapa/; (2)
WAPA-UGP's Rates web page at: https://www.wapa.gov/regions/UGP/rates/Pages/rates.aspx; and (3) the ``Western Area Power Administration UGP
Information'' link on SPP's Member Related Postings website at: https://opsportal.spp.org/OASIS/Directory/Member%20Related%20Postings.
RATEMAKING PROCEDURE REQUIREMENTS
Environmental Compliance
WAPA has determined that this action is categorically excluded from
the preparation of an environmental assessment or an environmental
impact statement.\5\ A copy of the categorical exclusion determination
is available on WAPA's website at: https://www.wapa.gov/regions/UGP/Environment/Pages/environment.aspx.
---------------------------------------------------------------------------
\5\ The determination was done in compliance with the National
Environmental Policy Act (NEPA) of 1969, as amended, 42 U.S.C. 4321-
4347; the Council on Environmental Quality Regulations for
implementing NEPA (40 CFR parts 1500-1508); and DOE NEPA
Implementing Procedures and Guidelines (10 CFR part 1021).
---------------------------------------------------------------------------
Determination Under Executive Order 12866
WAPA has an exemption from centralized regulatory review under
Executive Order 12866; accordingly, no clearance of this notice by the
Office of Management and Budget is required.
Submission to the Federal Energy Regulatory Commission
The Provisional Formula Rates herein confirmed, approved, and
placed into effect on an interim basis, together with supporting
documents, will be submitted to FERC for confirmation and final
approval.
ORDER
In view of the above and under the authority delegated to me, I
hereby confirm, approve, and place into effect, on an interim basis,
Rate Order No. WAPA-188. The rates will remain in effect on an interim
basis until: (1) FERC confirms and approves them on a final basis; (2)
subsequent rates are confirmed and approved; or (3) such rates are
superseded.
Dated: July 9, 2020.
Bruce J. Walker,
Assistant Secretary for Electricity.
Rate Schedule WAUGP-ATRR
October 1, 2020
(Supersedes Rate Schedule WAUGP-ATRR dated October 1, 2015, through
September 30, 2020)
[[Page 42393]]
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
ANNUAL TRANSMISSION REVENUE REQUIREMENT FOR TRANSMISSION SERVICE
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
Western Area Power Administration-Upper Great Plains Region's
(Western-UGP) formula based Annual Transmission Revenue Requirement
(ATRR) for its eligible transmission related facilities included under
the Southwest Power Pool, Inc. (SPP) Tariff will be calculated using
the formula outlined below.
Formula Rate
Define:
A = Operation & Maintenance allocated to transmission ($)
B = Depreciation allocated to transmission ($)
C = Interest Expense allocated to transmission ($)
D = Revenue Credits ($)
E = Scheduling, System Control, and Dispatch costs ($)
F = Prior Period True-up ($)
ATRR = A + B + C-D-E + F
Note: Western-UGP will identify any portion(s) of the ATRR
eligible for recovery under SPP Schedule 11 pursuant to the SPP
Tariff in its Rate Formula Template submitted under Attachment H of
the SPP Tariff.
A recalculated annual revenue requirement will go into effect every
January 1 based on the above formula and updated financial data.
Western-UGP will annually notify SPP and make data and information
available to interested parties for review and comment related to the
recalculated annual revenue requirement on or shortly after September 1
of the preceding year. Data used and the charges resulting from using
this formula will be posted on the applicable SPP website and Western-
UGP's Open Access Same-Time Information System (OASIS).
