Warrior Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 33658-33659 [2020-11866]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES 33658 Federal Register / Vol. 85, No. 106 / Tuesday, June 2, 2020 / Notices to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. Comment Date: 5:00 p.m. Eastern Standard Time on June 17, 2020. VerDate Sep<11>2014 20:46 Jun 01, 2020 Jkt 250001 Dated: May 27, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–11867 Filed 6–1–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2309–032] Jersey Central Power & Light Company, PSEG Fossil, LLC, Yards Creek Energy, LLC; Notice of Application for Partial Transfer of License and Soliciting Comments, Motions to Intervene, and Protests On May 6, 2020, Jersey Central Power & Light Company (JCP&L or transferor) and PSEG Fossil, LLC (PSEG) current co-licensees, and Yards Creek Energy, LLC (YCE or transferee) filed a joint application for a partial transfer of the license for the Yards Creek Pumped Storage Hydroelectric Project No. 2309. The project is located on Yards Creek in Warren County, New Jersey. The applicants seek Commission approval for a partial transfer of the license for the project to remove JCP&L as a co-licensee and to add YCE as colicensee. Applicants Contact: For transferor: Anne M. Rericha, Attorney, FirstEnergy Service Company, 76 S. Maine Street, Akron, Ohio 44308, Phone: (330) 374– 6550, Email: arericha@ firstenergycorp.com and Morgan E. Parke, Associate General Counsel, FirstEnergy Service Company, 76 S. Maine Street, Akron, Ohio 44308, Phone: (330) 384–4595, Email: mparke@ firstenergycorp.com For co-licensee: Cara J. Lewis, Managing Counsel—Federal Regulatory, PSEG Services Corporation, 80 Park Plaza—T5G, Newark, New Jersey 07102, Phone: (973) 430–8836, Email: cara.lewis@pseg.com For transferee: Kimberly Ognisty, Winston & Strawn LLC, 1901 L Street NW, Washington, DC 20036, Phone: (202) 282–5217, Email: kognisty@ winston.com FERC Contact: Anumzziatta Purchiaroni, (202) 502–6191, Anumzziatta.purchiaroni@ferc.gov. Deadline for filing comments, motions to intervene, and protests: 30 days from the date that the Commission issues this notice. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docsfiling/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–2309–032. Dated: May 27, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–11868 Filed 6–1–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 15022–000] Warrior Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On January 28, 2020, Warrior Hydro, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of a hydropower project to be located at the U.S. Army Corps of Engineers’ (Corps) William Bacon Oliver Lock and Dam on the Black Warrior River near the towns of Tuscaloosa and Northport in Tuscaloosa County, Alabama. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) An 80-foot-long, 140foot-wide intake channel; (2) four 10foot-diameter, 60-foot-long steel siphon penstocks, near the south abutment of the Corps’ dam; (3) a 80-foot-long, 40foot-wide powerhouse containing four generating units with a total capacity of 9.2 megawatts; (4) a 100-foot-long, 140foot-wide tailrace; and (5) a 0.9-milelong, 34.5kV transmission line. The proposed project would have an E:\FR\FM\02JNN1.SGM 02JNN1 Federal Register / Vol. 85, No. 106 / Tuesday, June 2, 2020 / Notices estimated average annual generation of 59,000 megawatt-hours, and operate as directed by the Corps. Applicant Contact: Mr. Jeremy Wells, Wells Engineering, LLC, 5962 Zebulon Rd #144, Macon, GA 35565; (478) 238– 3054 FERC Contact: Michael Spencer; michael.spencer@ferc.gov; (202) 502– 6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: Sixty (60) days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–15022–000. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s website at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–15022) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: May 27, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–11866 Filed 6–1–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY khammond on DSKJM1Z7X2PROD with NOTICES Federal Energy Regulatory Commission [Docket No. ER20–1879–000] Oliver Wind I, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Oliver VerDate Sep<11>2014 20:46 Jun 01, 2020 Jkt 250001 Wind I, LLC’s application for marketbased rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is June 16, 2020. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 33659 Dated: May 27, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–11836 Filed 6–1–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–1769–000] Chicot Solar, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Chicot Solar, LLC’s application for marketbased rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is June 16, 2020. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all E:\FR\FM\02JNN1.SGM 02JNN1

Agencies

[Federal Register Volume 85, Number 106 (Tuesday, June 2, 2020)]
[Notices]
[Pages 33658-33659]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-11866]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15022-000]


Warrior Hydro, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On January 28, 2020, Warrior Hydro, LLC filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of a hydropower project to be 
located at the U.S. Army Corps of Engineers' (Corps) William Bacon 
Oliver Lock and Dam on the Black Warrior River near the towns of 
Tuscaloosa and Northport in Tuscaloosa County, Alabama. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would consist of the following: (1) An 80-
foot-long, 140-foot-wide intake channel; (2) four 10-foot-diameter, 60-
foot-long steel siphon penstocks, near the south abutment of the Corps' 
dam; (3) a 80-foot-long, 40-foot-wide powerhouse containing four 
generating units with a total capacity of 9.2 megawatts; (4) a 100-
foot-long, 140-foot-wide tailrace; and (5) a 0.9-mile-long, 34.5kV 
transmission line. The proposed project would have an

[[Page 33659]]

estimated average annual generation of 59,000 megawatt-hours, and 
operate as directed by the Corps.
    Applicant Contact: Mr. Jeremy Wells, Wells Engineering, LLC, 5962 
Zebulon Rd #144, Macon, GA 35565; (478) 238-3054
    FERC Contact: Michael Spencer; [email protected]; (202) 502-
6093.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: Sixty (60) days from the issuance of this 
notice. Competing applications and notices of intent must meet the 
requirements of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-15022-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-15022) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: May 27, 2020.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2020-11866 Filed 6-1-20; 8:45 am]
 BILLING CODE 6717-01-P