Eagle Creek Hydro Power, LLC, Eagle Creek Water Resources, LLC, Eagle Creek Land Resources, LLC; Notice of Application Tendered for Filing With The Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 20680-20681 [2020-07809]
Download as PDF
20680
Federal Register / Vol. 85, No. 72 / Tuesday, April 14, 2020 / Notices
(NGVD29); (3) a 22-foot-long, concrete
gravity intake structure; (4) a 99-footlong, concrete gravity non-overflow
section; (5) a 540-foot-long, earth-fill
embankment; (6) a 102-foot-long,
concrete gravity non-overflow section;
(7) a 460-foot-long, earth-fill
embankment with a 20-foot-wide crest
at an elevation of 825 feet NGVD29; (8)
a 1.5-mile-long bypassed reach; (9) a
7,000-foot-long, 11-foot-diameter steel
penstock connected to a 40-footdiameter by 65-foot-high steel surge
tank; (10) a 10-foot-diameter, 280-footlong underground steel penstock from
the surge tank branching into two 7foot-diameter, 100-foot-long steel
penstocks leading to the main and
minimum flow powerhouses; (11) a 22foot-square reinforced-concrete
gatehouse; (12) a 15-foot-wide by 46foot-high trashrack with 2.9-inch bar
clear spacing; (13) a 82-foot-long by 30feet-wide by 33-foot-high brick and steel
main powerhouse containing two 5
megawatt (MW) vertical-axis turbines;
(14) a 30-foot-long by 27-foot-wide by
24-foot-high reinforced concrete
minimum flow powerhouse containing
one 0.8 MW horizontal-axis turbine; (15)
a 45-foot-wide by 225-foot-long tailrace
with a 65-foot-long concrete weir from
the main powerhouse; (16) a 10-footwide by 38-foot-long tailrace from the
minimum flow powerhouse; and (17) a
760-foot-long, 4-kilovolt aboveground
transmission line. The project generates
an average of 24,859 megawatt-hours
annually. The megawatt-hours
represents Units 1 through 3 from 2014–
2019, including an extended outage of
Unit 3 in 2015. Eagle Creek proposes to
continue to operate the project in a
peaking mode.
l. A copy of the application is
available for review on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room due to the
Proclamation on Declaring a National
Emergency Concerning the Novel
Coronavirus Disease (COVID–19)
Outbreak, issued by the President on
March 13, 2020. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis ...........................................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ........................................................
Commission issues Environmental Assessment (EA) ................................................................................................................
Comments on EA ........................................................................................................................................................................
Modified terms and conditions ....................................................................................................................................................
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: April 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–07811 Filed 4–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 10482–122]
jbell on DSKJLSW7X2PROD with NOTICES
Eagle Creek Hydro Power, LLC, Eagle
Creek Water Resources, LLC, Eagle
Creek Land Resources, LLC; Notice of
Application Tendered for Filing With
The Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 10482–122.
VerDate Sep<11>2014
18:26 Apr 13, 2020
Jkt 250001
c. Date Filed: March 31, 2020.
d. Applicant: Eagle Creek Hydro
Power, LLC, Eagle Creek Water
Resources, LLC, and Eagle Creek Land
Resources, LLC (collectively referred to
as Eagle Creek).
e. Name of Project: Swinging Bridge
Hydroelectric Project (Swinging Bridge
Project).
f. Location: The existing project is
located on the Mongaup River and Black
Lake Creek in Sullivan County, New
York. The project does not occupy
federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Robert
Gates, Senior Vice President—
Regulatory, Eagle Creek Renewable
Energy, LLC., 116 N State Street, PO Box
167, Neshkoro, WI 54960–0167; (973)
998–8400 or bob.gates@
eaglecreekre.com.
i. FERC Contact: Nicholas Ettema at
(312) 596–4447 or email at
nicholas.ettema@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The Swinging
Bridge Project includes the Toronto
Development, the Cliff Lake
Development, and the Swinging Bridge
Development. Water stored in Toronto
Reservoir is released into Cliff Lake
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
July 2020.