Rate Schedule WAUGP-AS1
October 1, 2020
(Supersedes Rate Schedule WAUGP-AS1 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
SCHEDULING, SYSTEM CONTROL, AND DISPATCH SERVICE
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
Scheduling, System Control, and Dispatch Service (SSCD) is required
to schedule the movement of power through, out of, within, or into the
Southwest Power Pool, Inc. (SPP) Balancing Authority Area and/or the
Western Area Power Administration, Upper Great Plains West Balancing
Authority Area (WAUW). Western Area Power Administration-Upper Great
Plains Region's (Western-UGP) annual revenue requirement for SSCD will
be used by SPP to calculate the regional SPP Schedule 1 rate for SPP
through and out transactions, and also to calculate the zonal SPP
Schedule 1 rate for the Upper Missouri Zone (UMZ or Zone 19). This rate
will also be charged by SPP for SPP Transmission Service provided
within the UMZ in the Western Interconnection.
Formula Rate
Define:
A = Operation & Maintenance for SSCD ($)
B = Administrative and General Expense for SSCD ($)
C = Depreciation for SSCD ($)
D = Taxes Other than Income Taxes for Transmission ($)
E = Allocation of General Plant for SSCD ($)
F = Cost of Capital for SSCD ($)
G = SSCD Revenue from non-Transmission facilities ($)
H = Prior Period True-up ($)
SSCD Annual Revenue Requirement = A + B + C + D + E + F-G + H
A recalculated annual revenue requirement will go into effect every
January 1 based on the above formula and updated financial data.
Western-UGP will annually notify SPP and make data and information
available to interested parties for review and comment related to the
recalculated annual revenue requirement on or shortly after September 1
of the preceding year. Data used and the charges resulting from using
this formula will be posted on the applicable SPP website and Western-
UGP's Open Access Same-Time Information System (OASIS).
Rate Schedule WAUW-AS3
October 1, 2020
(Supersedes Rate Schedule WAUW-AS3 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
REGULATION AND FREQUENCY RESPONSE SERVICE--WAUW
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
This Rate Schedule applies to the Western Area Power
Administration, Upper Great Plains West Balancing Authority Area
(WAUW). Regulation and Frequency Response Service (Regulation) is
necessary to provide for the continuous balancing of resources,
generation, and interchange with load and for maintaining scheduled
interconnection frequency at 60 cycles per second (60 Hz). Regulation
is accomplished by committing on-line generation whose output is raised
or lowered, predominantly through the use of automatic generating
control equipment, as necessary, to follow the moment-by-moment changes
in load. The obligation to maintain this balance between resources and
load lies with the Western Area Power Administration-Upper Great Plains
Region (Western-UGP) as the WAUW operator. The SPP Transmission
Customer must either purchase this service from SPP or make alternative
comparable arrangements pursuant to the SPP Tariff to satisfy its
Regulation obligation. Western-UGP's annual revenue requirement for
Regulation (outlined below) will be used by SPP to calculate the WAUW
charges for Regulation.
Western-UGP supports the installation of renewable sources of
energy but recognizes that certain operational constraints exist in
managing the significant fluctuations that are a normal part of their
operation. When Western-UGP purchases power resources to provide
Regulation to
[[Page 42394]]
intermittent resources serving load within Western-UGP's WAUW, costs
for these regulation resources will become part of Western's Regulation
revenue requirement, which will be billed by SPP, as the Transmission
Provider, to a SPP Transmission Customer along with the associated
transmission service provided by SPP under the SPP Tariff. However,
Western-UGP will not regulate for the difference between the output of
an intermittent resource located within Western-UGP's WAUW and a
delivery schedule from that generator serving load located outside of
Western-UGP's WAUW. Intermittent resources serving load outside
Western-UGP's WAUW will be required to be pseudo-tied or dynamically
scheduled to another Balancing Authority Area.
An intermittent resource, for the limited purpose of this Rate
Schedule, is an electric generator that is not dispatchable and cannot
store its fuel source and, therefore, cannot respond to changes in
demand or respond to transmission security constraints.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps) Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Capacity Used for Regulation (kW-year)
E = Capacity Purchases for Regulation ($)
F = Prior Period True-up
Regulation Annual Revenue Requirement = (A * B / C) * D + E + F
A recalculated revenue requirement will go into effect every
January 1 based on the above formula and updated financial data.
