National Fuel Gas Supply Corporation; Notice of Request for Extension of Time, 34619 [2020-12234]
Download as PDF
Federal Register / Vol. 85, No. 109 / Friday, June 5, 2020 / Notices
Dated: June 1, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–12222 Filed 6–4–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–220–000]
lotter on DSK9F5VC42PROD with NOTICES
National Fuel Gas Supply Corporation;
Notice of Request for Extension of
Time
Take notice that on May 20, 2020,
National Fuel Gas Supply Corporation
(National) requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of
time, until November 1, 2020, to
construct and place into service
Brockway Modernization Project
(Project) located in Jefferson and Elk
Counties, Pennsylvania authorized on
July 3, 2019. The Project will enable
replacement of approximately 9.7 miles
of 12-inch-diameter pipeline and certain
related facilities.
National was initially required to
construct the facilities and place them
into service by July 5, 2020. National
now requests a four-month extension of
this deadline through November 1,
2020. National states that due to delays
in receiving the required permits,
National was unable to begin
construction until March 1, 2020.
Accordingly, National proposes a new
construction schedule, deferring the
projected in-service date for the
facilities to no later than November 1,
2020.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on National’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).1
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
1 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC 61,144, at P 39 (2020).
VerDate Sep<11>2014
18:21 Jun 04, 2020
Jkt 250001
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,2 the Commission will aim to
issue an order acting on the request
within 45 days.3 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.4 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.5 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.6 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, The Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and three
copies of the protest or intervention to
2 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
3 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
4 Id. at P 40.
5 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
6 Algonquin Gas Transmission, LLC, 170 FERC
61,144, at P 40 (2020).
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
34619
the Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on June 12, 2020.
Dated: June 1, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–12234 Filed 6–4–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–218–000]
Equitrans, L.P.; Notice of Request for
Extension of Time
Take notice that on May 22, 2020,
Equitrans, L.P. (Equitrans) requested
that the Federal Energy Regulatory
Commission (Commission) grant an
extension of time, until March 31, 2021,
to construct and place into service its
TP–4555 Bare Pipe Replacement Project
(Project) located in Westmoreland
County, Pennsylvania. authorized on
July 3, 2019. The Project will enable
abandonment of approximately 3.85
miles of 20-inch-diameter pipeline on
the TP–4555 pipeline, replacing it with
a newly constructed approximately 3.92
miles of 20-inch-diameter pipeline.
Equitrans was initially required to
construct the facilities and place them
into service by July 3, 2020. Equitrans
now requests a nine-month extension of
this deadline through March 31, 2021.
Equitrans states that due to delays in
receiving the required Pennsylvania
Department of Environmental Protection
permits, Equitrans was unable to begin
construction until May 12, 2020.
Accordingly, Equitrans proposes a new
construction schedule, deferring the
projected in-service date for the
facilities to no later than March 31,
2021.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Equitrans request may do
so. No reply comments or answers will
be considered If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
E:\FR\FM\05JNN1.SGM
05JNN1
Agencies
[Federal Register Volume 85, Number 109 (Friday, June 5, 2020)]
[Notices]
[Page 34619]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-12234]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-220-000]
National Fuel Gas Supply Corporation; Notice of Request for
Extension of Time
Take notice that on May 20, 2020, National Fuel Gas Supply
Corporation (National) requested that the Federal Energy Regulatory
Commission (Commission) grant an extension of time, until November 1,
2020, to construct and place into service Brockway Modernization
Project (Project) located in Jefferson and Elk Counties, Pennsylvania
authorized on July 3, 2019. The Project will enable replacement of
approximately 9.7 miles of 12-inch-diameter pipeline and certain
related facilities.
National was initially required to construct the facilities and
place them into service by July 5, 2020. National now requests a four-
month extension of this deadline through November 1, 2020. National
states that due to delays in receiving the required permits, National
was unable to begin construction until March 1, 2020. Accordingly,
National proposes a new construction schedule, deferring the projected
in-service date for the facilities to no later than November 1, 2020.
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on National's request
for an extension of time may do so. No reply comments or answers will
be considered. If you wish to obtain legal status by becoming a party
to the proceedings for this request, you should, on or before the
comment date stated below, file a motion to intervene in accordance
with the requirements of the Commission's Rules of Practice and
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10).\1\
---------------------------------------------------------------------------
\1\ Only motions to intervene from entities that were party to
the underlying proceeding will be accepted. Algonquin Gas
Transmission, LLC, 170 FERC 61,144, at P 39 (2020).
---------------------------------------------------------------------------
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\2\ the
Commission will aim to issue an order acting on the request within 45
days.\3\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\4\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\5\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\6\ The OEP Director, or
his or her designee, will act on all of those extension requests that
are uncontested.
---------------------------------------------------------------------------
\2\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
\3\ Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40
(2020).
\4\ Id. at P 40.
\5\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\6\ Algonquin Gas Transmission, LLC, 170 FERC 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, The Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the eLibrary link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to Commission's Public Reference
Room, due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original and three copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern Time on June 12, 2020.
Dated: June 1, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-12234 Filed 6-4-20; 8:45 am]
BILLING CODE 6717-01-P