November 2020.
May 2021.
June 2021.
August 2021.
Reservoir, which is connected to
Swinging Bridge Reservoir via a tunnel.
The Toronto Development consists of:
(1) A reservoir with a gross storage
capacity of 27,064 acre-feet and a
surface area of 843 acres; (2) a 1,620foot-long by 103-foot-high earth-fill dam
with a 25-foot-wide crest at elevation
1,230 feet National Geodetic Vertical
Datum of 1929 (NGVD29); (3) a 700-footlong by 50-foot-wide concrete and rock
side-channel spillway equipped with 5foot-high by 50-foot-wide pin-type
flashboards; (4) a 17.5-foot-wide by
11.5-foot-long gated concrete tower; (5)
an upper 4-foot-wide by 5-foot-high gate
and a lower 3-foot-wide by 5-foot-high
gate; and 6) a 565-foot-long by 8-footwide by 8-foot-high horseshoe-shaped
concrete conduit.
The Cliff Lake Development consists
of: (1) A reservoir with a gross storage
capacity of 3,200 acre-feet and a surface
area of 183 acres; (2) a 95-foot-long by
20-foot-wide by 36-foot-high east
earthen embankment; (3) a 150-foot-long
by 44-foot-wide by 36-foot-high concrete
non-overflow section; (4) a 100-foot-long
by 5-foot-wide by 26-foot-high concrete
overflow spillway section with 13-inchhigh flashboards; (5) a 270-foot-long by
20-foot-wide by 50-foot-high west
earthen embankment; (6) a 5.3-footwide,
6.7-foot-high, 2,100-foot-long horseshoe-
E:\FR\FM\14APN1.SGM
14APN1
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 72 / Tuesday, April 14, 2020 / Notices
shaped tunnel; (7) a 4-foot by 4-foot
sluice gate; and (8) a 5-foot-wide by 5foot-high lift gate.
The Swinging Bridge Development
consists of: (1) A reservoir with a gross
storage capacity of 35,925 acre-feet and
a surface area of 980 acres; (2) a 965foot-long by 135-foot-high earth-fill dam
with a 25-foot-wide crest at elevation
1,080 feet NGVD29; (3) a 750-foot-long
by 250-foot-wide concrete side channel
spillway; (4) a 5-foot-high by 122.5-footwide gate section and five motor driven
22.5-foot-wide by 5-foot-high verticallift timber gates; (5) a 692-foot-long, 10foot-diameter steel lined concrete
penstock (which has been retired in
place); (6) 784-foot-long, 9.75-footdiameter concrete-lined tunnel
connected to a 188-foot-long, 10-footdiameter all-steel penstock; (7) a 10foot-long, 4-foot-diameter penstock; (8) a
30-foot-diameter steel surge tank; (9) a
48-foot-wide by 33-foot-long by 35-foot,
8-inch-high brick and steel Unit 2
powerhouse containing one 6.75
megawatt (MW) generating unit; (10) a
30-foot-long by 30-foot-wide by 20-foothigh concrete and steel Unit 3
powerhouse containing one 1.1 MW
generating unit; (11) one 25-foot-wide
by 75-foot-long tailrace and one 6-footwide by 20-foot-long tailrace; (12) a 150foot-long, 2.3 kilovolt (kV) transmission
line and a 250-foot-long, 4 kV
transmission line. The project generates
an average of 11,639 megawatt-hours
annually (Unit 2 only). Eagle Creek
proposes to continue to operate the
project in a peaking mode.
l. A copy of the application is
available for review on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room due to the
Proclamation on Declaring a National
Emergency Concerning the Novel
Coronavirus Disease (COVID–19)
Outbreak, issued by the President on
March 13, 2020. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary schedule.
VerDate Sep<11>2014
18:26 Apr 13, 2020
Jkt 250001
Revisions to the schedule may be made
as appropriate.
