Aspinook Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 30694-30695 [2020-10843]
Download as PDF
30694
Federal Register / Vol. 85, No. 98 / Wednesday, May 20, 2020 / Notices
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 9, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Lower Great Falls Hydroelectric Project
consists of: (1) A 297-foot-long, 32-foothigh stone masonry and concrete dam
that includes the following sections: (a)
A 176-foot-long spillway section with a
crest elevation of 102.37 feet National
Geodetic Vertical Datum of 1929
(NGVD) and 4-foot-high flashboards at
an elevation of 106.37 feet NGVD at the
top of the flashboards; (b) a 50-foot-long
left abutment section; and (c) a 71-footlong right abutment section; (2) a 32acre impoundment with a normal
elevation of 106.37 feet NGVD; (3) a
40.5-foot-wide, 20-foot-high intake
structure with four 5-foot-wide, 10.5foot-high steel frame gates and a
trashrack with 2-inch bar spacing; (4)
two steel penstocks that include: (a) An
8.5-foot-diameter, 120-foot-long left
penstock that bifurcates into a 5.3-footdiameter, 85-foot-long section and a 7.6foot-diameter, 85-foot-long section; and
(b) an 8.5-foot-diameter, 140-foot-long
right penstock that bifurcates into a 7foot-diameter, 85-foot-long section and a
7.6-foot-diameter, 85-foot-long section;
(5) a 46-foot-long, 30-foot-wide concrete
and brick powerhouse with four Francis
turbine-generator units with a total
capacity of 1.28 megawatt (MW); (6) a
55-foot-long, 30-foot-wide tailrace; (7) a
260-foot-long underground transmission
line that delivers power to a 4.16kilovolt distribution line; and (8)
appurtenant facilities. The project
creates a 250-foot-long bypassed reach
of the Salmon Falls River between the
dam and the downstream end of the
tailrace.
The project operates as a run-of-river
(ROR) facility with no storage or flood
control capacity. The project
impoundment is maintained at a
flashboard crest elevation of 106.37 feet
NGVD. The current license requires the
project to maintain a continuous
minimum flow of 6.05 cubic feet per
second (cfs) or inflow, whichever is less,
to the bypassed reach for the purpose of
protecting and enhancing aquatic
VerDate Sep<11>2014
17:51 May 19, 2020
Jkt 250001
resources in the Salmon Falls River. The
average annual generation production of
the project was 3,916,825 kilowatt-hours
from 2005 through 2018.
The applicant proposes to: (1)
Continue operating the project in a ROR
mode; (2) provide a minimum flow of 30
cfs or inflow, whichever is less, to the
bypassed reach; (3) install an eel ramp
for upstream eel passage at the project;
(4) implement targeted nighttime
turbine shutdowns to protect eels
during downstream passage; (5) install a
downstream fish passage structure for
eels and other fish species.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–4451).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)—
July 2020
Request Additional Information—July
2020
Issue Acceptance Letter—October 2020
Issue Scoping Document 1 for
comments—November 2020
Request Additional Information (if
necessary)—January 2021
Issue Scoping Document 2—February
2021
Issue Notice of Ready for Environmental
Analysis—February 2021
Commission issues Environmental
Assessment—August 2021
Final amendments to the application
must be filed with the Commission no
PO 00000
Frm 00013
Fmt 4703
Sfmt 4703
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–10842 Filed 5–19–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3472–024]
Aspinook Hydro, LLC; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–3472–024.
c. Date filed: April 30, 2020.
d. Applicant: Aspinook Hydro, LLC.
e. Name of Project: Wyre Wynd
Hydroelectric Project.
f. Location: On the Quinebaug River
in New London and Windham Counties,
Connecticut. No federal lands are
occupied by the project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mark
Boumansour, Chief Operating Officer,
Gravity Renewables, Inc., 1401 Walnut
Street, Boulder, CO 80302; Phone at
(303) 440–3378, or email at mark@
gravityrenewables.com.
