Texas Eastern Transmission, LP; Notice of Schedule for Environmental Review of the Lilly Compressor Units Replacement Project, 15165-15166 [2020-05459]
Download as PDF
khammond on DSKJM1Z7X2PROD with NOTICES
Federal Register / Vol. 85, No. 52 / Tuesday, March 17, 2020 / Notices
Accession Number: 20200310–5189.
Comments Due: 5 p.m. ET 3/20/20.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER19–2717–000.
Applicants: Madison ESS, LLC.
Description: Report Filing: Madison
ESS Supplemental Refund Report Filing
to be effective N/A.
Filed Date: 3/10/20.
Accession Number: 20200310–5000.
Comments Due: 5 p.m. ET 3/31/20.
Docket Numbers: ER20–793–001.
Applicants: American Transmission
Systems, Incorporated, PJM
Interconnection, L.L.C.
Description: Tariff Amendment: ATSI
submits Revised ECSAs, Service
Agreement No. 5390 and 5516 to be
effective 3/14/2020.
Filed Date: 3/10/20.
Accession Number: 20200310–5158.
Comments Due: 5 p.m. ET 3/20/20.
Docket Numbers: ER20–971–001.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Tariff Amendment:
2020–03–10_SA 3421 MEC-Heartland
Divide Wind II Substitute GIA (J583) to
be effective 1/28/2020.
Filed Date: 3/10/20.
Accession Number: 20200310–5134.
Comments Due: 5 p.m. ET 3/31/20.
Docket Numbers: ER20–972–001.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Tariff Amendment:
2020–03–11_SA 3422 ITC-Three Waters
Wind Farm Substitute GIA (J720) to be
effective 1/28/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5041.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–991–001.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Tariff Amendment:
2020–03–11_SA 1495 NSP-Walleye
Wind Substitute 1st Rev GIA (G253
J569) to be effective 1/29/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5090.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1223–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to ISA, SA No. 5422;
Queue No. AC1–158 to be effective
6/14/2019.
Filed Date: 3/10/20.
Accession Number: 20200310–5151
Comments Due: 5 p.m. ET 3/31/20.
Docket Numbers: ER20–1224–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
VerDate Sep<11>2014
17:32 Mar 16, 2020
Jkt 250001
Description: § 205(d) Rate Filing:
2020–03–11_SA 3455 OTP-Tatanka
Ridge Wind FSA (J493) Astoria BSSB In
& Out to be effective
3/12/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5073.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1225–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–11_SA 3456 OTP–OTP FSA
(J510) Astoria BSSB In & Out to be
effective 3/12/20.20.
Filed Date: 3/11/20.
Accession Number: 20200311–5074.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1226–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–11_SA 3457 OTP-Tatanka
Ridge Wind FSA (J493) Astoria
Switching Station to be effective 3/12/
2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5079.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1227–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–11_SA 3458 OTP–OTP FSA
(J510) Astoria Switching Station to be
effective 3/12/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5082.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1228–000.
Applicants: Duke Energy Progress,
LLC., Duke Energy Carolinas, LLC.
Description: § 205(d) Rate Filing:
DEC–DEP NC Excess ADIT Credit to be
effective 1/1/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5088.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1232–000.
Applicants: Louisville Gas and
Electric Company.
Description: Tariff Cancellation: EEI
IA Notice of Termination to be effective
2/29/2020.
Filed Date: 3/11/20.
Accession Number: 20200311–5098.
Comments Due: 5 p.m. ET 4/1/20.
Docket Numbers: ER20–1233–000.
Applicants: Kentucky Utilities
Company.
Description: Tariff Cancellation: KU
Concurrence EEI IA Notice of
Termination to be effective 2/29/2020.
Filed Date: 3/11/20.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
15165
Accession Number: 20200311–5101.
Comments Due: 5 p.m. ET 4/1/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 11, 2020..
