Liberty Power Holdings LLC v. Eversource Energy Service Company and ISO New England, Inc.; Notice of Complaint, 14193 [2020-04900]
Download as PDF
lotter on DSKBCFDHB2PROD with NOTICES
Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices
l. Description of Request: The licensee
is proposing to surrender its exemption.
The project operated until 2018 when
significant repairs necessitated an
extended outage until now. SSWD
evaluated repair along with future
operations and maintenance costs for
the project, and concluded that the
project is no longer economical,
especially since the power purchase
contract with Pacific Gas and Electric
expired on October 14, 2019. The
facilities would remain in place, except
for the turbine-generator units which
would be removed.
m. This filing may be viewed on the
Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction in the Commission’s
Public Reference Room located at 888
First Street NE, Room 2A, Washington,
DC 20426, or by calling (202) 502–8371.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .212
and .214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
p. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
VerDate Sep<11>2014
16:37 Mar 10, 2020
Jkt 250001
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to the surrender
application that is the subject of this
notice. Agencies may obtain copies of
the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
q. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the described proceeding.
If any agency does not file comments
within the time specified for filing
comments, it will be presumed to have
no comments.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04899 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL20–27–000]
Liberty Power Holdings LLC v.
Eversource Energy Service Company
and ISO New England, Inc.; Notice of
Complaint
Take notice that on February 28, 2020,
pursuant to section 206 of the Federal
Power Act (FPA), 16 U.S.C. 824e, and
Rule 206 of the Federal Energy
Regulatory Commission’s (Commission)
Rules of Practice and Procedure, 18 CFR
385.206, Liberty Power Holdings LLC
(Liberty or Complainant) filed a formal
complaint against Eversource Energy
Service Company (Eversource) and ISO
New England, Inc. (ISO–NE or
collectively Respondents), seeking
compensation for improperly calculated
and billed charges relating to load that
was not the responsibility of Liberty
during November of 2018 in violation of
PO 00000
Frm 00010
Fmt 4703
Sfmt 4703
14193
the FPA and the ISO–NE Tariff, all as
more fully explained in the complaint.
The Complainant certifies that copies
of the complaint were served on the
contacts listed for Respondents in the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondents’ answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondents’ answer, motions to
intervene, and protests must be served
on the Complainant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on March 19, 2020.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04900 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL20–29–000]
LS Power Grid California, LLC; Notice
of Petition for Declaratory Order
Take notice that on March 4, 2020,
pursuant to Rule 207 of the Federal
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 85, Number 48 (Wednesday, March 11, 2020)]
[Notices]
[Page 14193]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04900]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL20-27-000]
Liberty Power Holdings LLC v. Eversource Energy Service Company
and ISO New England, Inc.; Notice of Complaint
Take notice that on February 28, 2020, pursuant to section 206 of
the Federal Power Act (FPA), 16 U.S.C. 824e, and Rule 206 of the
Federal Energy Regulatory Commission's (Commission) Rules of Practice
and Procedure, 18 CFR 385.206, Liberty Power Holdings LLC (Liberty or
Complainant) filed a formal complaint against Eversource Energy Service
Company (Eversource) and ISO New England, Inc. (ISO-NE or collectively
Respondents), seeking compensation for improperly calculated and billed
charges relating to load that was not the responsibility of Liberty
during November of 2018 in violation of the FPA and the ISO-NE Tariff,
all as more fully explained in the complaint.
The Complainant certifies that copies of the complaint were served
on the contacts listed for Respondents in the Commission's list of
Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondents'
answer and all interventions, or protests must be filed on or before
the comment date. The Respondents' answer, motions to intervene, and
protests must be served on the Complainant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for electronic review in the
Commission's Public Reference Room in Washington, DC. There is an
``eSubscription'' link on the website that enables subscribers to
receive email notification when a document is added to a subscribed
docket(s). For assistance with any FERC Online service, please email
[email protected], or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on March 19, 2020.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-04900 Filed 3-10-20; 8:45 am]