Green Mountain Power Corporation; Notice of Intent To File License Application, Filing of Pre-Application Document (PAD), Commencement of Pre-Filing Process, and Scoping; Waiving Parts of the Pre-Filing Process; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests, 25431-25432 [2020-09319]

Download as PDF Federal Register / Vol. 85, No. 85 / Friday, May 1, 2020 / Notices Filed Date: 4/27/20. Accession Number: 20200427–5167. Comments Due: 5 p.m. ET 5/18/20. Docket Numbers: ER20–1661–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2020–04–27_SA 3481 A TC-Richland County Solar GIA (J864) to be effective 4/13/2020. Filed Date: 4/27/20. Accession Number: 20200427–5183. Comments Due: 5 p.m. ET 5/18/20. Docket Numbers: ER20–1662–000. Applicants: Crystal Lake Wind Energy I, LLC. Description: Baseline eTariff Filing: Reactive Power Compensation Filing to be effective 6/27/2020. Filed Date: 4/27/20. Accession Number: 20200427–5185. Comments Due: 5 p.m. ET 5/18/20. Docket Numbers: ER20–1663–000. Applicants: Public Service Electric and Gas Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: PSEG submits Interconnection Agreement, SA No. 5590 with Silver Run to be effective 5/27/2020. Filed Date: 4/27/20. Accession Number: 20200427–5186. Comments Due: 5 p.m. ET 5/18/20. Docket Numbers: ER20–1664–000. Applicants: RE Mustang Two Whirlaway LLC. Description: § 205(d) Rate Filing: RE Mustang Two Whirlaway LLC LGIA CoTenancy Agreement to be effective 4/28/ 2020. Filed Date: 4/27/20. Accession Number: 20200427–5187. Comments Due: 5 p.m. ET 5/18/20. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES20–26–000. Applicants: PJM Interconnection, L.L.C. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities, et al. of PJM Interconnection, L.L.C. Filed Date: 4/24/20. Accession Number: 20200424–5304. Comments Due: 5 p.m. ET 5/4/20. Docket Numbers: ES20–27–000. Applicants: PJM Settlement, Inc. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities, et al. of PJM Settlement, Inc. Filed Date: 4/24/20. Accession Number: 20200424–5305. Comments Due: 5 p.m. ET 5/4/20. The filings are accessible in the Commission’s eLibrary system by VerDate Sep<11>2014 08:07 May 01, 2020 Jkt 250001 clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 27, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–09313 Filed 4–30–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–1616–000] Western Spirit Transmission LLC; Supplemental Notice that Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Western Spirit Transmission LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is May 18, 2020. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 25431 FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Dated: April 27, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–09317 Filed 4–30–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2513–090] Green Mountain Power Corporation; Notice of Intent To File License Application, Filing of Pre-Application Document (PAD), Commencement of Pre-Filing Process, and Scoping; Waiving Parts of the Pre-Filing Process; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests a. Type of Filing: Notice of Intent to File License Application for a New E:\FR\FM\01MYN1.SGM 01MYN1 25432 Federal Register / Vol. 85, No. 85 / Friday, May 1, 2020 / Notices License and Commencing Pre-filing Process. b. Project No.: 2513–090. c. Dated Filed: February 27, 2020. d. Submitted By: Green Mountain Power Corporation. e. Name of Project: Essex No. 19 Hydroelectric Project. f. Location: On the Winooski River, in Chittenden County, Vermont. The project does not occupy federal lands. g. Filed Pursuant to: 18 CFR part 5 of the Commission’s Regulations. h. Licensee Contact: Mr. John Greenan, Green Mountain Power Corporation, 1252 Post Road, Rutland, Vermont 05701; phone: (802) 770–2195 or email at John.Greenan@ greenmountainpower.com;. i. FERC Contact: Michael Tust at (202) 502–6522 or email at michael.tust@ ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item o below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See 94 FERC ¶ 61,076 (2001). k. With this notice, we are initiating informal consultation with: (a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402 and (b) the State Historic Preservation Officer, as required by section 106, National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Green Mountain Power Corporation (Green Mountain Power) as the Commission’s non-federal representatives for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. Green Mountain Power filed a PreApplication Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents via the internet through the Commission’s VerDate Sep<11>2014 08:07 May 01, 2020 Jkt 250001 Home Page (https://www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCONlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TYY, (202) 502–8659. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. With this notice, we are soliciting comments on the PAD and Commission’s staff Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application must be filed with the Commission. The Commission strongly encourages electronic filing. Please file all documents using the Commission’s eFiling system at https://www.ferc.gov/ docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov. All filings with the Commission must bear the appropriate heading: ‘‘Comments on Pre-Application Document,’’ ‘‘Study Requests,’’ ‘‘Comments on Scoping Document 1,’’ ‘‘Request for Cooperating Agency Status,’’ or ‘‘Communications to and from Commission Staff.’’ Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so by June 26, 2020. p. Although our current intent is to prepare an environmental assessment (EA), there is the possibility that an Environmental Impact Statement (EIS) will be required. Nevertheless, this scoping document will satisfy the NEPA PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 scoping requirements, irrespective of whether an EA or EIS is issued by the Commission. Scoping Meetings and Environmental Site Review Due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020, we are waiving section 5.8(b)(viii) of the Commission’s regulations and do not intend to conduct a public scoping meeting or site visit in this case. Instead, we are soliciting written comments, recommendations, and information, on the SD1. Any individual or entity interested in submitting scoping comments must do so by the date specified in item o. SD1, which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list. Copies of SD1 may be viewed on the web at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. We may conduct the site visit, if needed, later in the process, such as in conjunction with the study plan meeting required by section 5.11(e) of the Commission’s regulations which is required to occur by September 9. 2020. Further revisions to the schedule may be made as appropriate. Dated: April 27, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–09319 Filed 4–30–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–1650–000] Little Bear Master Tenant, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Little Bear Master Tenant, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR E:\FR\FM\01MYN1.SGM 01MYN1

