Federal Register / Vol. 85, No. 125 / Monday, June 29, 2020 / Notices
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
3198R1 Evergy MO West & City of
Gilman City, MO Inter. Agr. to be
effective 8/22/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5068.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2129–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing: Rate
Schedule FERC No. 274 between TriState and Empire to be effective 6/24/
2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5074.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2130–000.
Applicants: Greenleaf Energy Unit 1
LLC.
Description: Tariff Cancellation:
Greenleaf Energy Unit 1, LLC Notice of
Cancellation of MBR Tariff to be
effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5088.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2131–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
2652R4 Waverly Wind Farm LLC GIA to
be effective 8/22/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5100.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2132–000.
Applicants: Edgecombe Genco, LLC.
Description: Notice of Cancellation of
Market-Based Rate Tariff of Edgecombe
Genco, LLC.
Filed Date: 6/23/20.
Accession Number: 20200623–5121.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2133–000.
Applicants: ISO New England Inc.,
Versant Power.
Description: Compliance filing:
Versant Power; Changes to Schedule
21–VP in Compliance with Order No.
864 to be effective 6/1/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5130.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2134–000.
Applicants: Cimarron Bend Wind
Project III, LLC.
Description: Baseline eTariff Filing:
Cimarron Bend Wind Project III MBR
Tariff to be effective 8/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5133.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2135–000.
Applicants: RE Mustang Two
Whirlaway LLC.
VerDate Sep<11>2014
20:25 Jun 26, 2020
Jkt 250001
Description: § 205(d) Rate Filing: RE
Mustang Two Whirlaway LLC SFA to be
effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5139.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2136–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
1298R1 Evergy Kansas South and AECI
Interconnection Agr to be effective 8/22/
2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5146.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2137–000.
Applicants: Starvation Solar I, LLC.
Description: Baseline eTariff Filing:
Starvation Solar I, LLC SFA
Concurrence to be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5176.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2138–000.
Applicants: Fort Rock Solar I, LLC.
Description: Baseline eTariff Filing:
Fort Rock Solar I, LLC SFA Concurrence
to be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5177.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2139–000.
Applicants: Fort Rock Solar IV, LLC.
Description: Baseline eTariff Filing:
Fort Rock Solar IV, LLC SFA
Concurrence to be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5178.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2140–000.
Applicants: Riley Solar I, LLC.
Description: Baseline eTariff Filing:
Riley Solar I, LLC SFA Concurrence to
be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5179.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2141–000.
Applicants: Fort Rock Solar IV, LLC.
Description: § 205(d) Rate Filing: Fort
Rock Solar IV, LLC SFA Concurrence to
be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5182.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2142–000.
Applicants: Fort Rock Solar I, LLC.
Description: § 205(d) Rate Filing: Fort
Rock Solar I, LLC SFA Concurrence to
be effective 6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5183.
Comments Due: 5 p.m. ET 7/14/20.
Docket Numbers: ER20–2143–000.
Applicants: RE Mustang Two Barbaro
LLC.
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
Description: § 205(d) Rate Filing: RE
Mustang Two Barbaro, LLC Certificate
of Concurrence with SFA to be effective
6/24/2020.
Filed Date: 6/23/20.
Accession Number: 20200623–5184.
Comments Due: 5 p.m. ET 7/14/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: June 23, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–13907 Filed 6–26–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[RM19–18–000]
Formal Requirements for Filings in
Proceedings Before the Commission;
Notice Regarding Effective Date
On August 27, 2019, the Commission
issued a Final Rule in Docket No.
RM19–18–000 requiring that deliveries
of filings and submissions, other than by
the United States Postal Service, be sent
to an off-site facility 1 for security
screening and processing.2 The Final
Rule indicated that the new regulation
would take effect 60 days after the date
of publication of the Final Rule in the
Federal Register. On October 11, 2019,
the Secretary issued a notice, stating
that the effective date for the Final Rule
was postponed indefinitely to ensure
that the public and the Commission
make an effective transition to utilizing
the off-site facility. This notice hereby
1 Health and Human Services, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
2 Formal Requirements for Filings in Proceedings
Before the Commission, 168 FERC ¶ 61,120 (2019)
(Final Rule).
E:\FR\FM\29JNN1.SGM
29JNN1
Federal Register / Vol. 85, No. 125 / Monday, June 29, 2020 / Notices
announces that the Final Rule will
become effective on July 1, 2020.
Dated: June 23, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–13917 Filed 6–26–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15032–000]
jbell on DSKJLSW7X2PROD with NOTICES
ECOsponsible, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On May 6, 2020, ECOsponsible, LLC,
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of hydropower at
the existing Springville Dam located on
Cattaraugus Creek in the town of
Concord in Erie County, New York. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed Springville Dam Hydro
Project would redevelop an abandoned
project and would consist of the
following: (1) An existing 338-foot-long
and 40-foot-high concrete gravity dam
with a 182-foot-long spillway; (2) an
existing impoundment; (3) an existing
powerhouse to be rebuilt and to include
two new identical turbine-generator
units with an installed capacity of 500
kilowatts each; (4) a new 4.8- to 13.2kilovolt, 500-foot-long transmission line
extending from the powerhouse to a grid
interconnection point; and (5)
appurtenant facilities. The proposed
project would have an annual
generation of 6.5 gigawatt-hours.
Applicant Contact: Dennis Ryan,
ECOsponsible, LLC, P.O. Box 114, West
Falls, NY 14170; phone: (716) 222–2188.
FERC Contact: Monir Chowdhury;
phone: (202) 502–6736.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
VerDate Sep<11>2014
20:25 Jun 26, 2020
Jkt 250001
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–15032) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: June 23, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–13916 Filed 6–26–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER20–1703–000]
Capital Energy PA LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced Capital Energy PA
LLC’s application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
38885
assumptions of liability, is July 13,
2020.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
may mail similar pleadings to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426. Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Dated: June 23, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–13909 Filed 6–26–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER20–2123–000]
Hardin Solar Energy LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Hardin
E:\FR\FM\29JNN1.SGM
29JNN1
Agencies
[Federal Register Volume 85, Number 125 (Monday, June 29, 2020)]
[Notices]
[Pages 38884-38885]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-13917]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[RM19-18-000]
Formal Requirements for Filings in Proceedings Before the
Commission; Notice Regarding Effective Date
On August 27, 2019, the Commission issued a Final Rule in Docket
No. RM19-18-000 requiring that deliveries of filings and submissions,
other than by the United States Postal Service, be sent to an off-site
facility \1\ for security screening and processing.\2\ The Final Rule
indicated that the new regulation would take effect 60 days after the
date of publication of the Final Rule in the Federal Register. On
October 11, 2019, the Secretary issued a notice, stating that the
effective date for the Final Rule was postponed indefinitely to ensure
that the public and the Commission make an effective transition to
utilizing the off-site facility. This notice hereby
[[Page 38885]]
announces that the Final Rule will become effective on July 1, 2020.
---------------------------------------------------------------------------
\1\ Health and Human Services, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
\2\ Formal Requirements for Filings in Proceedings Before the
Commission, 168 FERC ] 61,120 (2019) (Final Rule).
Dated: June 23, 2020.
Kimberly D. Bose,
Secretary.