Download as PDF Federal Register / Vol. 85, No. 134 / Monday, July 13, 2020 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP20–68–000; CP20–70–000] Enable Gas Transmission, LLC; Enable Gulf Run Transmission, LLC; Notice of Revised Schedule for Environmental Review of The Gulf Run and Line CP Modifications Project This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for Enable Gas Transmission, LLC and Enable Gulf Run Transmission, LLC (collectively, Enable) Gulf Run and Line CP Modifications Project. The first notice of schedule, issued on April 28, 2020, identified July 31, 2020 as the EA issuance date. However, Enable filed supplemental information on June 23, 2020 related to certain modifications to its project. In addition, the U.S. Army Corps of Engineers (USACE) recently requested cooperating agency status for the project to ensure that the EA addresses the USACE National Environmental Policy Act requirements for processing Enable’s June 4, 2020 USACE application for a Clean Water Act Section 404 Individual Permit for the project. This change is in response to the court vacatur, in April 2020, of the Nationwide Permit 12 Program. As a result, Commission staff has revised the schedule for issuance of the EA. jbell on DSKJLSW7X2PROD with NOTICES Schedule for Environmental Review Issuance of the EA October 29, 2020 90-day Federal Authorization Decision Deadline January 27, 2021 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the VerDate Sep<11>2014 20:25 Jul 10, 2020 Jkt 250001 eLibrary link, enter the ‘‘Docket Number’’ excluding the last three digits (i.e., CP20–68 or –70), select a date range, and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208– 3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: July 7, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–15025 Filed 7–10–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12532–006] Pine Creek Mine, LLC; Notice of Petition for Declaratory Order Take notice that on June 3, 2020, pursuant to Rule 207 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 CFR 385.207(2019), Pine Creek Mine, LLC (PCM or Petitioner), filed a petition for declaratory order (Petition) requesting that the Commission issue a declaratory order finding that the California State Water Resources Control Board has waived its authority to issue a certification for the Pine Creek Mine Tunnel Hydroelectric Project under section 401 of the Clean Water Act, 33 U.S.C. 1341(a)(1), as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. Any person wishing to comment on PCM’s petition may do so.1 The 1 PCM’s request is part of its licensing proceeding in Project No. 12532–006. Thus, any person that intervened in the relicensing proceeding is already a party. Generally, the filing of a petition for a PO 00000 Frm 00034 Fmt 4703 Sfmt 9990 41971 deadline for filing comments is 30 days from the issuance of this notice. The Commission encourages electronic submission of comments in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should send comments to the following address: Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. Be sure to reference the project docket number (P–12532–006) with your submission. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on August 6, 2020. Dated: July 7, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–15024 Filed 7–10–20; 8:45 am] BILLING CODE 6717–01–P declaratory order involving an issue arising from the relicensing proceeding does not trigger a new opportunity to intervene. Accordingly, at this point in this proceeding, any person seeking to become a party to the proceeding must file a motion to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the Commission’s Rules of Practice and Procedures that provides justification by reference to the factors set forth in Rule 214(d). The Commission may limit a late intervenor’s participation to the issues raised in the petition for declaratory order. 18 CFR 385.214(d)(3)(i). E:\FR\FM\13JYN1.SGM 13JYN1

Agencies

[Federal Register Volume 85, Number 134 (Monday, July 13, 2020)]
[Notices]
[Page 41971]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-15025]



[[Page 41971]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP20-68-000; CP20-70-000]


Enable Gas Transmission, LLC; Enable Gulf Run Transmission, LLC; 
Notice of Revised Schedule for Environmental Review of The Gulf Run and 
Line CP Modifications Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Enable Gas Transmission, LLC and Enable Gulf Run 
Transmission, LLC (collectively, Enable) Gulf Run and Line CP 
Modifications Project. The first notice of schedule, issued on April 
28, 2020, identified July 31, 2020 as the EA issuance date. However, 
Enable filed supplemental information on June 23, 2020 related to 
certain modifications to its project. In addition, the U.S. Army Corps 
of Engineers (USACE) recently requested cooperating agency status for 
the project to ensure that the EA addresses the USACE National 
Environmental Policy Act requirements for processing Enable's June 4, 
2020 USACE application for a Clean Water Act Section 404 Individual 
Permit for the project. This change is in response to the court 
vacatur, in April 2020, of the Nationwide Permit 12 Program. As a 
result, Commission staff has revised the schedule for issuance of the 
EA.

Schedule for Environmental Review

Issuance of the EA October 29, 2020
90-day Federal Authorization Decision Deadline January 27, 2021

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, enter the 
``Docket Number'' excluding the last three digits (i.e., CP20-68 or -
70), select a date range, and follow the instructions. For assistance 
with access to eLibrary, the helpline can be reached at (866) 208-3676, 
TTY (202) 502-8659, or at [email protected]. The eLibrary link 
on the FERC website also provides access to the texts of formal 
documents issued by the Commission, such as orders, notices, and rule 
makings.

    Dated: July 7, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-15025 Filed 7-10-20; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.