Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices
implementation, and analysis of
automatic underfrequency load
shedding (UFLS) programs among all
NPCC applicable entities. These
requirements are more stringent and
specific than the NERC continent-wide
UFLS Reliability Standard, PRC–006–3,
and were established such that the
declining frequency is arrested and
recovered in accordance with NPCC
performance requirements. NPCC
revised currently effective Regional
Reliability Standard PRC–006–NPCC–1
to remove redundancies with the
Reliability Standard PRC–006–3, clarify
obligations for registered entities,
improve communication of island
boundaries to affected registered
entities, and provide entities with the
flexibility to calculate net load shed for
UFLS in certain situations.
On February 19, 2020, the
Commission issued a Delegated Letter
Order, Docket No. RD20–1–000,
approving proposed Reliability
Standard PRC–006–NPCC–2, the
associated VRFs and VSLs, the Effective
Date, and the retirement of the currently
effective Regional Reliability Standard
PRC–006–NPCC–1. The effective date
for Reliability Standard PRC–006–
NPCC–2 is as of the date of this order,
January 18, 2020.
Type of Respondents: Generator
owners, planning coordinators,
distribution providers, and transmission
owners in the Northeast Power
Coordinating Council (NPCC) Region.
Estimate of Annual Burden: 5 Our
estimates are based on the NERC
Compliance Registry Summary of
Entities as of January 31, 2019.
According to the NERC compliance
14191
registry, and Functions as of, which
indicates there are registered as GO, PC,
DP and TO entities.
The individual burden estimates are
based on the time needed to gather data,
run studies, and analyze study results to
design or update the underfrequency
load shedding programs. Additionally,
documentation and the review of
underfrequency load shedding program
results by supervisors and management
is included in the administrative
estimations. These are consistent with
estimates for similar tasks in other
Commission approved standards.
Estimates for the additional burden
and cost imposed by the order in Docket
No. RD20–1–000 follow:
Commission estimates the annual
burden and cost 6 as follows. Burden
and cost for the information collection
as follows:
RD20–1–000—MANDATORY RELIABILITY STANDARDS FOR THE BULK-POWER SYSTEM: REGIONAL RELIABILITY STANDARD
PRC–006–NPCC–2 AUTOMATIC UNDERFREQUENCY LOAD SHEDDING
[UFLS]
Reliability standard &
requirement
Average
annual number 1
of respondents
Average
annual number
of responses
per respondent
Average annual
total number of
responses
Average burden
hrs. & cost
($) per response
Total annual burden
hours & cost
($) (rounded)
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
...........
...........
...........
...........
3,000 hrs.; $10,000 ...
48 hrs.; $160 .............
1,224 hrs.; $4,080 .....
936 hrs.; $3,120 ........
$80
$80
$80
....................
...............................
5,208 hrs.; $17,360 ...
....................
GO ....................................
PC .....................................
DP .....................................
TO .....................................
125
2
51
39
1
1
1
1
125
2
51
39
Total ..........................
............................
..........................
..........................
lotter on DSKBCFDHB2PROD with NOTICES
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
24
24
24
24
hrs.;
hrs.;
hrs.;
hrs.;
$80
$80
$80
$80
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
BILLING CODE 6717–01–P
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–1113–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment: 3616
Iron Star Wind Project/ITC E&P Ag
Cancel-Amended Filing to be effective
2/8/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5060.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1164–000.
Applicants: Midcontinent
Independent System Operator, Inc.
5 Burden is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a federal agency. See 5 CFR
1320 for additional information on the definition of
information collection burden.
6 The Commission staff estimates that industry is
similarly situated in terms of hourly cost (for wages
Dated: March 5, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04953 Filed 3–10–20; 8:45 am]
VerDate Sep<11>2014
16:37 Mar 10, 2020
Jkt 250001
PO 00000
Frm 00008
Fmt 4703
Sfmt 4703
Description: § 205(d) Rate Filing:
2020–03–04_SA 3438 Entergy ArkansasLong Lake Solar GIA (J834) to be
effective 2/21/2020.