i. FERC Contact: Dr. Nicholas Palso at
(202) 502–8854, or nicholas.palso@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
E:\FR\FM\20MYN1.SGM
20MYN1
Federal Register / Vol. 85, No. 98 / Wednesday, May 20, 2020 / Notices
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 70 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 9, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Wyre Wynd Hydroelectric Project
consists of: (1) A concrete-encased
masonry dam that includes the
following sections: (a) A 473-foot-long,
19-foot-high spillway section with a
crest elevation of 95.3 feet National
Geodetic Vertical Datum of 1929
(NGVD) and 2-foot-high flashboards at
an elevation of 97.3 feet NGVD at the
top of the flashboards; (b) a left
abutment section; and (c) a right
abutment section; (2) a 333-acre
impoundment with a normal elevation
of 97.3 feet NGVD; (3) a 100-foot-long,
25-foot-wide headgate structure with
five 10.5-foot-wide, 11.5-foot-high sluice
gates; (4) a 170-foot-long, 50-foot-wide
forebay with five 13-foot-high, 9.5-footwide flood gates, a 110-foot-long
overflow weir, and two 13-foot-high,
9.5-foot-wide low-level outlet gates; (5)
a powerhouse intake structure located at
the downstream end of the forebay that
includes: (a) A 38.2-foot-long, 20- to
21.3- foot-wide trashrack with 2.6-inch
clear-bar spacing; (b) a 16-foot-long, 12foot-diameter steel penstock that
provides flow to a 2.7-megawatt (MW)
S-type Kaplan turbine-generator unit
located inside of a 75-foot-long, 30-footwide concrete powerhouse; and (c) a
450-foot-long, 60-foot-wide tailrace; (6)
a minimum flow unit intake structure
that branches off of the right side of
forebay approximately 35 feet
downstream of the headgate structure,
and that includes: (a) A 20-foot-long, 9foot-wide trashrack with 1.5-inch clearbar spacing; (b) a 40-foot-long, 4-footdiameter steel penstock that provides
flow to a 0.08-megawatt (MW) propellertype turbine-generator unit located
outside; and (c) a 10-foot-long, 30-foot-
VerDate Sep<11>2014
17:51 May 19, 2020
Jkt 250001
wide tailrace; (7) two generator leads
connecting the turbine-generator units
to the local electric distribution system;
and (8) appurtenant facilities. The
project creates an approximately 400foot-long bypassed reach of the
Quinebaug River.
The current license requires an
instantaneous minimum flow of 120
cubic feet per second (cfs), or the
inflow, whichever is less, downstream
of the dam to protect fish and wildlife
resources in the Quinebaug River.
The project had an average annual
generation production of approximately
11,000,000 kilowatt-hours from 2003
through 2015.
Aspinook proposes to: (1) Operate the
project in run-of-river mode; (2) provide
an 84-cfs minimum flow to the bypassed
reach; and (3) provide upstream and
downstream fish passage.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–3472).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)—
July 2020
Request Additional Information—July
2020
Issue Acceptance Letter—October 2020
Issue Scoping Document 1 for
comments—November 2020
Request Additional Information (if
necessary)—January 2021
Issue Scoping Document 2—February
2021
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
30695
Issue Notice of Ready for Environmental
Analysis—February 2021
Commission issues Environmental
Assessment—August 2021
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: May 14, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–10843 Filed 5–19–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP20–844–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: § 4(d) Rate Filing:
Amendment to a Negotiated Rate
Agreement-Corpus Christi Liquefaction,
LLC to be effective 5/1/2020.
Filed Date: 5/1/20.
Accession Number: 20200501–5001.
Comments Due: 5 p.m. ET 5/18/20.
Docket Number: PR20–57–000.
Applicants: Louisville Gas and
Electric Company.
Description: Tariff filing per
284.123(b),(e)/: Revised Statement of
Operating Conditions eff 5–1–2020 to be
effective 5/1/2020.
Filed Date: 5/11/2020.
Accession Number: 202005115056.
Comments/Protests Due: 5 p.m. ET 6/
1/2020.
Docket Number: PR20–58–000.
Applicants: Black Hills/Kansas Gas
Utility Company, LLC.
Description: Tariff filing per
284.123(b),(e)/: Black Hills/Kansas Gas
Utility Company LLC SOC Filing CP19–
483 to be effective 8/1/2019.
Filed Date: 5/11/2020.
Accession Number: 202005115080.
Comments/Protests Due: 5 p.m. ET 6/
1/2020.
Docket Number: PR20–59–000.
Applicants: Columbia Gas of
Maryland, Inc.
Description: Tariff filing per
284.123(b),(e)/: CMD Rates effective
May 1 2020 to be effective 5/1/2020.
Filed Date: 5/13/2020.
Accession Number: 202005135043.
Comments/Protests Due: 5 p.m. ET 6/
3/2020.