Western-UGP will annually notify SPP and make data and information
available to interested parties for review and comment related to the
recalculated annual revenue requirement on or shortly after September 1
of the preceding year. Data used and the charges resulting from using
this formula will be posted on the applicable SPP website and Western-
UGP's Open Access Same-Time Information System (OASIS).
Rate Schedule WAUW-AS4
October 1, 2020
(Supersedes Rate Schedule WAUW-AS4 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
ENERGY IMBALANCE SERVICE--WAUW
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
This Rate Schedule applies to the Western Area Power
Administration, Upper Great Plains West Balancing Authority Area
(WAUW). Energy Imbalance Service is provided when a difference occurs
between scheduled and actual delivery of energy to a load located
within Western Area Power Administration-Upper Great Plains Region's
(Western-UGP) WAUW over a single hour (or different dispatch interval
for energy imbalance service market, if applicable). Given the
Southwest Power Pool, Inc. (SPP) Integrated Marketplace does not extend
into the Western Interconnection, Western-UGP, as the Balancing
Authority, will offer to provide Energy Imbalance Service in the WAUW
at the request of SPP, if it is capable of doing so, from its own
resources or from resources available to it including possible
participation in a Western Interconnection energy imbalance service
market. SPP is the Transmission Provider for the eligible Western-UGP
facilities transferred to the functional control of SPP in the WAUW.
Energy Imbalance Service is needed when transmission service is
provided by SPP and used to serve load within the WAUW, or when a
difference occurs between the expected and actual delivery of energy
to/from the WAUW over a single hour (or different dispatch interval for
energy imbalance service market, if applicable) in the event that
Western-UGP participates in a Western Interconnection energy imbalance
service market in the WAUW as the Balancing Authority. Energy Imbalance
Service in the WAUW will be billed by SPP to the SPP Transmission
Customer along with the associated transmission service provided by
SPP. The SPP Transmission Customer must either purchase this service
from SPP, or make alternative comparable arrangements pursuant to the
SPP Tariff to satisfy its Energy Imbalance Service obligation.
The SPP Transmission Customer will incur a charge for either hourly
energy imbalances under this Schedule, WAUW-AS4, or hourly generator
imbalances under Rate Schedule WAUW-AS7 for imbalances occurring during
the same hour, but not both, unless the imbalances aggravate rather
than offset each other.
Formula Rate
(A) In the event that Western-UGP does not participate in a Western
Interconnection energy imbalance service market in the WAUW as the
Balancing Authority, or such energy imbalance market is unable to
provide the total energy imbalance requirements for certain loads and
generation within the Balancing Authority Area:
For deviations within +/-1.5 percent (with a minimum of 2 MW) of
the scheduled transaction to be applied hourly to any energy imbalance
that occurs as a result of the SPP Transmission Customer's scheduled
transaction(s) will be netted on a monthly basis and settled
financially, at the end of the month, at 100 percent of the average
incremental cost.
Deviations greater than +/-1.5 percent up to 7.5 percent (or
greater than 2 MW up to 10 MW) of the scheduled transaction to be
applied hourly to any energy imbalance that occurs as a result of the
SPP Transmission Customer's scheduled transaction(s) will be settled
financially, at the end of each month. When energy taken in a schedule
hour is greater than the energy scheduled, the charge is 110 percent of
incremental cost. When energy taken is less than the scheduled amount,
the credit is 90 percent of the incremental cost.
Deviations greater than +/-7.5 percent (or 10 MW) of the scheduled
transaction to be applied hourly to any energy imbalance that occurs as
a result of the SPP Transmission Customer's scheduled transaction(s)
will be settled at 125 percent of Western-UGP's incremental cost when
energy taken in a schedule hour is greater than the energy scheduled or
75 percent of Western- UGP's incremental cost when energy taken by a
SPP Transmission Customer is less than the scheduled amount.