Milestone
Target date
Notice of Acceptance/Notice of
Ready for Environmental.
Analysis ......................................
Filing of recommendations, preliminary terms and conditions,
and fishway prescriptions.
Commission issues Environmental Assessment (EA).
Comments on EA .......................
Modified terms and conditions ...
July 2020.
November 2020
May 2021.
June 2021.
August 2021.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: April 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–07809 Filed 4–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–118–000]
Trans-Foreland Pipeline Company,
LLC; Notice Suspending
Environmental Review Schedule
The Federal Energy Regulatory
Commission (FERC or Commission) is
suspending the environmental review
schedule for Trans-Foreland Pipeline
Company, LLC’s (Trans-Foreland)
application for the Kenai LNG Cool
Down Project in Nikiski, Alaska. The
notice of revised schedule, issued on
December 12, 2019, identified an April
24, 2020 environmental assessment (EA)
issuance date. This schedule was based
upon Trans-Foreland providing
complete and timely responses to any
data requests. In its March 18, 2020
response to FERC staff’s March 3, 2020
data request, Trans-Foreland stated it
was pursuing an equivalency
determination from the United States
Department of Transportation’s Pipeline
and Hazardous Material Safety
Administration (PHMSA) pertaining to
the trim vaporizer it proposes to locate
within the liquefied natural gas (LNG)
storage tank impoundment area.1
Because the PHMSA equivalency
determination is necessary for
completion of the EA, the Commission
1 While PHMSA issued a letter of determination
(LOD) on March 25, 2020 that addresses the siting
of LNG facilities, including the vaporizer, under
Subpart B of its regulations, the LOD does not
address Trans-Foreland’s March 17, 2020
equivalency determination request.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
20681
will suspend the environmental review
schedule for the project. Once staff has
reviewed the PHMSA equivalency
determination, FERC will issue an
additional revised schedule for the EA.
This is not a suspension of the FERC
staff’s review of Trans-Foreland’s
project. Staff will continue to process
Trans-Foreland’s proposal to the extent
possible based upon the information it
has filed to date.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP19–118), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: April 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–07812 Filed 4–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL20–40–000]
Brookfield Asset Management, Inc.;
Notice of Petition for Declaratory Order
Take notice that on April 7, 2020,
pursuant to Rule 207 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207, Brookfield
Asset Management Inc. (Petitioner), on
behalf of itself and its current and future
subsidiary companies that are holding
E:\FR\FM\14APN1.SGM
14APN1
Agencies
[Federal Register Volume 85, Number 72 (Tuesday, April 14, 2020)]
[Notices]
[Pages 20680-20681]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-07809]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 10482-122]
Eagle Creek Hydro Power, LLC, Eagle Creek Water Resources, LLC,
Eagle Creek Land Resources, LLC; Notice of Application Tendered for
Filing With The Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 10482-122.
c. Date Filed: March 31, 2020.
d. Applicant: Eagle Creek Hydro Power, LLC, Eagle Creek Water
Resources, LLC, and Eagle Creek Land Resources, LLC (collectively
referred to as Eagle Creek).
e. Name of Project: Swinging Bridge Hydroelectric Project (Swinging
Bridge Project).
f. Location: The existing project is located on the Mongaup River
and Black Lake Creek in Sullivan County, New York. The project does not
occupy federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Robert Gates, Senior Vice President--
Regulatory, Eagle Creek Renewable Energy, LLC., 116 N State Street, PO
Box 167, Neshkoro, WI 54960-0167; (973) 998-8400 or
[email protected].
i. FERC Contact: Nicholas Ettema at (312) 596-4447 or email at
[email protected].
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The Swinging Bridge Project includes the
Toronto Development, the Cliff Lake Development, and the Swinging
Bridge Development. Water stored in Toronto Reservoir is released into
Cliff Lake Reservoir, which is connected to Swinging Bridge Reservoir
via a tunnel.
