City of Watervliet; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 14474 [2020-05067]
Download as PDF
14474
Federal Register / Vol. 85, No. 49 / Thursday, March 12, 2020 / Notices
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
Dated: March 6, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–05069 Filed 3–11–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2955–011]
khammond on DSKJM1Z7X2PROD with NOTICES
City of Watervliet; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 2955–011.
c. Date Filed: February 28, 2020.
d. Applicant: City of Watervliet, New
York.
e. Name of Project: Normanskill
Hydroelectric Project.
f. Location: The project is located on
the Normans Kill in Guilderland,
Albany County, New York. The project
does not occupy any federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Michele E.
Stottler, Gomez and Sullivan Engineers,
DPC, 399 Albany Shaker Road, Suite
203, Loudonville, NY 12211; (518) 407–
0050; email—mstottler@
gomezandsullivan.com or Joseph
LaCivita, General Manager, The City of
Watervliet, 2 Fifteenth Street,
Watervliet, NY 12189; (518) 270–3800;
email—jlacivita@watervliet.com.
i. FERC Contact: Woohee Choi at
(202) 502–6336; or email at
woohee.choi@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
VerDate Sep<11>2014
16:31 Mar 11, 2020
Jkt 250001
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: April 28, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–2955–011.
m. This application is not ready for
environmental analysis at this time.
n. The Normanskill Project consists of
the following existing facilities: (1) A
380-foot-long reinforced concrete
Ambursen-type dam with a 306-footlong overflow section having a crest
elevation of 259 feet National Geodetic
Vertical Datum of 1929 (NGVD29)
surmounted by 3-foot flashboards; (2) a
380-acre reservoir with a gross volume
of 3,600 acre-feet at the normal
maximum pool elevation of 262 feet
NGVD29; (3) an intake structure and
sluiceway; (4) a 700-foot-long, 6-footdiameter, concrete-encased steel, buried
penstock; (5) a reinforced concrete
underground powerhouse containing a
single 1,250-kilowatt tube-type
generating unit; (6) a 600-foot-long, 2.4kilovolt (kV) transmission line; (7) a 2.4/
13.2–kV transformer bank; and (8)
appurtenant facilities.
The Normanskill Project is operated
in a run-of-river mode with an average
annual generation of 2,863 megawatthours between 2010 and 2019.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary).
Request Additional Information ..
Issue Acceptance Letter .............
Issue Scoping Document 1 for
comments.
Request Additional Information
(if necessary).
Issue Scoping Document 2 ........
Issue notice of ready for environmental analysis.
Commission issues EA ...............
Comments on EA .......................
April 2020.
April 2020.
July 2020.
August 2020.
October 2020.
November 2020.
November 2020.
May 2021.
June 2021.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: March 6, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–05067 Filed 3–11–20; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OAR–2019–0338; FRL–10006–53–
OAR]
Notice of Finding of Failure To Submit
State Plans for the Municipal Solid
Waste Landfills Emission Guidelines
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The U.S. Environmental
Protection Agency (EPA) finds that 42
states and territories have failed to
submit state plans for the 2016 Emission
Guidelines and Compliance Times for
Municipal Solid Waste Landfills (MSW
Landfills EG). According to the MSW
SUMMARY:
E:\FR\FM\12MRN1.SGM
12MRN1
Agencies
[Federal Register Volume 85, Number 49 (Thursday, March 12, 2020)]
[Notices]
[Page 14474]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-05067]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2955-011]
City of Watervliet; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 2955-011.
c. Date Filed: February 28, 2020.
d. Applicant: City of Watervliet, New York.
e. Name of Project: Normanskill Hydroelectric Project.
f. Location: The project is located on the Normans Kill in
Guilderland, Albany County, New York. The project does not occupy any
federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Michele E. Stottler, Gomez and Sullivan
Engineers, DPC, 399 Albany Shaker Road, Suite 203, Loudonville, NY
12211; (518) 407-0050; [email protected] or Joseph
LaCivita, General Manager, The City of Watervliet, 2 Fifteenth Street,
Watervliet, NY 12189; (518) 270-3800; [email protected]
i. FERC Contact: Woohee Choi at (202) 502-6336; or email at
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: April 28, 2020.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first page of any filing should include
docket number P-2955-011.
m. This application is not ready for environmental analysis at this
time.
n. The Normanskill Project consists of the following existing
facilities: (1) A 380-foot-long reinforced concrete Ambursen-type dam
with a 306-foot-long overflow section having a crest elevation of 259
feet National Geodetic Vertical Datum of 1929 (NGVD29) surmounted by 3-
foot flashboards; (2) a 380-acre reservoir with a gross volume of 3,600
acre-feet at the normal maximum pool elevation of 262 feet NGVD29; (3)
an intake structure and sluiceway; (4) a 700-foot-long, 6-foot-
diameter, concrete-encased steel, buried penstock; (5) a reinforced
concrete underground powerhouse containing a single 1,250-kilowatt
tube-type generating unit; (6) a 600-foot-long, 2.4-kilovolt (kV)
transmission line; (7) a 2.4/13.2-kV transformer bank; and (8)
appurtenant facilities.
The Normanskill Project is operated in a run-of-river mode with an
average annual generation of 2,863 megawatt-hours between 2010 and
2019.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's website at https://www.ferc.gov using the eLibrary link.
Enter the docket number excluding the last three digits in the docket
number field to access the document. For assistance, contact FERC
Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
------------------------------------------------------------------------
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).. April 2020.
Request Additional Information.......... April 2020.
Issue Acceptance Letter................. July 2020.
Issue Scoping Document 1 for comments... August 2020.
Request Additional Information (if October 2020.
necessary).
Issue Scoping Document 2................ November 2020.
Issue notice of ready for environmental November 2020.
analysis.
Commission issues EA.................... May 2021.
Comments on EA.......................... June 2021.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: March 6, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-05067 Filed 3-11-20; 8:45 am]