Agencies

[Federal Register Volume 85, Number 85 (Friday, May 1, 2020)]
[Notices]
[Pages 25431-25432]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-09319]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2513-090]


Green Mountain Power Corporation; Notice of Intent To File 
License Application, Filing of Pre-Application Document (PAD), 
Commencement of Pre-Filing Process, and Scoping; Waiving Parts of the 
Pre-Filing Process; Request for Comments on the Pad and Scoping 
Document, and Identification of Issues and Associated Study Requests

    a. Type of Filing: Notice of Intent to File License Application for 
a New

[[Page 25432]]

License and Commencing Pre-filing Process.
    b. Project No.: 2513-090.
    c. Dated Filed: February 27, 2020.
    d. Submitted By: Green Mountain Power Corporation.
    e. Name of Project: Essex No. 19 Hydroelectric Project.
    f. Location: On the Winooski River, in Chittenden County, Vermont. 
The project does not occupy federal lands.
    g. Filed Pursuant to: 18 CFR part 5 of the Commission's 
Regulations.
    h. Licensee Contact: Mr. John Greenan, Green Mountain Power 
Corporation, 1252 Post Road, Rutland, Vermont 05701; phone: (802) 770-
2195 or email at [email protected];.
    i. FERC Contact: Michael Tust at (202) 502-6522 or email at 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item o below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC ] 
61,076 (2001).
    k. With this notice, we are initiating informal consultation with: 
(a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under 
section 7 of the Endangered Species Act and the joint agency 
regulations thereunder at 50 CFR, Part 402 and (b) the State Historic 
Preservation Officer, as required by section 106, National Historic 
Preservation Act, and the implementing regulations of the Advisory 
Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Green Mountain Power 
Corporation (Green Mountain Power) as the Commission's non-federal 
representatives for carrying out informal consultation, pursuant to 
section 7 of the Endangered Species Act and section 106 of the National 
Historic Preservation Act.
    m. Green Mountain Power filed a Pre-Application Document (PAD; 
including a proposed process plan and schedule) with the Commission, 
pursuant to 18 CFR 5.6 of the Commission's regulations.
    n. In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents via the internet through 
the Commission's Home Page (https://www.ferc.gov) using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. At this time, the 
Commission has suspended access to the Commission's Public Reference 
Room, due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TYY, 
(202) 502-8659.
    Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. With this notice, we are soliciting comments on the PAD and 
Commission's staff Scoping Document 1 (SD1), as well as study requests. 
All comments on the PAD and SD1, and study requests should be sent to 
the address above in paragraph h. In addition, all comments on the PAD 
and SD1, study requests, requests for cooperating agency status, and 
all communications to and from Commission staff related to the merits 
of the potential application must be filed with the Commission.
    The Commission strongly encourages electronic filing. Please file 
all documents using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected]
    All filings with the Commission must bear the appropriate heading: 
``Comments on Pre-Application Document,'' ``Study Requests,'' 
``Comments on Scoping Document 1,'' ``Request for Cooperating Agency 
Status,'' or ``Communications to and from Commission Staff.'' Any 
individual or entity interested in submitting study requests, 
commenting on the PAD or SD1, and any agency requesting cooperating 
status must do so by June 26, 2020.
    p. Although our current intent is to prepare an environmental 
assessment (EA), there is the possibility that an Environmental Impact 
Statement (EIS) will be required. Nevertheless, this scoping document 
will satisfy the NEPA scoping requirements, irrespective of whether an 
EA or EIS is issued by the Commission.

Scoping Meetings and Environmental Site Review

    Due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020, we are waiving section 5.8(b)(viii) of the Commission's 
regulations and do not intend to conduct a public scoping meeting or 
site visit in this case. Instead, we are soliciting written comments, 
recommendations, and information, on the SD1. Any individual or entity 
interested in submitting scoping comments must do so by the date 
specified in item o. SD1, which outlines the subject areas to be 
addressed in the environmental document, was mailed to the individuals 
and entities on the Commission's mailing list. Copies of SD1 may be 
viewed on the web at https://www.ferc.gov, using the ``eLibrary'' link. 
Follow the directions for accessing information in paragraph n. Based 
on all written comments, a Scoping Document 2 (SD2) may be issued. SD2 
may include a revised process plan and schedule, as well as a list of 
issues, identified through the scoping process.
    We may conduct the site visit, if needed, later in the process, 
such as in conjunction with the study plan meeting required by section 
5.11(e) of the Commission's regulations which is required to occur by 
September 9. 2020. Further revisions to the schedule may be made as 
appropriate.

    Dated: April 27, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-09319 Filed 4-30-20; 8:45 am]
BILLING CODE 6717-01-P