Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC20–66–000.
Applicants: Northern States Power
Company, a Minnesota corporation,
Crowned Ridge Wind II, LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Northern
States Power Company, a Minnesota
corporation, et al.
Filed Date: 5/8/20.
Accession Number: 20200508–5330.
Comments Due: 5 p.m. ET 6/22/20.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG20–155–000.
Applicants: High Majestic Wind I,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of High Majestic Wind
I, LLC.
Filed Date: 5/12/20.
Accession Number: 20200512–5085.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: EG20–156–000.
Applicants: Soldier Creek Wind, LLC.
Description: Notice Self-Certification
of Exempt Wholesale Generator Status
of Soldier Creek Wind, LLC.
Filed Date: 5/12/20.
Accession Number: 20200512–5087.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: EG20–157–000.
Applicants: El Campo Wind, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of El Campo Wind,
LLC.
Filed Date: 5/12/20.
Accession Number: 20200512–5099.
Comments Due: 5 p.m. ET 6/2/20.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–539–001.
Applicants: East Fork Wind Project,
LLC.
Description: Notice of Change in
Status of East Fork Wind Project, LLC.
Filed Date: 5/11/20.
Accession Number: 20200511–5203.
Comments Due: 5 p.m. ET 6/1/20.
Docket Numbers: ER20–936–000.
Applicants: Entergy Arkansas, LLC.
Description: Response of Entergy
Services, LLC, on behalf of Entergy
Arkansas LLC, to the April 10, 2020
VerDate Sep<11>2014
18:03 May 15, 2020
Jkt 250001
Deficiency Letter for additional
information.
Filed Date: 5/11/20.
Accession Number: 20200511–5193.
Comments Due: 5 p.m. ET 6/1/20.
Docket Numbers: ER20–1525–000.
Applicants: Eastern Landfill Gas, LLC.
Description: Clarifications to April 13,
2020 Amendment to April 8, 2020
Waiver Request of Eastern Landfill Gas,
LLC.
Filed Date: 5/11/20.
Accession Number: 20200511–5205.
Comments Due: 5 p.m. ET 5/18/20.
Docket Numbers: ER20–1801–001.
Applicants: Techren Solar V LLC.
Description: Tariff Amendment:
Amendment to MBR Application to be
effective 10/1/2020.
Filed Date: 5/12/20.
Accession Number: 20200512–5000.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: ER20–1805–000.
Applicants: Ohio Edison Company,
The Cleveland Electric Illuminating
Comp, The Toledo Edison Company.
Description: Request for Waiver, et al.
of the FirstEnergy Ohio Utilities.
Filed Date: 5/11/20.
Accession Number: 20200511–5190.
Comments Due: 5 p.m. ET 5/18/20.
Docket Numbers: ER20–1806–000.
Applicants: Catalyst Old River
Hydroelectric Limited.
Description: Baseline eTariff Filing:
Application For Market Based Rate
Authority to be effective 7/12/2020.
Filed Date: 5/12/20.
Accession Number: 20200512–5044.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: ER20–1807–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: GIA
and DSA Dutch Wind, LLC—Dutch
Energy, SA No. 1104, 1105 to be
effective 4/13/2020.
Filed Date: 5/12/20.
Accession Number: 20200512–5098.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: ER20–1808–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: 3670
West Texas A&M University and SPS
Affected Systems FCA to be effective
5/4/2020.
Filed Date: 5/12/20.
Accession Number: 20200512–5101.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: ER20–1809–000.
Applicants: PJM Interconnection,
L.L.C., Potomac Electric Power
Company.
Description: § 205(d) Rate Filing:
PEPCO submits Interconnection
Agreement, SA No. 5610 with SMECO
to be effective 4/23/2020.
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
Filed Date: 5/12/20.
Accession Number: 20200512–5114.
Comments Due: 5 p.m. ET 6/2/20.
Docket Numbers: ER20–1810–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2020–05–12_SA 3180 Dunns Bridge
Solar-NIPSCO 2nd Rev GIA (J643 J847)
to be effective 5/5/2020.
Filed Date: 5/12/20.
Accession Number: 20200512–5134.
