Federal Register / Vol. 85, No. 46 / Monday, March 9, 2020 / Notices
5. Vote on Inv. Nos. 701–TA–618–619
and 731–TA–1441–1442 (Final) (Carbon
and Alloy Steel Threaded Rod from
China and India). The Commission is
currently scheduled to complete and file
its determinations and views of the
Commission by April 3, 2020.
6. Outstanding action jackets: None.
CONTACT PERSON FOR MORE INFORMATION:
William Bishop, Supervisory Hearings
and Information Officer, 202–205–2595.
The Commission is holding the
meeting under the Government in the
Sunshine Act, 5 U.S.C. 552(b). In
accordance with Commission policy,
subject matter listed above, not disposed
of at the scheduled meeting, may be
carried over to the agenda of the
following meeting.
By order of the Commission.
Issued: March 4, 2020.
William Bishop,
Supervisory Hearings and Information
Officer.
BILLING CODE 7020–02–P
INTERNATIONAL TRADE
COMMISSION
[USITC SE–20–009]
Sunshine Act Meetings
United
States International Trade Commission.
TIME AND DATE: March 17, 2020 at 11:00
a.m.
PLACE: Room 101, 500 E Street SW,
Washington, DC 20436, Telephone:
(202) 205–2000.
STATUS: Open to the public.
MATTERS TO BE CONSIDERED:
1. Agendas for future meetings: None.
2. Minutes.
3. Ratification List.
4. Vote on Inv. Nos. 731–TA–1435–
1436 and 1439 (Final) (Acetone from
Belgium, Korea, and South Africa). The
Commission is currently scheduled to
complete and file its determinations and
views of the Commission by March 30,
2020.
5. Outstanding action jackets: None.
CONTACT PERSON FOR MORE INFORMATION:
William Bishop, Supervisory Hearings
and Information Officer, 202–205–2595.
The Commission is holding the
meeting under the Government in the
Sunshine Act, 5 U.S.C. 552(b). In
accordance with Commission policy,
subject matter listed above, not disposed
of at the scheduled meeting, may be
carried over to the agenda of the
following meeting.
jbell on DSKJLSW7X2PROD with NOTICES
By order of the Commission.
VerDate Sep<11>2014
17:47 Mar 06, 2020
Jkt 250001
[FR Doc. 2020–04792 Filed 3–5–20; 11:15 am]
BILLING CODE 7020–02–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–247 and 50–286; NRC–
2020–0045]
Entergy Nuclear Operations, Inc.;
Indian Point Nuclear Generating Unit
Nos. 2 and 3
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to an April 15,
2019 request from Entergy Nuclear
Operations, Inc. (Entergy, the licensee).
The exemption allows a certified fuel
handler, in addition to a licensed senior
operator, to suspend security measures
in an emergency or during severe
weather for Indian Point Nuclear
Generating Unit Nos. 2 and 3 (Indian
Point 2 and 3) after both the
‘‘Certification of Permanent Cessation of
Operations’’ and the ‘‘Certification of
Permanent Fuel Removal’’ have been
docketed for that respective unit.
DATES: The exemption was issued on
February 28, 2020.
ADDRESSES: Please refer to Docket ID
NRC–2020–0045 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2020–0045. Address
questions about NRC docket IDs in
Regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
SUMMARY:
[FR Doc. 2020–04791 Filed 3–5–20; 11:15 am]
AGENCY HOLDING THE MEETING:
Issued: March 4, 2020.
William Bishop,
Supervisory Hearings and Information
Officer.
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
13673
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Richard V. Guzman, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
1030, email: Richard.Guzman@nrc.gov.
SUPPLEMENTARY INFORMATION: The text of
the exemption is attached.
Dated at Rockville, Maryland, this 3rd day
of March, 2020.
For the Nuclear Regulatory Commission.
Richard V. Guzman,
Senior Project Manager, Plant Licensing
Branch I, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
Attachment—Exemption
NUCLEAR REGULATORY
COMMISSION
Docket Nos. 50–247 and 50–286
Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Unit
Nos. 2 and 3
Exemption Related to the Approval
Authority for Suspension of Security
Measures in an Emergency or During
Severe Weather
I. Background
Entergy Nuclear Operations, Inc.
