Erie Boulevard Hydropower, L.P.; Notice of Authorization for Continued Project Operation, 28619 [2020-10258]
Download as PDF
Federal Register / Vol. 85, No. 93 / Wednesday, May 13, 2020 / Notices
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 7, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–10279 Filed 5–12–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2837–000]
jbell on DSKJLSW7X2PROD with NOTICES
Erie Boulevard Hydropower, L.P.;
Notice of Authorization for Continued
Project Operation
On March 29, 2018, Erie Boulevard
Hydropower, L.P., licensee for the
Granby Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Granby Hydroelectric Project is on
the Oswego River in the town of Fulton
in Oswego County, New York.
The license for Project No. 2837 was
issued for a period ending March 31,
2020. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
VerDate Sep<11>2014
19:53 May 12, 2020
Jkt 250001
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2837
is issued to Erie Boulevard Hydropower,
L.P., for a period effective April 1, 2020
through March 31, 2021, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before March 31,
2021, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the Erie Boulevard Hydropower,
L.P., is authorized to continue operation
of the Granby Hydroelectric Project,
until such time as the Commission acts
on its application for a subsequent
license.
Dated: May 7, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–10258 Filed 5–12–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2669–000]
Bear Swamp Power Company, LLC;
Notice of Authorization for Continued
Project Operation
On March 30, 2018, Bear Swamp
Power Company, LLC, licensee for the
Bear Swamp Hydroelectric Project, filed
an Application for a New License
pursuant to the Federal Power Act
(FPA) and the Commission’s regulations
thereunder. The Bear Swamp
Hydroelectric Project is on Deerfield
River, in Berkshire and Franklin
Counties, Massachusetts.
The license for Project No. 2669 was
issued for a period ending March 31,
2020. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
28619
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2669
is issued to Bear Swamp Power
Company, LLC for a period effective
April 1, 2020 through March 31, 2021,
or until the issuance of a new license for
the project or other disposition under
the FPA, whichever comes first. If
issuance of a new license (or other
disposition) does not take place on or
before March 31, 2021, notice is hereby
given that, pursuant to 18 CFR 16.18(c),
an annual license under section 15(a)(1)
of the FPA is renewed automatically
without further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the Bear Swamp Power Company,
LLC, Inc. is authorized to continue
operation of the Bear Swamp
Hydroelectric Project, until such time as
the Commission acts on its application
for a subsequent license.
Dated: May 7, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–10257 Filed 5–12–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Number: PR20–44–001.
Applicants: ONEOK Gas
Transportation, L.L.C.
E:\FR\FM\13MYN1.SGM
13MYN1
Agencies
[Federal Register Volume 85, Number 93 (Wednesday, May 13, 2020)]
[Notices]
[Page 28619]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-10258]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2837-000]
Erie Boulevard Hydropower, L.P.; Notice of Authorization for
Continued Project Operation
On March 29, 2018, Erie Boulevard Hydropower, L.P., licensee for
the Granby Hydroelectric Project, filed an Application for a New
License pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Granby Hydroelectric Project is on the
Oswego River in the town of Fulton in Oswego County, New York.
The license for Project No. 2837 was issued for a period ending
March 31, 2020. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2837 is issued to
Erie Boulevard Hydropower, L.P., for a period effective April 1, 2020
through March 31, 2021, or until the issuance of a new license for the
project or other disposition under the FPA, whichever comes first. If
issuance of a new license (or other disposition) does not take place on
or before March 31, 2021, notice is hereby given that, pursuant to 18
CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the Erie Boulevard Hydropower, L.P., is authorized to
continue operation of the Granby Hydroelectric Project, until such time
as the Commission acts on its application for a subsequent license.
Dated: May 7, 2020.
Kimberly D. Bose,
Secretary.