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–05469 Filed 3–16–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–37–000]
Texas Eastern Transmission, LP;
Notice of Schedule for Environmental
Review of the Lilly Compressor Units
Replacement Project
On January 10, 2020, Texas Eastern
Transmission, LP filed an application in
Docket No. CP20–37–000 requesting a
Certificate of Public Convenience and
Necessity pursuant to Sections 7(c) of
the Natural Gas Act to construct and
operate certain natural gas pipeline
facilities in Cambria County,
Pennsylvania. The proposed project is
known as the Lilly Compressor Unit
Replacement Project (Project) and
consists of Texas Eastern Transmission,
LP’s proposed replacement of four
existing compressor units at the Lilly
Compressor Station with two new more
efficient turbine units.
On January 22, 2020, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
E:\FR\FM\17MRN1.SGM
17MRN1
15166
Federal Register / Vol. 85, No. 52 / Tuesday, March 17, 2020 / Notices
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA June 5, 2020
90-day Federal Authorization Decision
Deadline September 3, 2020
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The Lilly Compressor Units
Replacement Project would comprise
replacing the four existing gas turbine
units totaling 34,800 horsepower (hp)
with two new, more efficient, 18,100 hp
gas turbine units. Software controls
would be installed on the two new units
to limit the total station hp to 34,800 hp,
keeping the delivery capacity at the
station the same. The Project also
involves the construction of a new
compressor building to house the two
new compressor units. All facilities are
located in Cambria County,
Pennsylvania.
khammond on DSKJM1Z7X2PROD with NOTICES
Background
On February 25, 2020, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Lilly Compressor Units
Replacement Project and Request for
Comments on Environmental Issues
(NOI). The NOI was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the NOI,
the Commission received no comments
to date. All substantive comments will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
VerDate Sep<11>2014
17:32 Mar 16, 2020
Jkt 250001
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP20–37), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: March 11, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–05459 Filed 3–16–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2221–041]
Empire District Electric Company;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2221–041.
c. Date Filed: February 28, 2020.
d. Applicant: Empire District Electric
Company (Empire District).
e. Name of Project: Ozark Beach
Hydroelectric Project (Ozark Beach
Project).
f. Location: The existing project is
located on the White River in Taney
County, Missouri. The project occupies
5.1 acres of United States lands
administered by the U.S. Army Corps of
Engineers (Corps).
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Tim Wilson,
Strategic Projects and Energy Supply,
Empire District Electric Company, 602
South Joplin Avenue, P.O. Box 127,
Joplin, MO 64802, (913) 458–6437 or
timpedccccc@by.com; and Randy
Richardson, Plant Manager, Empire
District Electric Company, 2537 Fir
Road, Sarcoxie, MO 64862, (417) 625–
6138 or RRichardson@
libertyutilities.com.
i. FERC Contact: Colleen Corballis at
(202) 502–8598 or email at
colleen.corballis@ferc.gov.
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
j. This application is not ready for
environmental analysis at this time.
k. The Ozark Beach Project consists of
the following existing facilities: (1) 2,200
acre Lake Taneycomo with a gross
storage capacity of 22,000 acre-feet and
a usable storage capacity of 6,500 acrefeet at a water surface elevation of
701.35 feet National Geodetic Vertical
Datum of 1929; (2) a 1,273-foot-long, 53foot-high dam consisting of, from west
to east: (a) A 420-foot-long earth fill
embankment, (b) a 575-foot-long
concrete overflow spillway topped with
32 Obermeyer gates, (c) an 18-foot-long
concrete overflow spillway, (d) an
integral 210-foot-long reinforced
concrete powerhouse, and (e) a 50-footlong concrete non-overflow section; (3)
a 210-foot-long, 80-foot-wide, 92-foothigh reinforced concrete integral
powerhouse with an operating head of
50 feet; (4) trash racks at the entrance to
intakes; (5) four 7,250 horsepower
vertical-shaft Francis-type turbines with
a total capacity of 29,000 horsepower,
each couple to a 4.0 megawatt (MW)
generator with a total capacity of 16.0
MW; (6) a 200-foot-long, 4,600-volt
overhead transmission line connected to
a three phase 22,400-kilovolt ampere
4,600 to 161,000-volt step-up
transformer that connects to Empire
District Electric Company’s 161,000-volt
transmission system; and (7)
appurtenant facilities.