(Entergy, the licensee) is the holder of
Renewed Facility Operating License
Nos. DPR–26 and DPR–64 for Indian
Point Nuclear Generating Units Nos. 2
and 3 (Indian Point 2 and 3). The
licenses provide, among other things,
that the facility is subject to all rules,
regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC,
the Commission), now or hereafter in
effect. The Indian Point 2 and 3 facility
consists of two pressurized-water
reactors located in Buchanan, New
York.
By letter dated February 8, 2017
(Agencywide Documents Access and
Management System (ADAMS)
Accession No. ML17044A004), the
licensee submitted a Notification of
Permanent Cessation of Power
Operations for Indian Point 2 and 3. In
this letter, Entergy provided notification
to the NRC of its intent to permanently
cease power operations at Indian Point
2 and 3 no later than April 30, 2020, and
April 30, 2021, respectively, subject to
E:\FR\FM\09MRN1.SGM
09MRN1
13674
Federal Register / Vol. 85, No. 46 / Monday, March 9, 2020 / Notices
operating extensions through, but not
beyond, 2024 and 2025, respectively.
In accordance with title 10 of the
Code of Federal Regulations (10 CFR)
Sections 50.82(a)(1)(i) and (ii) and
50.82(a)(2), upon the docketing of the
certifications for permanent cessation of
operations and the permanent removal
of fuel from the reactor vessel, the 10
CFR part 50 license no longer authorizes
reactor operation or emplacement or
retention of fuel in the reactor vessel. As
a result, licensed senior operators (i.e.,
individuals licensed under 10 CFR part
55 to manipulate the controls of a
facility and to direct the licensed
activities of licensed operators) will no
longer be required to support plant
operating activities. Instead, certified
fuel handlers (CFHs) (i.e., non-licensed
operators who have qualified in
accordance with a fuel handler training
program approved by the Commission)
will perform activities associated with
decommissioning and irradiated fuel
handling and management. Commission
approval of a fuel handler training
program is needed to facilitate these
activities.
By letter dated April 15, 2019
(ADAMS Accession No. ML19105A632),
Entergy submitted a request for
Commission approval of the CFH
Training and Retraining Program for
Indian Point 2 and 3. By letter dated
December 18, 2019 (ADAMS Accession
No. ML19333B868), the Commission
approved the CFH Training and
Retraining Program for Indian Point 2
and 3. The CFH Training and Retraining
Program is to be used to satisfy training
requirements for the plant personnel
responsible for supervising and
directing the monitoring, storage,
handling, and cooling of irradiated fuel
in a manner consistent with ensuring
the health and safety of the public. As
stated in 10 CFR 50.2, ‘‘Definitions,’’
CFHs are qualified in accordance with
a Commission-approved training
program.
II. Request/Action
jbell on DSKJLSW7X2PROD with NOTICES
The Commission’s regulations at 10
CFR 73.55(p)(1) address the suspension
of security measures in an emergency
(10 CFR 73.55(p)(1)(i)) or during severe
weather (10 CFR 73.55(p)(1)(ii)):
The licensee may suspend implementation
of affected requirements of this section under
the following conditions:
(i) In accordance with §§ 50.54(x) and
50.54(y) of this chapter, the licensee may
suspend any security measures under this
section in an emergency when this action is
immediately needed to protect the public
health and safety and no action consistent
with license conditions and technical
specifications that can provide adequate or
VerDate Sep<11>2014
17:47 Mar 06, 2020
Jkt 250001
equivalent protection is immediately
apparent. This suspension of security
measures must be approved as a minimum by
a licensed senior operator before taking this
action.
(ii) During severe weather when the
suspension of affected security measures is
immediately needed to protect the personal
health and safety of security force personnel
and no other immediately apparent action
consistent with the license conditions and
technical specifications can provide adequate
or equivalent protection. This suspension of
security measures must be approved, as a
minimum, by a licensed senior operator, with
input from the security supervisor or
manager, before taking this action.
By letter dated April 15, 2019
(ADAMS Accession No. ML19105B237),
the licensee requested an exemption
from 10 CFR 73.55(p)(1)(i) and (ii),
pursuant to 10 CFR 73.5, ‘‘Specific
exemptions.’’ Consistent with 10 CFR
50.54(y), Entergy intends to have a CFH,
in addition to a licensed senior operator,
approve the suspension of security
measures in an emergency or during
severe weather at Indian Point 2 and 3.