Filed Date: 3/4/20.
Accession Number: 20200304–5295.
Comments Due: 5 p.m. ET 3/25/20.
Docket Numbers: ER20–1167–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Republic Transmission, LLC.
Description: § 205(d) Rate Filing:
2020–03–04_Republic Transmission
Integration Filing to be effective 12/31/
9998.
Filed Date: 3/4/20.
Accession Number: 20200304–5247.
Comments Due: 5 p.m. ET 3/25/20.
Docket Numbers: ER20–1168–000.
Applicants: DTE Big Turtle Wind
Farm I, LLC.
Description: § 205(d) Rate Filing: DTE
Big Turtle Wind Farm I, LLC Notice of
Succession to be effective 1/15/2020.
plus benefits). Based on the Commission’s FY
(Fiscal Year) 2019 average cost (for wages plus
benefits), $80.00/hour is used.
E:\FR\FM\11MRN1.SGM
11MRN1
lotter on DSKBCFDHB2PROD with NOTICES
14192
Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices
Filed Date: 3/5/20.
Accession Number: 20200305–5056.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1169–000.
Applicants: The Dayton Power and
Light Company, East Kentucky Power
Cooperative, Inc., PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: The
Dayton Power and Light Company
submits IA SA No. 3137 to be effective
5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5070.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1170–000.
Applicants: Electric Energy, Inc.
Description: Tariff Cancellation:
Cancellation Open Access Transmission
Tariff to be effective 3/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5072.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1171–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: First
Revised ISA, SA No. 5231; Queue No.
AC1–048/AC2–053/AE1–006 to be
effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5078.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1172–000.
Applicants: Emera Maine.
Description: Tariff Cancellation:
Notice of Termination of Expired TSA—
ReEnergy Ashland, LLC to be effective
2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5079.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1173–000.
Applicants: Emera Maine.
Description: Tariff Cancellation:
Notice of Termination of Expired
Interconnect Agreement—ReEnergy
Ashland, LP to be effective 2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5081.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1174–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3440 OTP-Dakota
Range III FSA (J488) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5083.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1175–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3441 OTP-Tatanka
VerDate Sep<11>2014
16:37 Mar 10, 2020
Jkt 250001
Ridge Wind FSA (J493) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5089.
Comments Due: 5 p.m. ET 3/26/20.
DEPARTMENT OF ENERGY
Docket Numbers: ER20–1176–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3342 OTP-Deuel
Harvest Wind FSA (J526) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5091.
Comments Due: 5 p.m. ET 3/26/20.
South Sutter Water District; Notice of
Application for Surrender of Conduit
Exemption, Soliciting Comments,
Motions To Intervene, and Protests
Docket Numbers: ER20–1177–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
Amended GIA and DSA San Gorgonio
Westwinds II, San Jacinto Power SA No.
863–864 to be effective 5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5112.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1178–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5596; Queue No.
AD1–020 to be effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5117.
Comments Due: 5 p.m. ET 3/26/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 5, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–04961 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00009
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Project No. 7580–003]
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Proceeding: Application for
surrender of conduit exemption from
licensing.
b. Project No.: 7580–003.
c. Date Filed: December 31, 2019.
d. Exemptee: South Sutter Water
District (SSWD).
e. Name of Project: Vanjop No. 1
Hydroelectric Project.
f. Location: The project is located on
SSWD’s Conveyance Canal which is
part of SSWD’s water delivery system
near Sheridan in Placer County,
California.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Licensee Contact: Brad Arnold,
General Manager, South Suter Water
District, 2464 Pacific Avenue,
Trowbridge, CA 95659, (530) 656–2242
sswd@hughes.net.
i. FERC Contact: Kim Nguyen, (202)
502–6105, Kim.Nguyen@ferc.gov.
j. Deadline for filing comments,
interventions, and protests is April 3,
2020. The Commission strongly
encourages electronic filing. Please file
motions to intervene, protests and
comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–7580–003.
k. Description of Project Facilities:
The project consists of a radial gate, a
bypass gate, an intake structure, a catch
basin, a discharge structure, three
turbine-generator units with total
generating capacity of 415 kilowatts,
and a short transmission line.
