Combined Notice of Filings, 33150 [2020-11687]
Download as PDF
33150
Federal Register / Vol. 85, No. 105 / Monday, June 1, 2020 / Notices
Accession Number: 20200526–5177.
Comments Due: 5 p.m. ET 6/16/20.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES20–23–000.
Applicants: Mississippi Power
Company.
Description: Amendment to April 14,
2020 Application Under Section 204 of
the Federal Power Act for Authorization
to Issue Securities of Mississippi Power
Company.
Filed Date: 5/22/20.
Accession Number: 20200522–5292
Comments Due: 5 p.m. ET 5/27/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 26, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Description: § 4(d) Rate Filing:
Negotiated Rate—Manchester Street
K511085 to be effective 6/1/2020.
Filed Date: 5/21/20.
Accession Number: 20200521–5095.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: RP20–883–000.
Applicants: White River Hub, LLC.
Description: Annual Fuel Gas
Reimbursement Percentage Report of
White River Hub, LLC under RP20–883.
Filed Date: 5/22/20.
Accession Number: 20200522–5131.
Comments Due: 5 p.m. ET 6/3/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 26, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–11687 Filed 5–29–20; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2020–11686 Filed 5–29–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15029–000]
Federal Energy Regulatory
Commission
jbell on DSKJLSW7X2PROD with NOTICES
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP20–871–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: § 4(d) Rate Filing: Update
Filing—Removal of Expired Agreements
to be effective 6/14/2020.
Filed Date: 5/15/20.
Accession Number: 20200515–5000.
Comments Due: 5 p.m. ET 5/28/20.
Docket Numbers: RP20–882–000.
Applicants: Algonquin Gas
Transmission, LLC.
VerDate Sep<11>2014
19:40 May 29, 2020
Jkt 250001
SV Hydro, LLC; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On April 23, 2020, SV Hydro, LLC,
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study
the feasibility of the Itasca County
Pumped Storage Project (Itasca County
Project or project) to be located near the
City of Marble, Itasca County,
Minnesota. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project is a closed loop
pumped storage project and would
consist of the following: (1) A 50-foothigh, 120-acre-area circular upper
reservoir constructed as a rockfill
embankment with a total storage
capacity of approximately 4,500 acrefeet at a maximum operating elevation
of 1,455 feet mean sea level (msl); (2) an
18-foot-diameter upper intake; (3) a
2,800-foot-long, 16-foot-diameter
vertical penstock excavated in granitic
bedrock and lined with steel extending
between the upper intake and the
pump/turbines below; (4) a 5,400-foot to
4,200-foot-circular underground lower
reservoir excavated in granitic bedrock,
located 2,500 feet below the ground
surface elevation of 1,410 msl with a
usable storage capacity approximately
the same as the upper reservoir and
operational water elevations between
minus 1,012.5 feet msl and minus 1,055
feet msl; (5) a 200-foot-long, 70-footwide, 130-foot-high powerhouse located
250 feet below the lower reservoir
containing two vertical Francis
reversible pump/turbine-motor/
generator units rated for 333 megawatts
each; (6) a 240-foot-long, 50-foot-wide,
40-foot-high underground transformer
gallery; (7) a 200-foot-square above
ground substation; (8) a 200 to 500-footlong, 230 kilovolts (kV) transmission
line extending from the substation to an
existing 230 kV transmission line
owned by others; and (9) appurtenant
facilities. There would be no federal
land within the proposed project
boundary. The estimated annual
generation of the Itasca County Project
would be 1,500 gigawatt-hours.
Applicant Contact: Mr. Douglas
Spaulding, P.E., Nelson Energy, 8441
Wayzata Blvd., Suite 101 Golden Valley,
MN 55426; phone: (952) 544–8133.
FERC Contact: Sergiu Serban; phone:
(202) 502–6211.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
E:\FR\FM\01JNN1.SGM
01JNN1
Agencies
[Federal Register Volume 85, Number 105 (Monday, June 1, 2020)]
[Notices]
[Page 33150]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-11687]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP20-871-000.
Applicants: Natural Gas Pipeline Company of America.
Description: Sec. 4(d) Rate Filing: Update Filing--Removal of
Expired Agreements to be effective 6/14/2020.
Filed Date: 5/15/20.
Accession Number: 20200515-5000.
Comments Due: 5 p.m. ET 5/28/20.
Docket Numbers: RP20-882-000.
Applicants: Algonquin Gas Transmission, LLC.
Description: Sec. 4(d) Rate Filing: Negotiated Rate--Manchester
Street K511085 to be effective 6/1/2020.
Filed Date: 5/21/20.
Accession Number: 20200521-5095.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: RP20-883-000.
Applicants: White River Hub, LLC.
Description: Annual Fuel Gas Reimbursement Percentage Report of
White River Hub, LLC under RP20-883.
Filed Date: 5/22/20.
Accession Number: 20200522-5131.
Comments Due: 5 p.m. ET 6/3/20.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified date(s). Protests may be considered,
but intervention is necessary to become a party to the proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: May 26, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-11687 Filed 5-29-20; 8:45 am]
BILLING CODE 6717-01-P