III. Discussion
The NRC’s security rules have long
recognized the potential need to
suspend security or safeguards measures
under certain conditions. Accordingly,
10 CFR 50.54(x) and (y), first published
in 1983, allow a licensee to take
reasonable actions in an emergency that
depart from license conditions or
technical specifications when those
actions are immediately ‘‘needed to
protect the public health and safety,’’
and no actions consistent with license
conditions and technical specifications
that can provide adequate or equivalent
protection are immediately apparent (48
FR 13970; April 1, 1983). As originally
issued, the departure from license
conditions or technical specifications
must be approved, as a minimum, by a
licensed senior operator. In 1986, in its
final rule, ‘‘Miscellaneous Amendments
Concerning the Physical Protection of
Nuclear Power Plants’’ (51 FR 27821;
August 4, 1986), the Commission issued
10 CFR 73.55(a), stating in part:
In accordance with § [§ ] 50.54 (x) and (y)
of Part 50, the licensee may suspend any
safeguards measures pursuant to § 73.55 in
an emergency when this action is
immediately needed to protect the public
health and safety and no action consistent
with license conditions and technical
specification that can provide adequate or
equivalent protection is immediately
apparent. This suspension must be approved
as a minimum by a licensed senior operator
prior to taking the action.
In 1996, the NRC made a number of
regulatory changes to address
decommissioning. One of the changes
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
was to amend 10 CFR 50.54(x) and (y)
to authorize a non-licensed operator
called a ‘‘certified fuel handler,’’ in
addition to a licensed senior operator, to
approve such protective actions in an
emergency situation at a permanently
shutdown facility. Specifically, in
addressing the role of the CFH during
emergencies, the Commission stated in
the proposed rule, ‘‘Decommissioning of
Nuclear Power Reactors’’ (60 FR 37379;
July 20, 1995):
The Commission is proposing to amend 10
CFR 50.54(y) to permit a certified fuel
handler at nuclear power reactors that have
permanently ceased operations and
permanently removed fuel from the reactor
vessel, subject to the requirements of
§ 50.82(a) and consistent with the proposed
definition of ‘‘Certified Fuel Handler’’
specified in § 50.2, to make these evaluations
and judgments. A nuclear power reactor that
has permanently ceased operations and no
longer has fuel in the reactor vessel does not
require a licensed individual to monitor core
conditions. A certified fuel handler at a
permanently shutdown and defueled nuclear
power reactor undergoing decommissioning
is an individual who has the requisite
knowledge and experience to evaluate plant
conditions and make these judgments.
In the final rule (61 FR 39298; July 29,
1996), the NRC added the following
definition to 10 CFR 50.2: ‘‘Certified fuel
handler means, for a nuclear power
reactor facility, a non-licensed operator
who has qualified in accordance with a
fuel handler training program approved
by the Commission.’’ However, the
decommissioning rule did not propose
or make parallel changes to 10 CFR
73.55(a), and did not discuss the role of
a non-licensed CFH at a permanently
shutdown facility.
In the final rule, ‘‘Power Reactor
Security Requirements’’ (74 FR 13926;
March 27, 2009), the NRC relocated the
security suspension requirements from
10 CFR 73.55(a) to 10 CFR 73.55(p)(1)(i)
and (ii). The role of a CFH was not
discussed in the rulemaking; therefore,
the suspension of security measures in
accordance with 10 CFR 73.55(p)
continues to require approval, as a
minimum, by a licensed senior operator,
even for a permanently shutdown
facility.
Under 10 CFR 73.5, the Commission
may, upon application of any interested
person or upon its own initiative, grant
exemptions from the requirements of 10
CFR part 73 as it determines are
authorized by law, will not endanger
life or property or the common defense
and security, and are otherwise in the
public interest. As explained below, the
proposed exemption is authorized by
law, will not endanger life or property
or the common defense and security,
and is otherwise in the public interest.
