Wisconsin Power and Light Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 14194-14195 [2020-04955]

Download as PDF 14194 Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices lotter on DSKBCFDHB2PROD with NOTICES Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207 (2019), LS Power Grid California, LLC (Petitioner), filed a petition for a declaratory order requesting that the Commission authorize specific rate incentives and treatments described for the Gates 500 kV Dynamic Reactive Support Project and Round Mountain 500 kV Area Dynamic Reactive Support Project, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern time on April 3, 2020. Dated: March 5, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–04954 Filed 3–10–20; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 16:37 Mar 10, 2020 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. P–11162–136] Wisconsin Power and Light Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Non-Capacity Amendment of License. b. Project No: P–11162–136. c. Date Filed: February 14, 2020. d. Applicant: Wisconsin Power and Light Company. e. Name of Project: Prairie du Sac Hydroelectric Project. f. Location: The project is located on the Wisconsin River in Sauk and Columbia counties, Wisconsin. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Amanda Blank, Wisconsin Power and Light Company, S9270A Dam Rd Prairie du Sac, WI 53558, (608) 458–6316, amandablank@ alliantenergy.com. i. FERC Contact: Aneela Mousam, (202) 502–8357, aneela.mousam@ ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: April 6, 2020. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–11162–136. k. Description of Request: Wisconsin Power and Light Company requests Commission approval for an amendment to the license for the Prairie du Sac Hydroelectric Project. The project is currently undergoing maintenance activities, which are increasing the efficiency of the facility. PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 During a recent internal compliance review, in preparation for maintenance activities, the licensee identified a discrepancy between the actual operating head and nameplate operating head due to drop in the tailwater elevation over the last 100 years. Therefore, the current authorized installed capacity of 27.3 MW needs to be amended to 31.4 MW, based on the actual operating head of 37.4 feet and calculated proposed capacity following turbine refurbishment. The turbines are being refurbished with in kind materials and will not change project operations. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits (P–11162) in the docket number field to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1– 866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the E:\FR\FM\11MRN1.SGM 11MRN1 14195 Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: March 5, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–04955 Filed 3–10–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness Of Exempt Wholesale Generator Status Jumbo Hill Wind Project, LLC East Fork Wind Project, LLC .. Wilton Wind Energy I, LLC .... [EG20–58–000] [EG20–59–000] [EG20–60–000] Take notice that during the month of February 2020, the status of the abovecaptioned entities as Exempt Wholesale Generators became effective by operation of the Commission’s regulations. 18 CFR 366.7(a) (2019). Dated: March 4, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–04962 Filed 3–10–20; 8:45 am] BILLING CODE 6717–01–P FOR FURTHER INFORMATION CONTACT: ENVIRONMENTAL PROTECTION AGENCY [FRL–10006–45–Region 3] Clean Water Act: Virginia—Sarah Creek and Perrin River Vessel Sewage No-Discharge Zone—Tentative Affirmative Determination Environmental Protection Agency (EPA). ACTION: Notice of tentative affirmative determination. AGENCY: Notice is hereby given that an application for a no-discharge zone has been received from the Secretary of Natural Resources on behalf of the Commonwealth of Virginia requesting a determination by the Regional Administrator, U.S. Environmental Protection Agency (EPA) Mid-Atlantic Region, that adequate facilities for the safe and sanitary removal and treatment of sewage from all vessels are reasonably available for the Sarah Creek and Perrin River, Gloucester County, Virginia. The EPA is requesting comments on this application and whether the EPA should finalize its tentative affirmative determination or make a negative determination on the proposed designation for Sarah Creek and Perrin River as provided in the Clean Water Act. The application is available upon request from the EPA (at the email address below) or at https:// www.deq.virginia.gov/Programs/Water/ WaterQualityInformationTMDLs/TMDL/ NoDischargeZoneDesignations.aspx. SUMMARY: Comments must be received in writing to the EPA on or before April 10, 2020. ADDRESSES: Comments should be sent to Matthew A. Konfirst, U.S. Environmental Protection Agency— Mid-Atlantic Region, 1650 Arch Street, Mail Code 3WD31, Philadelphia, PA 19103–2029, or emailed to konfirst.matthew@epa.gov. Only written comments will be considered. DATES: Matthew A. Konfirst, U.S. Environmental Protection Agency— Mid-Atlantic Region. Telephone: (215) 814–5801, Fax number: (215) 814–5007; email address: konfirst.matthew@ epa.gov. The delineation of the proposed nodischarge zone of Sarah Creek from York River will begin at 37°14′58.34″ N, 76°29′39.17″ W and extend to 37°15′00.81″ N, 76°28′37.84″ W. From there it will continue north throughout any navigable waters including all tributaries and bays. The delineation of the proposed no-discharge zone of Perrin River from York River will begin at 37°15′47.18″ N, 76°25′20.73″ W and extend to 37°15′50.63″ N, 76°25′11.84″ W. From there it will continue north throughout any navigable waters including all tributaries and bays. Based on the boater population in Sarah Creek and Perrin River, EPA guidance recommends one pumpout facility for each waterbody. The Commonwealth of Virginia has certified that there are three stationary and one mobile pumpout facilities at two locations on Sarah Creek and one stationary pumpout facility on Perrin River. Two of the three locations also have a method to empty portable toilets. Furthermore, the Hampton Roads Sanitation District (HRSD) provides free portable pumpout service in Gloucester County on Fridays, Saturdays and Sundays during summer months and on Saturdays the rest of the year. HRSD prefers to service marinas but will provide the portable pumpout at a private residence when requested. The Virginia Department of Health (VDH) ensures that proper sanitary facilities are present at marinas, and marina facilities are inspected annually by VDH for compliance with regulations. A list of the facilities, phone numbers, locations and hours of operation follows. SUPPLEMENTARY INFORMATION: lotter on DSKBCFDHB2PROD with NOTICES LIST OF FACILITIES WITH PUMPOUTS IN THE PROPOSED NO-DISCHARGE ZONE Mean low water depth (ft) Pumpout facility Operating hours York River Yacht Haven (Sarah Creek). Dockside Condominiums (Sarah Creek). Crown Pointe Marina (Perrin River). 24/7 .................................................................... VerDate Sep<11>2014 16:37 Mar 10, 2020 Phone No. Address 8 804–642–2156 24/7—April 1–November 15 .............................. 6 757–876–1568 The pump-out is available 24/7 from March 1– November 30 (so it is available even if the other marina services are closed). Dec 1– Feb 28 pump-out is winterized 5 804–642–6177 8109 Yacht Haven Road, Gloucester Point, VA 23062. Sunset Drive, Gloucester Point, VA 23062. 9737 Cooks Landing Road, Hayes, VA 23072. Jkt 250001 PO 00000 Frm 00012 Fmt 4703 Sfmt 4703 E:\FR\FM\11MRN1.SGM 11MRN1