E:\FR\FM\20MYN1.SGM
20MYN1
Agencies
[Federal Register Volume 85, Number 98 (Wednesday, May 20, 2020)]
[Notices]
[Pages 30694-30695]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-10843]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3472-024]
Aspinook Hydro, LLC; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: P-3472-024.
c. Date filed: April 30, 2020.
d. Applicant: Aspinook Hydro, LLC.
e. Name of Project: Wyre Wynd Hydroelectric Project.
f. Location: On the Quinebaug River in New London and Windham
Counties, Connecticut. No federal lands are occupied by the project
works or located within the project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mark Boumansour, Chief Operating Officer,
Gravity Renewables, Inc., 1401 Walnut Street, Boulder, CO 80302; Phone
at (303) 440-3378, or email at [email protected].
i. FERC Contact: Dr. Nicholas Palso at (202) 502-8854, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional
[[Page 30695]]
scientific study should be conducted in order to form an adequate
factual basis for a complete analysis of the application on its merit,
the resource agency, Indian Tribe, or person must file a request for a
study with the Commission not later than 70 days from the date of
filing of the application, and serve a copy of the request on the
applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: July 9, 2020.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY).
m. The application is not ready for environmental analysis at this
time.
n. Project Description: The existing Wyre Wynd Hydroelectric
Project consists of: (1) A concrete-encased masonry dam that includes
the following sections: (a) A 473-foot-long, 19-foot-high spillway
section with a crest elevation of 95.3 feet National Geodetic Vertical
Datum of 1929 (NGVD) and 2-foot-high flashboards at an elevation of
97.3 feet NGVD at the top of the flashboards; (b) a left abutment
section; and (c) a right abutment section; (2) a 333-acre impoundment
with a normal elevation of 97.3 feet NGVD; (3) a 100-foot-long, 25-
foot-wide headgate structure with five 10.5-foot-wide, 11.5-foot-high
sluice gates; (4) a 170-foot-long, 50-foot-wide forebay with five 13-
foot-high, 9.5-foot-wide flood gates, a 110-foot-long overflow weir,
and two 13-foot-high, 9.5-foot-wide low-level outlet gates; (5) a
powerhouse intake structure located at the downstream end of the
forebay that includes: (a) A 38.2-foot-long, 20- to 21.3- foot-wide
trashrack with 2.6-inch clear-bar spacing; (b) a 16-foot-long, 12-foot-
diameter steel penstock that provides flow to a 2.7-megawatt (MW) S-
type Kaplan turbine-generator unit located inside of a 75-foot-long,
30-foot-wide concrete powerhouse; and (c) a 450-foot-long, 60-foot-wide
tailrace; (6) a minimum flow unit intake structure that branches off of
the right side of forebay approximately 35 feet downstream of the
headgate structure, and that includes: (a) A 20-foot-long, 9-foot-wide
trashrack with 1.5-inch clear-bar spacing; (b) a 40-foot-long, 4-foot-
diameter steel penstock that provides flow to a 0.08-megawatt (MW)
propeller-type turbine-generator unit located outside; and (c) a 10-
foot-long, 30-foot-wide tailrace; (7) two generator leads connecting
the turbine-generator units to the local electric distribution system;
and (8) appurtenant facilities. The project creates an approximately
400-foot-long bypassed reach of the Quinebaug River.
The current license requires an instantaneous minimum flow of 120
cubic feet per second (cfs), or the inflow, whichever is less,
downstream of the dam to protect fish and wildlife resources in the
Quinebaug River.
The project had an average annual generation production of
approximately 11,000,000 kilowatt-hours from 2003 through 2015.
Aspinook proposes to: (1) Operate the project in run-of-river mode;
(2) provide an 84-cfs minimum flow to the bypassed reach; and (3)
provide upstream and downstream fish passage.
o. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov)
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
3472). At this time, the Commission has suspended access to the
Commission's Public Reference Room due to the proclamation declaring a
National Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact FERC
at [email protected] or call toll-free, (866) 208-3676 or
(202) 502-8659 (TTY).
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)--July 2020
Request Additional Information--July 2020
Issue Acceptance Letter--October 2020
Issue Scoping Document 1 for comments--November 2020
Request Additional Information (if necessary)--January 2021
Issue Scoping Document 2--February 2021
Issue Notice of Ready for Environmental Analysis--February 2021
Commission issues Environmental Assessment--August 2021
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: May 14, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-10843 Filed 5-19-20; 8:45 am]
BILLING CODE 6717-01-P