Western-UGP's incremental cost will be based upon a representative
hourly energy index or combination of indexes. The index to be used
will be posted on the applicable SPP website and Western-UGP's Open
Access Same-Time Information System (OASIS) at least 30 days before use
for determining the
[[Page 42395]]
Western-UGP incremental cost and will not be changed more often than
once per year unless Western-UGP determines that the existing index is
no longer a reliable price index.
The pricing and charge for deviations in the above deviation
bandwidths is as specified above. Data used and the charges resulting
from using this formula will be posted on the applicable SPP website
and Western-UGP's OASIS.
(B) In the event that Western-UGP participates in a Western
Interconnection energy imbalance service market in the WAUW as the
Balancing Authority:
Charges to the SPP Transmission Customer will reflect only the
pass-through of the applicable charges associated with the Western
Interconnection energy imbalance service market assessed to Western-UGP
as the WAUW Balancing Authority for embedded load and/or generation in
the WAUW of such SPP Transmission Customer that does not make adequate
alternate arrangements in such Western Interconnection energy imbalance
service market or other alternative comparable arrangements pursuant to
the SPP Tariff to satisfy its Energy Imbalance Service obligation.
Western-UGP will post notice on the applicable SPP website and
Western-UGP's OASIS, and also notify existing SPP Transmission
Customers, at least 30 days before Western-UGP participates in a
Western Interconnection energy imbalance service market, as the
Balancing Authority. Western-UGP will also post information related to
the charges assessed by the market operator for Energy Imbalance
Service in the WAUW under such Western Interconnection energy imbalance
service market.
Data used and the charges resulting from using this formula will be
posted on the applicable SPP website and Western-UGP's OASIS.
Rate Schedule WAUW-AS5
October 1, 2020
(Supersedes Rate Schedule WAUW-AS5 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
OPERATING RESERVE--SPINNING RESERVE SERVICE--WAUW
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
This Rate Schedule applies to the Western Area Power
Administration, Upper Great Plains West Balancing Authority Area
(WAUW). Operating Reserve-Spinning Reserve Service (Spinning Reserves)
is needed to serve load immediately in the event of a system
contingency. Spinning Reserves may be provided by generating units that
are on-line and loaded at less than maximum output. Given the Southwest
Power Pool, Inc. (SPP) Integrated Marketplace does not extend into the
Western Interconnection, Western Area Power Administration-Upper Great
Plains Region (Western-UGP), as the Balancing Authority, will offer to
provide Spinning Reserves, if available, at the request of SPP as the
Transmission Provider in the WAUW. Operating Reserve-Spinning Reserve
Service in the WAUW will be billed by SPP to the SPP Transmission
Customer along with the associated transmission service provided by
SPP. The SPP Transmission Customer must either purchase this service
from SPP or make alternative comparable arrangements pursuant to the
SPP Tariff to satisfy its Spinning Reserves obligation. Western-UGP's
annual revenue requirement for Spinning Reserves (outlined below) will
be utilized by SPP to calculate the WAUW charges for Spinning Reserves.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps) Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Maximum Load in the WAUW (kW)
E = Maximum Generation in the WAUW (kW)
F = Reserve Sharing Program Requirement based upon Load (%)--See
Note 1
G = Reserve Sharing Program Requirement based upon Generation (%)--
See Note 2
H = Prior Period True-up
I = Annual cost associated with Western-UGP's current reserve
sharing group membership
Note 1: Currently 3% in the Northwest Power Pool (NWPP) Reserve
Sharing Program.
Note 2: Currently 3% in the NWPP Reserve Sharing Program.
Spinning Reserves Annual Revenue Requirement = (A * B/C) * ((D * F) +
(E * G)) + H + I
A recalculated revenue requirement will go into effect every
January 1 based on the above formula and updated financial, load/
generation, and Reserve Sharing Program requirements data. Western-UGP
will annually notify SPP and make data and information available to
interested parties for review and comment related to the recalculated
annual revenue requirement on or shortly after September 1 of the
preceding year. Data used and the charges resulting from using this
formula will be posted on the applicable SPP website and Western-UGP's
Open Access Same-Time Information System (OASIS).