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 85, Number 48 (Wednesday, March 11, 2020)]
[Notices]
[Pages 14191-14192]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04961]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER20-1113-001.
Applicants: Southwest Power Pool, Inc.
Description: Tariff Amendment: 3616 Iron Star Wind Project/ITC E&P
Ag Cancel-Amended Filing to be effective 2/8/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5060.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1164-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2020-03-04_SA 3438 Entergy
Arkansas-Long Lake Solar GIA (J834) to be effective 2/21/2020.
Filed Date: 3/4/20.
Accession Number: 20200304-5295.
Comments Due: 5 p.m. ET 3/25/20.
Docket Numbers: ER20-1167-000.
Applicants: Midcontinent Independent System Operator, Inc.,
Republic Transmission, LLC.
Description: Sec. 205(d) Rate Filing: 2020-03-04_Republic
Transmission Integration Filing to be effective 12/31/9998.
Filed Date: 3/4/20.
Accession Number: 20200304-5247.
Comments Due: 5 p.m. ET 3/25/20.
Docket Numbers: ER20-1168-000.
Applicants: DTE Big Turtle Wind Farm I, LLC.
Description: Sec. 205(d) Rate Filing: DTE Big Turtle Wind Farm I,
LLC Notice of Succession to be effective 1/15/2020.
[[Page 14192]]
Filed Date: 3/5/20.
Accession Number: 20200305-5056.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1169-000.
Applicants: The Dayton Power and Light Company, East Kentucky Power
Cooperative, Inc., PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: The Dayton Power and Light
Company submits IA SA No. 3137 to be effective 5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5070.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1170-000.
Applicants: Electric Energy, Inc.
Description: Tariff Cancellation: Cancellation Open Access
Transmission Tariff to be effective 3/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5072.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1171-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: First Revised ISA, SA No.
5231; Queue No. AC1-048/AC2-053/AE1-006 to be effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5078.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1172-000.
Applicants: Emera Maine.
Description: Tariff Cancellation: Notice of Termination of Expired
TSA--ReEnergy Ashland, LLC to be effective 2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5079.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1173-000.
Applicants: Emera Maine.
Description: Tariff Cancellation: Notice of Termination of Expired
Interconnect Agreement--ReEnergy Ashland, LP to be effective 2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5081.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1174-000.
Applicants: Midcontinent Independent System Operator, Inc., Otter
Tail Power Company.
Description: Sec. 205(d) Rate Filing: 2020-03-05_SA 3440 OTP-
Dakota Range III FSA (J488) BSP Switch Replacement to be effective 3/6/
2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5083.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1175-000.
Applicants: Midcontinent Independent System Operator, Inc., Otter
Tail Power Company.
Description: Sec. 205(d) Rate Filing: 2020-03-05_SA 3441 OTP-
Tatanka Ridge Wind FSA (J493) BSP Switch Replacement to be effective 3/
6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5089.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1176-000.
Applicants: Midcontinent Independent System Operator, Inc., Otter
Tail Power Company.
Description: Sec. 205(d) Rate Filing: 2020-03-05_SA 3342 OTP-Deuel
Harvest Wind FSA (J526) BSP Switch Replacement to be effective 3/6/
2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5091.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1177-000.
Applicants: Southern California Edison Company.
Description: Sec. 205(d) Rate Filing: Amended GIA and DSA San
Gorgonio Westwinds II, San Jacinto Power SA No. 863-864 to be effective
5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5112.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20-1178-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original ISA, SA No. 5596;
Queue No. AD1-020 to be effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305-5117.
Comments Due: 5 p.m. ET 3/26/20.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: March 5, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-04961 Filed 3-10-20; 8:45 am]
BILLING CODE 6717-01-P