E:\FR\FM\09MRN1.SGM
09MRN1
Federal Register / Vol. 85, No. 46 / Monday, March 9, 2020 / Notices
A. The Exemption is Authorized by Law
The proposed exemption from 10 CFR
73.55(p)(1)(i) and (ii) would remove the
requirement that a licensed senior
operator at Indian Point 2 and 3 approve
the suspension of security measures
under certain emergency conditions or
severe weather. The licensee intends to
use the authority of a non-licensed CFH,
in addition to a licensed senior operator,
to approve the suspension of security
measures in an emergency or during
severe weather. Although the exemption
is effective upon receipt, the exemption
may not be implemented at Indian Point
2 and 3 until the respective 10 CFR part
50 license no longer authorizes
operation of the reactor or the
emplacement or retention of fuel in the
reactor vessel in accordance with 10
CFR 50.82(a)(2).
Per 10 CFR 73.5, the NRC may grant
specific exemptions from the
requirements of 10 CFR part 73.
Granting the proposed exemption is
consistent with the Atomic Energy Act
of 1954, as amended, and not otherwise
inconsistent with NRC regulations or
other applicable laws. Therefore, the
exemption is authorized by law.
jbell on DSKJLSW7X2PROD with NOTICES
B. The Exemption Will Not Endanger
Life or Property or the Common Defense
and Security
The requested exemption would
permit a CFH, in addition to a licensed
senior operator, to approve the
suspension of security measures in an
emergency or during severe weather at
Indian Point 2 and 3 only when that
respective reactor is permanently shut
down and defueled. The NRC staff finds
that the exemption will not endanger
life or property or the common defense
and security for the reasons discussed
below.
First, 10 CFR 73.55(p)(2) will
continue to require that ‘‘[s]uspended
security measures must be reinstated as
soon as conditions permit.’’
Second, the suspension of security
measures for emergencies under 10 CFR
73.55(p)(1)(i) will continue to be
invoked only ‘‘when this action is
immediately needed to protect the
public health and safety and no action
consistent with license conditions and
technical specifications that can provide
adequate or equivalent protection is
immediately apparent.’’ Thus, the
exemption would not prevent the
licensee from meeting the underlying
purpose of 10 CFR 73.55(p)(1)(i) to
protect the public health and safety.
Third, the suspension of security
measures for severe weather under 10
CFR 73.55(p)(1)(ii) will continue to be
used only when ‘‘the suspension of
VerDate Sep<11>2014
17:47 Mar 06, 2020
Jkt 250001
affected security measures is
immediately needed to protect the
personal health and safety of security
force personnel and no other
immediately apparent action consistent
with the license conditions and
technical specifications can provide
adequate or equivalent protection.’’ The
requirement in 10 CFR 73.55(p)(1)(ii) to
receive input from the security
supervisor or manager will remain.
Therefore, the exemption would not
prevent the licensee from meeting the
underlying purpose of 10 CFR
73.55(p)(1)(ii) to protect the health and
safety of the security force.
Additionally, by letter dated
December 18, 2019 (ADAMS Accession
No. ML19333B868), the NRC approved
the Indian Point 2 and 3 CFH Training
and Retraining Program. The NRC staff
found that, among other things, the
program addresses the safe conduct of
decommissioning activities, the safe
handling and storage of spent fuel, and
the appropriate response to plant
emergencies. Because a CFH at Indian
Point 2 and 3 will be sufficiently trained
and qualified under an NRC-approved
program, the NRC staff considers the
CFH to have sufficient knowledge of
operational and safety concerns, such
that allowing the CFH to suspend
security measures in emergencies or
during severe weather will not result in
undue risk to the public health and
safety.
In addition, since the exemption
allows a CFH the same authority
currently given to the licensed senior
operator under 10 CFR 73.55(p)(1)(i)
and (ii), no change is required to
physical security. Since no change is
required to physical security, the
exemption would not reduce the overall
effectiveness of the Indian Point 2 and
3 physical security plan and would not
adversely impact the licensee’s ability to
physically secure the site or protect
special nuclear material at Indian Point
2 and 3, and thus, would not have an
adverse effect on the common defense
and security. The NRC staff has
determined that the exemption would
not reduce security measures currently
in place to protect against radiological
sabotage. Instead, the exemption would
align the requirements of 10 CFR
73.55(p)(1)(i) and (ii) with the existing
requirements of 10 CFR 50.54(y).