Comments Due: 5 p.m. ET 6/2/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 12, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–10575 Filed 5–15–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1933–113]
Southern California Edison Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Non-Capacity
Amendment of License.
b. Project No.: 1933–113.
c. Date Filed: April 13, 2020.
d. Applicant: Southern California
Edison Company.
e. Name of Project: Santa Ana River
1 and 3 Hydroelectric Project.
f. Location: The project is located
primarily on the Santa Ana River in San
Bernardino County, California. The
E:\FR\FM\18MYN1.SGM
18MYN1
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 96 / Monday, May 18, 2020 / Notices
project occupies federal lands
administered by the U.S. Forest Service
within the San Bernardino National
Forest.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Matthew
Woodhall, Southern California Edison
Company, 1515 Walnut Grove Avenue,
Rosemead, CA 91770; telephone (626)
302–9596 and email
matthew.woodhall@sce.com.
i. FERC Contact: Linda Stewart, (202)
502–8184, linda.stewart@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance date of this
notice by the Commission.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–1933–113. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, it must also
serve a copy of the document on that
resource agency.
k. Description of Request: Southern
California Edison Company (licensee)
proposes to remove from the project
license the Breakneck Creek diversion,
which is one of three diversions
included as part of the Santa Ana River
1 (SAR 1) development. Located on
private lands owned by the licensee, the
VerDate Sep<11>2014
18:03 May 15, 2020
Jkt 250001
Breakneck Creek diversion system
includes a diversion dam, upstream
intake gates to the settling basin, a
walkway on the dam crest, a buried
trash rack and intake, and a buried
outlet tunnel. Since the diversion has
become inoperable as the settling basin
has filled with sediment, the licensee
proposes to leave in place the
underground or partially buried
features, including the diversion dam,
and to remove the aboveground
ancillary features.
l. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, and
.214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
deadline date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person commenting,
protesting, or intervening; and (4)
otherwise comply with the requirements
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
29709
of 18 CFR 385.2001 through 385.2005.
All comments, motions to intervene, or
protests must set forth their evidentiary
basis. Any filing made by an intervenor
must be accompanied by proof of
service on all persons listed in the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 385.2010.
Dated: May 12, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–10578 Filed 5–15–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AC20–106–000]
Florida Power & Light Company, Gulf
Power Company; Notice of Petition for
Waiver
Take notice that on May 1, 2020,
Florida Power & Light Company (FPL)
and Gulf Power Company (Gulf Power)
filed a petition for a limited waiver of
Part 101 and sections 141.1 and 141.400
of the Commission’s regulations to
allow FPL to (1) maintain separate
books and records under the Uniform
System of Accounts; and (2) make
separate FERC Form No.1 and 3–Q
submissions for two separate operating
divisions corresponding to the current
FPL and Gulf Power utilities for the
2021 reporting year, following the
proposed legal merger of Gulf Power
into FPL on January 1, 2021, as more
fully explained in the petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene, or protest must serve a
copy of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
E:\FR\FM\18MYN1.SGM
18MYN1
Agencies
[Federal Register Volume 85, Number 96 (Monday, May 18, 2020)]
[Notices]
[Pages 29708-29709]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-10578]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1933-113]
Southern California Edison Company; Notice of Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Non-Capacity Amendment of License.
b. Project No.: 1933-113.
c. Date Filed: April 13, 2020.
d. Applicant: Southern California Edison Company.
e. Name of Project: Santa Ana River 1 and 3 Hydroelectric Project.
f. Location: The project is located primarily on the Santa Ana
River in San Bernardino County, California. The
[[Page 29709]]
project occupies federal lands administered by the U.S. Forest Service
within the San Bernardino National Forest.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Matthew Woodhall, Southern California
Edison Company, 1515 Walnut Grove Avenue, Rosemead, CA 91770; telephone
(626) 302-9596 and email [email protected].
i. FERC Contact: Linda Stewart, (202) 502-8184,
[email protected].
j. Deadline for filing comments, motions to intervene, and protests
is 30 days from the issuance date of this notice by the Commission.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC 20426. Hand delivered submissions
in docketed proceedings should be delivered to Health and Human
Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first
page of any filing should include docket number P-1933-113. Comments
emailed to Commission staff are not considered part of the Commission
record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, it
must also serve a copy of the document on that resource agency.
k. Description of Request: Southern California Edison Company
(licensee) proposes to remove from the project license the Breakneck
Creek diversion, which is one of three diversions included as part of
the Santa Ana River 1 (SAR 1) development. Located on private lands
owned by the licensee, the Breakneck Creek diversion system includes a
diversion dam, upstream intake gates to the settling basin, a walkway
on the dam crest, a buried trash rack and intake, and a buried outlet
tunnel. Since the diversion has become inoperable as the settling basin
has filled with sediment, the licensee proposes to leave in place the
underground or partially buried features, including the diversion dam,
and to remove the aboveground ancillary features.
l. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
and .214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
deadline date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person commenting, protesting, or intervening; and (4)
otherwise comply with the requirements of 18 CFR 385.2001 through
385.2005. All comments, motions to intervene, or protests must set
forth their evidentiary basis. Any filing made by an intervenor must be
accompanied by proof of service on all persons listed in the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 385.2010.
Dated: May 12, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-10578 Filed 5-15-20; 8:45 am]