If resources are not available from a Western-UGP resource,
Western-UGP, at the request of SPP as the Transmission Provider, will
offer to purchase the Spinning Reserves and pass through the costs,
plus an amount for administration, to SPP for the SPP Transmission
Customer.
In the event that Spinning Reserves are called upon for emergency
use, the SPP Transmission Customer will be assessed a charge for energy
used at the prevailing market energy rate in the WAUW. The prevailing
market energy rate will be based upon a representative hourly energy
index or combination of indexes. The index to be used will be posted on
the applicable SPP website and Western UGP's OASIS at least 30 days
before use for determining the prevailing market energy rate and will
not be changed more often than once per year unless Western-UGP
determines that the existing index is no longer a reliable price index.
The SPP Transmission Customer would be responsible for providing
transmission service to get the Spinning Reserves to its destination.
Rate Schedule WAUW-AS6
October 1, 2020
(Supersedes Rate Schedule WAUW-AS6 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
OPERATING RESERVE--SUPPLEMENTAL RESERVE SERVICE--WAUW
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
[[Page 42396]]
Applicable
This Rate Schedule applies to the Western Area Power
Administration, Upper Great Plains West Balancing Authority Area
(WAUW). Operating Reserve-Supplemental Reserve Service (Supplemental
Reserves) is needed to serve load in the event of a system contingency;
however, it is not available immediately to serve load but rather
within a short period of time.
Supplemental Reserves may be provided by generating units that are
on-line but unloaded, by quick-start generation, or by interruptible
load. Given the Southwest Power Pool, Inc. (SPP) Integrated Marketplace
does not extend into the Western Interconnection, Western Area Power
Administration-Upper Great Plains Region (Western-UGP), as the
Balancing Authority, will offer to provide Supplemental Reserves, if
available, at the request of SPP as the Transmission Provider, in the
WAUW. Operating Reserve-Supplemental Reserve Service in the WAUW will
be billed by SPP to the SPP Transmission Customer along with the
associated transmission service provided by SPP. The SPP Transmission
Customer must either purchase this service from SPP or make alternative
comparable arrangements pursuant to the SPP Tariff to satisfy its
Supplemental Reserves obligation. Western-UGP's annual revenue
requirement for Supplemental Reserves (outlined below) will be utilized
by SPP to calculate the WAUW charges for Supplemental Reserves.
Formula Rate
Define:
A = U.S. Army Corps of Engineers (Corps) Fixed Charge Rate (%)
B = Corps Generation Net Plant Costs ($)
C = Plant Capacity (kW)
D = Maximum Load in the WAUW (kW)
E = Maximum Generation in the WAUW (kW)
F = Reserve Sharing Program Requirement based upon Load (%)--See
Note 1
G = Reserve Sharing Program Requirement based upon Generation (%)--
See Note 2
H = Prior Period True-up
I = Annual cost associated with Western-UGP's current reserve
sharing group membership
Note 1: Currently 3% in the Northwest Power Pool (NWPP) Reserve
Sharing Program.
Note 2: Currently 3% in the NWPP Reserve Sharing Program.
Supplemental Reserves Annual Revenue Requirement = (A * B/C) * ((D * F)
+ (E * G)) + H + I
A recalculated revenue requirement will go into effect every
January 1 based on the above formula and updated financial, load/
generation, and Reserve Sharing Program requirements data. Western-UGP
will annually notify SPP and make data and information available to
interested parties for review and comment related to the recalculated
annual revenue requirement on or shortly after September 1 of the
preceding year. Data used and the charges resulting from using this
formula will be posted on the applicable SPP website and Western-UGP's
Open Access Same-Time Information System (OASIS).
If resources are not available from a Western-UGP resource,
Western-UGP, at the request of SPP as the Transmission Provider, will
offer to purchase the Supplemental Reserves and pass through the costs,
plus an amount for administration, to SPP for the SPP Transmission
Customer.