For these reasons, granting the
exemption from the requirements in 10
CFR 73.55(p)(1)(i) and (ii) and
permitting a CFH, in addition to a
licensed senior operator, to approve the
suspension of security measures in an
emergency or during severe weather at
Indian Point 2 and 3 when that
respective reactor is permanently shut
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
13675
down and defueled will not endanger
life or property or the common defense
and security.
C. The Exemption is Otherwise in the
Public Interest
The proposed exemption would allow
a CFH, in addition to a licensed senior
operator, to approve the suspension of
security measures in an emergency
when ‘‘immediately needed to protect
the public health and safety,’’ or during
severe weather events when
‘‘immediately needed to protect the
personal health and safety of security
force personnel’’ at Indian Point 2 and
3 when that respective reactor is
permanently shut down. If the
exemption is not granted, Indian Point
2 and 3 will be required to have a
licensed senior operator available to
approve the suspension of security
measures in an emergency or during
severe weather for a permanently
shutdown plant, even though there
would no longer be an NRC requirement
for Entergy to maintain a licensed senior
operator at Indian Point 2 and 3 after the
certifications required by 10 CFR
50.82(a)(1)(i) and (ii) are submitted
respective to each reactor.
This exemption is in the public
interest for the following reasons.
Without the exemption, there would be
uncertainty regarding how the licensee
will invoke the temporary suspension of
security measures that may be needed
for protecting the public health and
safety or the personal health and safety
of the security force personnel in
emergencies or during severe weather,
given the differences between the
requirements in 10 CFR 73.55(p)(1)(i)
and (ii), and 10 CFR 50.54(y). The
exemption would allow the licensee to
make decisions pursuant to 10 CFR
73.55(p)(1)(i) and (ii) without having to
maintain a staff of licensed senior
operators at a nuclear power reactor that
has permanently ceased operations and
permanently removed fuel from the
reactor vessel. The exemption would
also allow the licensee to have an
established procedure in place to allow
a CFH to suspend security measures in
an emergency or during severe weather
after the certifications required by 10
CFR 50.82(a)(1)(i) and (ii) have been
submitted. Finally, the consistent and
efficient regulation of nuclear power
plants serves the public interest, and
this exemption would ensure
consistency between the regulations in
10 CFR part 73 and 10 CFR 50.54(y) and
the requirements concerning licensed
operators in 10 CFR part 55.
The NRC staff has determined that
granting the proposed exemption would
allow the licensee to designate a CFH
E:\FR\FM\09MRN1.SGM
09MRN1
13676
Federal Register / Vol. 85, No. 46 / Monday, March 9, 2020 / Notices
jbell on DSKJLSW7X2PROD with NOTICES
with qualifications appropriate for a
permanently shutdown and defueled
reactor to approve the suspension of
security measures in an emergency to
protect the public health and safety and
during severe weather to protect the
personal health and safety of the
security force personnel. The actions
permitted by the exemption may be
implemented at each Indian Point 2 and
3 unit separately when both the
‘‘Certification of Permanent Cessation of
Operations’’ and the ‘‘Certification of
Permanent Fuel Removal’’ for that
respective reactor is submitted in
accordance with 10 CFR 50.82(a)(1)(i)
and (ii), which is consistent with the
similar authority provided by 10 CFR
50.54(y). Therefore, the exemption is in
the public interest.
D. Environmental Consideration
The NRC’s approval of the proposed
exemption belongs to a category of
actions that the Commission, by rule or
regulation, has declared to be a
categorical exclusion, after first finding
that the category of actions does not
individually or cumulatively have a
significant effect on the human
environment. Pursuant to 10 CFR
51.22(b), as determined by the
Commission, an environmental
assessment or an environmental impact
statement is not required for any action
within a category of actions included in
the list of categorical exclusions set out
in paragraph (c) of Section 51.22.
Specifically, the NRC’s approval of the
exemption is categorically excluded
from further environmental analysis
under 10 CFR 51.22(c)(25).
