South Sutter Water District; Notice of Application for Surrender of Conduit Exemption, Soliciting Comments, Motions To Intervene, and Protests, 14192-14193 [2020-04899]
Download as PDF
lotter on DSKBCFDHB2PROD with NOTICES
14192
Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices
Filed Date: 3/5/20.
Accession Number: 20200305–5056.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1169–000.
Applicants: The Dayton Power and
Light Company, East Kentucky Power
Cooperative, Inc., PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: The
Dayton Power and Light Company
submits IA SA No. 3137 to be effective
5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5070.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1170–000.
Applicants: Electric Energy, Inc.
Description: Tariff Cancellation:
Cancellation Open Access Transmission
Tariff to be effective 3/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5072.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1171–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: First
Revised ISA, SA No. 5231; Queue No.
AC1–048/AC2–053/AE1–006 to be
effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5078.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1172–000.
Applicants: Emera Maine.
Description: Tariff Cancellation:
Notice of Termination of Expired TSA—
ReEnergy Ashland, LLC to be effective
2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5079.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1173–000.
Applicants: Emera Maine.
Description: Tariff Cancellation:
Notice of Termination of Expired
Interconnect Agreement—ReEnergy
Ashland, LP to be effective 2/28/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5081.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1174–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3440 OTP-Dakota
Range III FSA (J488) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5083.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1175–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3441 OTP-Tatanka
VerDate Sep<11>2014
16:37 Mar 10, 2020
Jkt 250001
Ridge Wind FSA (J493) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5089.
Comments Due: 5 p.m. ET 3/26/20.
DEPARTMENT OF ENERGY
Docket Numbers: ER20–1176–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2020–03–05_SA 3342 OTP-Deuel
Harvest Wind FSA (J526) BSP Switch
Replacement to be effective 3/6/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5091.
Comments Due: 5 p.m. ET 3/26/20.
South Sutter Water District; Notice of
Application for Surrender of Conduit
Exemption, Soliciting Comments,
Motions To Intervene, and Protests
Docket Numbers: ER20–1177–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
Amended GIA and DSA San Gorgonio
Westwinds II, San Jacinto Power SA No.
863–864 to be effective 5/5/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5112.
Comments Due: 5 p.m. ET 3/26/20.
Docket Numbers: ER20–1178–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5596; Queue No.
AD1–020 to be effective 2/4/2020.
Filed Date: 3/5/20.
Accession Number: 20200305–5117.
Comments Due: 5 p.m. ET 3/26/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 5, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–04961 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00009
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Project No. 7580–003]
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Proceeding: Application for
surrender of conduit exemption from
licensing.
b. Project No.: 7580–003.
c. Date Filed: December 31, 2019.
d. Exemptee: South Sutter Water
District (SSWD).
e. Name of Project: Vanjop No. 1
Hydroelectric Project.
f. Location: The project is located on
SSWD’s Conveyance Canal which is
part of SSWD’s water delivery system
near Sheridan in Placer County,
California.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Licensee Contact: Brad Arnold,
General Manager, South Suter Water
District, 2464 Pacific Avenue,
Trowbridge, CA 95659, (530) 656–2242
sswd@hughes.net.
i. FERC Contact: Kim Nguyen, (202)
502–6105, Kim.Nguyen@ferc.gov.
j. Deadline for filing comments,
interventions, and protests is April 3,
2020. The Commission strongly
encourages electronic filing. Please file
motions to intervene, protests and
comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–7580–003.
k. Description of Project Facilities:
The project consists of a radial gate, a
bypass gate, an intake structure, a catch
basin, a discharge structure, three
turbine-generator units with total
generating capacity of 415 kilowatts,
and a short transmission line.
E:\FR\FM\11MRN1.SGM
11MRN1
lotter on DSKBCFDHB2PROD with NOTICES
Federal Register / Vol. 85, No. 48 / Wednesday, March 11, 2020 / Notices
l. Description of Request: The licensee
is proposing to surrender its exemption.
The project operated until 2018 when
significant repairs necessitated an
extended outage until now. SSWD
evaluated repair along with future
operations and maintenance costs for
the project, and concluded that the
project is no longer economical,
especially since the power purchase
contract with Pacific Gas and Electric
expired on October 14, 2019. The
facilities would remain in place, except
for the turbine-generator units which
would be removed.
m. This filing may be viewed on the
Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction in the Commission’s
Public Reference Room located at 888
First Street NE, Room 2A, Washington,
DC 20426, or by calling (202) 502–8371.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .212
and .214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
p. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
VerDate Sep<11>2014
16:37 Mar 10, 2020
Jkt 250001
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to the surrender
application that is the subject of this
notice. Agencies may obtain copies of
the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
q. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the described proceeding.