The existing Ozark Beach Project is
situated between two multipurpose
projects that are owned by the Corps.
The Table Rock Project, which is
immediately upstream of the Ozark
Beach Project, is operated in a peaking
mode based on regional demand
requirements. The Ozark Beach Project
discharges directly into the Bull Shoals
Project reservoir, which is immediately
downstream. Using the storage in Lake
Taneycomo, the Ozark Beach Project is
operated based on various conditions
including closely matching the releases
of the upstream Table Rock Project,
market pricing, Lake Taneycomo water
level, Bull Shoals water level and
rainfall. The Ozark Beach Project has an
estimated annual energy production of
about 50,768 megawatt hours. Empire
District proposes to continue to operate
using the storage in Lake Taneycomo.
Empire District does not propose any
new construction.
Empire District proposes to modify
the project boundary by removing 6,021
acres from the existing area of 8,267
acres for a proposed project boundary of
2,246 acres. Empire District’s proposal
would reduce the existing area of
United States lands administered by the
Corps from 5.1 acres to 0.64 acres.
E:\FR\FM\17MRN1.SGM
17MRN1
Agencies
[Federal Register Volume 85, Number 52 (Tuesday, March 17, 2020)]
[Notices]
[Pages 15165-15166]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-05459]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-37-000]
Texas Eastern Transmission, LP; Notice of Schedule for
Environmental Review of the Lilly Compressor Units Replacement Project
On January 10, 2020, Texas Eastern Transmission, LP filed an
application in Docket No. CP20-37-000 requesting a Certificate of
Public Convenience and Necessity pursuant to Sections 7(c) of the
Natural Gas Act to construct and operate certain natural gas pipeline
facilities in Cambria County, Pennsylvania. The proposed project is
known as the Lilly Compressor Unit Replacement Project (Project) and
consists of Texas Eastern Transmission, LP's proposed replacement of
four existing compressor units at the Lilly Compressor Station with two
new more efficient turbine units.
On January 22, 2020, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance
[[Page 15166]]
of the Commission staff's Environmental Assessment (EA) for the
Project. This instant notice identifies the FERC staff's planned
schedule for the completion of the EA for the Project.
Schedule for Environmental Review
Issuance of EA June 5, 2020
90-day Federal Authorization Decision Deadline September 3, 2020
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The Lilly Compressor Units Replacement Project would comprise
replacing the four existing gas turbine units totaling 34,800
horsepower (hp) with two new, more efficient, 18,100 hp gas turbine
units. Software controls would be installed on the two new units to
limit the total station hp to 34,800 hp, keeping the delivery capacity
at the station the same. The Project also involves the construction of
a new compressor building to house the two new compressor units. All
facilities are located in Cambria County, Pennsylvania.
Background
On February 25, 2020, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed Lilly Compressor
Units Replacement Project and Request for Comments on Environmental
Issues (NOI). The NOI was sent to affected landowners; federal, state,
and local government agencies; elected officials; environmental and
public interest groups; Native American tribes; other interested
parties; and local libraries and newspapers. In response to the NOI,
the Commission received no comments to date. All substantive comments
will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the eLibrary link, select General
Search from the eLibrary menu, enter the selected date range and Docket
Number excluding the last three digits (i.e., CP20-37), and follow the
instructions. For assistance with access to eLibrary, the helpline can
be reached at (866) 208-3676, TTY (202) 502-8659, or at
[email protected]. The eLibrary link on the FERC website also
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rule makings.
Dated: March 11, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-05459 Filed 3-16-20; 8:45 am]
BILLING CODE 6717-01-P