In the event Supplemental Reserves are called upon for emergency
use, the SPP Transmission Customer will be assessed a charge for energy
used at the prevailing market energy rate in the WAUW. The prevailing
market energy rate will be based upon a representative hourly energy
index or combination of indexes. The index to be used will be posted on
the applicable SPP website and Western-UGP's OASIS at least 30 days
before use for determining the prevailing market energy rate and will
not be changed more often than once per year unless Western-UGP
determines that the existing index is no longer a reliable price index.
The SPP Transmission Customer would be responsible for providing
transmission service to get the Supplemental Reserves to its
destination.
Rate Schedule WAUW-AS7
October 1, 2020
(Supersedes Rate Schedule WAUW-AS7 dated October 1, 2015, through
September 30, 2020)
UNITED STATES DEPARTMENT OF ENERGY WESTERN AREA POWER ADMINISTRATION
UPPER GREAT PLAINS REGION PICK-SLOAN MISSOURI BASIN PROGRAM--EASTERN
DIVISION
GENERATOR IMBALANCE SERVICE--WAUW
Effective
Beginning on October 1, 2020, and remaining in effect through
September 30, 2025, or until superseded by another rate schedule,
whichever occurs earlier. Notification of the effective date of the
formula rates will be published in the Federal Register.
Applicable
This Rate Schedule applies to the Western Area Power
Administration, Upper Great Plains West Balancing Authority Area
(WAUW). Generator Imbalance Service is provided when a difference
occurs between the output of a generator located within Western Area
Power Administration-Upper Great Plains Region's (Western-UGP) WAUW and
a delivery schedule from that generator to (1) another Balancing
Authority Area or (2) a load within Western-UGP's WAUW over a single
hour (or different dispatch interval for energy imbalance service
market, if applicable). Given the Southwest Power Pool, Inc. (SPP)
Integrated Marketplace does not extend into the Western
Interconnection, Western-UGP, as the Balancing Authority, will offer to
provide this service at the request of SPP, if it is capable of doing
so, from its own resources or from resources available to it including
possible participation in a Western Interconnection energy imbalance
service market. SPP is the Transmission Provider for the eligible
Western-UGP facilities transferred to the functional control of SPP in
the WAUW. Generator Imbalance Service is needed when transmission
service is provided by SPP and used to deliver energy from a generator
located within the WAUW, or when a difference occurs between the
expected and actual delivery of energy to/from the WAUW over a single
hour (or different dispatch interval for energy imbalance service
market, if applicable) in the event that Western-UGP participates in a
Western Interconnection energy imbalance service market in the WAUW as
the Balancing Authority. Generator Imbalance Service in the WAUW will
be billed by SPP to the SPP Transmission Customer along with the
associated transmission service provided by SPP. The SPP Transmission
Customer must either purchase this service from SPP or make alternative
comparable arrangements pursuant to the SPP Tariff, to satisfy its
Generator Imbalance Service obligation. The SPP Transmission Customer
will incur a charge for either hourly generator imbalances under this
Schedule, WAUW-AS7, or hourly energy imbalances under Rate Schedule
WAUW-AS4 for imbalances occurring during the same hour, but not both,
unless the imbalances aggravate rather than offset each other.
Western-UGP supports the installation of renewable sources of
energy but recognizes that certain operational constraints exist in
[[Page 42397]]
managing the significant fluctuations that are a normal part of their
operation. Western-UGP has marketed the maximum practical amount of
power from each of its projects, leaving little or no flexibility for
provision of additional power services. Consequently, Western-UGP will
not regulate for the difference between the output of an intermittent
resource located within the WAUW and a delivery schedule from that
generator serving load located outside of the WAUW. Intermittent
resources serving load outside Western-UGP's WAUW will be required to
be pseudo-tied or dynamically scheduled to another Balancing Authority
Area.
An intermittent resource, for the limited purpose of this Rate
Schedule, is an electric generator that is not dispatchable and cannot
store its fuel source and, therefore, cannot respond to changes in
demand or respond to transmission security constraints.