If any agency does not file comments
within the time specified for filing
comments, it will be presumed to have
no comments.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04899 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL20–27–000]
Liberty Power Holdings LLC v.
Eversource Energy Service Company
and ISO New England, Inc.; Notice of
Complaint
Take notice that on February 28, 2020,
pursuant to section 206 of the Federal
Power Act (FPA), 16 U.S.C. 824e, and
Rule 206 of the Federal Energy
Regulatory Commission’s (Commission)
Rules of Practice and Procedure, 18 CFR
385.206, Liberty Power Holdings LLC
(Liberty or Complainant) filed a formal
complaint against Eversource Energy
Service Company (Eversource) and ISO
New England, Inc. (ISO–NE or
collectively Respondents), seeking
compensation for improperly calculated
and billed charges relating to load that
was not the responsibility of Liberty
during November of 2018 in violation of
PO 00000
Frm 00010
Fmt 4703
Sfmt 4703
14193
the FPA and the ISO–NE Tariff, all as
more fully explained in the complaint.
The Complainant certifies that copies
of the complaint were served on the
contacts listed for Respondents in the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondents’ answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondents’ answer, motions to
intervene, and protests must be served
on the Complainant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on March 19, 2020.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04900 Filed 3–10–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL20–29–000]
LS Power Grid California, LLC; Notice
of Petition for Declaratory Order
Take notice that on March 4, 2020,
pursuant to Rule 207 of the Federal
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 85, Number 48 (Wednesday, March 11, 2020)]
[Notices]
[Pages 14192-14193]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04899]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 7580-003]
South Sutter Water District; Notice of Application for Surrender
of Conduit Exemption, Soliciting Comments, Motions To Intervene, and
Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Proceeding: Application for surrender of conduit
exemption from licensing.
b. Project No.: 7580-003.
c. Date Filed: December 31, 2019.
d. Exemptee: South Sutter Water District (SSWD).
e. Name of Project: Vanjop No. 1 Hydroelectric Project.
f. Location: The project is located on SSWD's Conveyance Canal
which is part of SSWD's water delivery system near Sheridan in Placer
County, California.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Licensee Contact: Brad Arnold, General Manager, South Suter
Water District, 2464 Pacific Avenue, Trowbridge, CA 95659, (530) 656-
2242 [email protected].
i. FERC Contact: Kim Nguyen, (202) 502-6105, [email protected].
j. Deadline for filing comments, interventions, and protests is
April 3, 2020. The Commission strongly encourages electronic filing.
Please file motions to intervene, protests and comments using the
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426. The first page of any filing should include
docket number P-7580-003.
k. Description of Project Facilities: The project consists of a
radial gate, a bypass gate, an intake structure, a catch basin, a
discharge structure, three turbine-generator units with total
generating capacity of 415 kilowatts, and a short transmission line.
[[Page 14193]]
l. Description of Request: The licensee is proposing to surrender
its exemption. The project operated until 2018 when significant repairs
necessitated an extended outage until now. SSWD evaluated repair along
with future operations and maintenance costs for the project, and
concluded that the project is no longer economical, especially since
the power purchase contract with Pacific Gas and Electric expired on
October 14, 2019. The facilities would remain in place, except for the
turbine-generator units which would be removed.
m. This filing may be viewed on the Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number
excluding the last three digits in the docket number field to access
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and
issuances related to this or other pending projects. For assistance,
call 1-866-208-3676 or email [email protected], for TTY, call
(202) 502-8659. A copy is also available for inspection and
reproduction in the Commission's Public Reference Room located at 888
First Street NE, Room 2A, Washington, DC 20426, or by calling (202)
502-8371.
n. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
o. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.212 and .214. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
p. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis and otherwise comply with the requirements of 18 CFR
4.34(b). All comments, motions to intervene, or protests should relate
to the surrender application that is the subject of this notice.
Agencies may obtain copies of the application directly from the
applicant. A copy of any protest or motion to intervene must be served
upon each representative of the applicant specified in the particular
application. If an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
q. Agency Comments--Federal, state, and local agencies are invited
to file comments on the described proceeding. If any agency does not
file comments within the time specified for filing comments, it will be
presumed to have no comments.
Dated: March 4, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-04899 Filed 3-10-20; 8:45 am]