The Toronto Development consists of: (1) A reservoir with a gross
storage capacity of 27,064 acre-feet and a surface area of 843 acres;
(2) a 1,620-foot-long by 103-foot-high earth-fill dam with a 25-foot-
wide crest at elevation 1,230 feet National Geodetic Vertical Datum of
1929 (NGVD29); (3) a 700-foot-long by 50-foot-wide concrete and rock
side-channel spillway equipped with 5-foot-high by 50-foot-wide pin-
type flashboards; (4) a 17.5-foot-wide by 11.5-foot-long gated concrete
tower; (5) an upper 4-foot-wide by 5-foot-high gate and a lower 3-foot-
wide by 5-foot-high gate; and 6) a 565-foot-long by 8-foot-wide by 8-
foot-high horseshoe-shaped concrete conduit.
The Cliff Lake Development consists of: (1) A reservoir with a
gross storage capacity of 3,200 acre-feet and a surface area of 183
acres; (2) a 95-foot-long by 20-foot-wide by 36-foot-high east earthen
embankment; (3) a 150-foot-long by 44-foot-wide by 36-foot-high
concrete non-overflow section; (4) a 100-foot-long by 5-foot-wide by
26-foot-high concrete overflow spillway section with 13-inch-high
flashboards; (5) a 270-foot-long by 20-foot-wide by 50-foot-high west
earthen embankment; (6) a 5.3-footwide, 6.7-foot-high, 2,100-foot-long
horseshoe-
[[Page 20681]]
shaped tunnel; (7) a 4-foot by 4-foot sluice gate; and (8) a 5-foot-
wide by 5-foot-high lift gate.
The Swinging Bridge Development consists of: (1) A reservoir with a
gross storage capacity of 35,925 acre-feet and a surface area of 980
acres; (2) a 965-foot-long by 135-foot-high earth-fill dam with a 25-
foot-wide crest at elevation 1,080 feet NGVD29; (3) a 750-foot-long by
250-foot-wide concrete side channel spillway; (4) a 5-foot-high by
122.5-foot-wide gate section and five motor driven 22.5-foot-wide by 5-
foot-high vertical-lift timber gates; (5) a 692-foot-long, 10-foot-
diameter steel lined concrete penstock (which has been retired in
place); (6) 784-foot-long, 9.75-foot-diameter concrete-lined tunnel
connected to a 188-foot-long, 10-foot-diameter all-steel penstock; (7)
a 10-foot-long, 4-foot-diameter penstock; (8) a 30-foot-diameter steel
surge tank; (9) a 48-foot-wide by 33-foot-long by 35-foot, 8-inch-high
brick and steel Unit 2 powerhouse containing one 6.75 megawatt (MW)
generating unit; (10) a 30-foot-long by 30-foot-wide by 20-foot-high
concrete and steel Unit 3 powerhouse containing one 1.1 MW generating
unit; (11) one 25-foot-wide by 75-foot-long tailrace and one 6-foot-
wide by 20-foot-long tailrace; (12) a 150-foot-long, 2.3 kilovolt (kV)
transmission line and a 250-foot-long, 4 kV transmission line. The
project generates an average of 11,639 megawatt-hours annually (Unit 2
only). Eagle Creek proposes to continue to operate the project in a
peaking mode.
l. A copy of the application is available for review on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. At this time, the
Commission has suspended access to the Commission's Public Reference
Room due to the Proclamation on Declaring a National Emergency
Concerning the Novel Coronavirus Disease (COVID-19) Outbreak, issued by
the President on March 13, 2020. For assistance, please contact FERC
Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY).
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule may be
made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for July 2020.
Environmental.
Analysis................................
Filing of recommendations, preliminary November 2020
terms and conditions, and fishway
prescriptions.
Commission issues Environmental May 2021.
Assessment (EA).
Comments on EA.......................... June 2021.
Modified terms and conditions........... August 2021.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: April 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-07809 Filed 4-13-20; 8:45 am]
BILLING CODE 6717-01-P