Formula Rate
(A) In the event that Western-UGP does not participate in a Western
Interconnection energy imbalance service market in the WAUW as the
Balancing Authority, or such energy imbalance market is unable to
provide the total energy imbalance requirements for certain loads and
generation within the Balancing Authority Area:
For deviations within +/-1.5 percent (with a minimum of 2 MW) of
the scheduled transaction to be applied hourly to any generator
imbalance that occurs as a result of the SPP Transmission Customer's
scheduled transaction(s) will be netted on a monthly basis and settled
financially, at the end of the month, at 100 percent of the average
incremental cost.
Deviations greater than +/-1.5 percent up to 7.5 percent (or
greater than 2 MW up to 10 MW) of the scheduled transaction to be
applied hourly to any generator imbalance that occurs as a result of
the SPP Transmission Customer's scheduled transaction(s) will be
settled financially, at the end of each month. When energy delivered in
a schedule hour from the generation resource is less than the energy
scheduled, the charge is 110 percent of incremental cost. When energy
delivered from the generation resource is greater than the scheduled
amount, the credit is 90 percent of the incremental cost.
Deviations greater than +/-7.5 percent (or 10 MW) of the scheduled
transaction to be applied hourly to any generator imbalance that occurs
as a result of the SPP Transmission Customer's scheduled transaction(s)
will be settled at 125 percent of Western-UGP's highest incremental
cost for the day when energy delivered in a schedule hour is less than
the energy scheduled or 75 percent of Western-UGP's lowest daily
incremental cost when energy delivered from the generation resource is
greater than the scheduled amount. As an exception, an intermittent
resource will be exempt from this deviation band and will pay the
deviation band charges for all deviations greater than the larger of
1.5 percent or 2 MW.
Deviations from scheduled transactions responding to directives by
the Transmission Provider, a Balancing Authority, or a reliability
coordinator will not be subject to the deviation bands identified above
and, instead, will be settled financially, at the end of the month, at
100 percent of incremental cost. Such directives may include
instructions to correct frequency decay, respond to a reserve sharing
event, or change output to relieve congestion.
Western-UGP's incremental cost will be based upon a representative
hourly energy index or combination of indexes. The index to be used
will be posted on the applicable SPP website and Western-UGP's Open
Access Same-Time Information System (OASIS) at least 30 days before use
for determining the Western-UGP incremental cost and will not be
changed more often than once per year unless Western-UGP determines
that the existing index is no longer a reliable price index.
The pricing and charge for deviations in the deviation bandwidths
is as specified above. Data used and the charges resulting from using
this formula will be posted on the applicable SPP website and Western-
UGP's OASIS.
(B) In the event that Western-UGP participates in a Western
Interconnection energy imbalance service market in the WAUW as the
Balancing Authority:
Charges to the SPP Transmission Customer will reflect only the
pass-through of the applicable charges associated with the Western
Interconnection energy imbalance service market assessed to Western-UGP
as the WAUW Balancing Authority for embedded load and/or generation in
the WAUW of such SPP Transmission Customer that does not make adequate
alternate arrangements in such Western Interconnection energy imbalance
service market or other alternative comparable arrangements pursuant to
the SPP Tariff to satisfy its Generator Imbalance Service obligation.
Western-UGP will post notice on the applicable SPP website and
Western-UGP's OASIS, and also notify existing Transmission Customers,
at least 30 days before Western-UGP participates in a Western
Interconnection energy imbalance service market, as the Balancing
Authority. Western-UGP will also post information related to the
charges assessed by the market operator for Generator Imbalance Service
in the WAUW under such Western Interconnection energy imbalance service
market.
Data used and the charges resulting from using this formula will be
posted on the applicable SPP website and Western-UGP's OASIS.
[FR Doc. 2020-15173 Filed 7-13-20; 8:45 am]
BILLING CODE 6450-01-P