Under 10 CFR 51.22(c)(25), the
granting of an exemption from the
requirements of any regulation of
Chapter I to 10 CFR is a categorical
exclusion provided that: (i) There is no
significant hazards consideration; (ii)
there is no significant change in the
types or significant increase in the
amounts of any effluents that may be
released offsite; (iii) there is no
significant increase in individual or
cumulative public or occupational
radiation exposure; (iv) there is no
significant construction impact; (v)
there is no significant increase in the
potential for or consequences from
radiological accidents; and (vi) the
requirements from which an exemption
is sought involve: Recordkeeping
requirements; reporting requirements;
inspection or surveillance requirements;
equipment servicing or maintenance
scheduling requirements; education,
training, experience, qualification,
requalification or other employment
suitability requirements; safeguard
plans, and materials control and
VerDate Sep<11>2014
17:47 Mar 06, 2020
Jkt 250001
accounting inventory scheduling
requirements; scheduling requirements;
surety, insurance or indemnity
requirements; or other requirements of
an administrative, managerial, or
organizational nature.
The NRC staff has determined that
granting the proposed exemption
involves no significant hazards
consideration because allowing a CFH,
in addition to a licensed senior operator,
to approve the security suspension at a
permanently shutdown and defueled
power plant does not (1) involve a
significant increase in the probability or
consequences of an accident previously
evaluated, or (2) create the possibility of
a new or different kind of accident from
any accident previously evaluated, or
(3) involve a significant reduction in a
margin of safety. The proposed
exemption is unrelated to any
operational restriction. Accordingly,
there is no significant change in the
types or significant increase in the
amounts of any effluents that may be
released offsite and no significant
increase in individual or cumulative
public or occupational radiation
exposure. The proposed exemption is
not associated with construction, so
there is no significant construction
impact. The proposed exemption does
not concern the source term (i.e.,
potential amount of radiation in an
accident) or mitigation. Thus, there is
no significant increase in the potential
for or consequences from radiological
accidents. Finally, the requirement
regarding suspensions of security
measures involves either safeguards,
materials control, or managerial/
organizational matters.
Therefore, pursuant to 10 CFR
51.22(b) and (c)(25), no environmental
impact statement or environmental
assessment need be prepared in
connection with the approval of the
proposed exemption.
IV. Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
73.5, the exemption is authorized by
law, will not endanger life or property
or the common defense and security,
and is otherwise in the public interest.
Therefore, the Commission hereby
grants the licensee’s request for an
exemption from the requirements of 10
CFR 73.55(p)(1)(i) and (ii) to authorize
that the suspension of security measures
must be approved, as a minimum, by
either a licensed senior operator or a
CFH at Indian Point 2 and 3 during
emergency or severe weather, once the
respective unit’s certifications required
under 10 CFR 50.82(a)(1) have been
submitted.
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
Dated at Rockville, Maryland, this 28th day
of February, 2020.
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2020–04710 Filed 3–6–20; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. STN 50–528, STN 50–529, and
STN 50–530; NRC–2020–0069]
Arizona Public Service Company; Palo
Verde Nuclear Generating Station,
Units 1, 2, and 3
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to a July 6, 2018,
request, as supplemented by letters
dated October 18, 2018; March 1, 2019;
May 17, 2019; October 4, 2019;
November 26, 2019; and December 19,
2019, from Arizona Public Service
Company (the licensee) in order to use
Framatome M5® alloy as a fuel rod
cladding material at Palo Verde Nuclear
Generating Station, Units 1, 2, and 3.
DATES: The exemption was issued on
March 4, 2020.
ADDRESSES: Please refer to Docket ID
NRC–2020–0069 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2020–0069. Address
questions about NRC docket IDs in
Regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced in this
SUMMARY:
E:\FR\FM\09MRN1.SGM
09MRN1
Agencies
[Federal Register Volume 85, Number 46 (Monday, March 9, 2020)]
[Notices]
[Pages 13673-13676]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04710]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-247 and 50-286; NRC-2020-0045]
Entergy Nuclear Operations, Inc.; Indian Point Nuclear Generating
Unit Nos. 2 and 3
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to an April 15, 2019 request from Entergy Nuclear
Operations, Inc. (Entergy, the licensee). The exemption allows a
certified fuel handler, in addition to a licensed senior operator, to
suspend security measures in an emergency or during severe weather for
Indian Point Nuclear Generating Unit Nos. 2 and 3 (Indian Point 2 and
3) after both the ``Certification of Permanent Cessation of
Operations'' and the ``Certification of Permanent Fuel Removal'' have
been docketed for that respective unit.
DATES: The exemption was issued on February 28, 2020.