Agencies

[Federal Register Volume 85, Number 48 (Wednesday, March 11, 2020)]
[Notices]
[Pages 14194-14195]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04955]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. P-11162-136]


Wisconsin Power and Light Company; Notice of Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Non-Capacity Amendment of License.
    b. Project No: P-11162-136.
    c. Date Filed: February 14, 2020.
    d. Applicant: Wisconsin Power and Light Company.
    e. Name of Project: Prairie du Sac Hydroelectric Project.
    f. Location: The project is located on the Wisconsin River in Sauk 
and Columbia counties, Wisconsin.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Amanda Blank, Wisconsin Power and Light 
Company, S9270A Dam Rd Prairie du Sac, WI 53558, (608) 458-6316, 
[email protected].
    i. FERC Contact: Aneela Mousam, (202) 502-8357, 
[email protected].
    j. Deadline for filing comments, motions to intervene, and 
protests: April 6, 2020.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, or recommendations using the 
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-11162-136.
    k. Description of Request: Wisconsin Power and Light Company 
requests Commission approval for an amendment to the license for the 
Prairie du Sac Hydroelectric Project. The project is currently 
undergoing maintenance activities, which are increasing the efficiency 
of the facility. During a recent internal compliance review, in 
preparation for maintenance activities, the licensee identified a 
discrepancy between the actual operating head and nameplate operating 
head due to drop in the tailwater elevation over the last 100 years. 
Therefore, the current authorized installed capacity of 27.3 MW needs 
to be amended to 31.4 MW, based on the actual operating head of 37.4 
feet and calculated proposed capacity following turbine refurbishment. 
The turbines are being refurbished with in kind materials and will not 
change project operations.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 
20426, or by calling (202) 502-8371. This filing may also be viewed on 
the Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits (P-11162) 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above. Agencies may obtain copies of the application directly from 
the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the

[[Page 14195]]

application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person commenting, protesting or 
intervening; and (4) otherwise comply with the requirements of 18 CFR 
385.2001 through 385.2005. All comments, motions to intervene, or 
protests must set forth their evidentiary basis. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 385.2010.

    Dated: March 5, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-04955 Filed 3-10-20; 8:45 am]