ADDRESSES: Please refer to Docket ID NRC-2020-0045 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2020-0045. Address
questions about NRC docket IDs in Regulations.gov to Jennifer Borges;
telephone: 301-287-9127; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Richard V. Guzman, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-1030, email: [email protected].
SUPPLEMENTARY INFORMATION: The text of the exemption is attached.
Dated at Rockville, Maryland, this 3rd day of March, 2020.
For the Nuclear Regulatory Commission.
Richard V. Guzman,
Senior Project Manager, Plant Licensing Branch I, Division of Operating
Reactor Licensing, Office of Nuclear Reactor Regulation.
Attachment--Exemption
NUCLEAR REGULATORY COMMISSION
Docket Nos. 50-247 and 50-286
Entergy Nuclear Operations, Inc.
Indian Point Nuclear Generating Unit Nos. 2 and 3
Exemption Related to the Approval Authority for Suspension of Security
Measures in an Emergency or During Severe Weather
I. Background
Entergy Nuclear Operations, Inc. (Entergy, the licensee) is the
holder of Renewed Facility Operating License Nos. DPR-26 and DPR-64 for
Indian Point Nuclear Generating Units Nos. 2 and 3 (Indian Point 2 and
3). The licenses provide, among other things, that the facility is
subject to all rules, regulations, and orders of the U.S. Nuclear
Regulatory Commission (NRC, the Commission), now or hereafter in
effect. The Indian Point 2 and 3 facility consists of two pressurized-
water reactors located in Buchanan, New York.
By letter dated February 8, 2017 (Agencywide Documents Access and
Management System (ADAMS) Accession No. ML17044A004), the licensee
submitted a Notification of Permanent Cessation of Power Operations for
Indian Point 2 and 3. In this letter, Entergy provided notification to
the NRC of its intent to permanently cease power operations at Indian
Point 2 and 3 no later than April 30, 2020, and April 30, 2021,
respectively, subject to
[[Page 13674]]
operating extensions through, but not beyond, 2024 and 2025,
respectively.
In accordance with title 10 of the Code of Federal Regulations (10
CFR) Sections 50.82(a)(1)(i) and (ii) and 50.82(a)(2), upon the
docketing of the certifications for permanent cessation of operations
and the permanent removal of fuel from the reactor vessel, the 10 CFR
part 50 license no longer authorizes reactor operation or emplacement
or retention of fuel in the reactor vessel. As a result, licensed
senior operators (i.e., individuals licensed under 10 CFR part 55 to
manipulate the controls of a facility and to direct the licensed
activities of licensed operators) will no longer be required to support
plant operating activities. Instead, certified fuel handlers (CFHs)
(i.e., non-licensed operators who have qualified in accordance with a
fuel handler training program approved by the Commission) will perform
activities associated with decommissioning and irradiated fuel handling
and management. Commission approval of a fuel handler training program
is needed to facilitate these activities.
By letter dated April 15, 2019 (ADAMS Accession No. ML19105A632),
Entergy submitted a request for Commission approval of the CFH Training
and Retraining Program for Indian Point 2 and 3. By letter dated
December 18, 2019 (ADAMS Accession No. ML19333B868), the Commission
approved the CFH Training and Retraining Program for Indian Point 2 and
3. The CFH Training and Retraining Program is to be used to satisfy
training requirements for the plant personnel responsible for
supervising and directing the monitoring, storage, handling, and
cooling of irradiated fuel in a manner consistent with ensuring the
health and safety of the public. As stated in 10 CFR 50.2,
``Definitions,'' CFHs are qualified in accordance with a Commission-
approved training program.
II. Request/Action
The Commission's regulations at 10 CFR 73.55(p)(1) address the
suspension of security measures in an emergency (10 CFR 73.55(p)(1)(i))
or during severe weather (10 CFR 73.55(p)(1)(ii)):
The licensee may suspend implementation of affected requirements
of this section under the following conditions:
(i) In accordance with Sec. Sec. 50.54(x) and 50.54(y) of this
chapter, the licensee may suspend any security measures under this
section in an emergency when this action is immediately needed to
protect the public health and safety and no action consistent with
license conditions and technical specifications that can provide
adequate or equivalent protection is immediately apparent. This
suspension of security measures must be approved as a minimum by a
licensed senior operator before taking this action.
(ii) During severe weather when the suspension of affected
security measures is immediately needed to protect the personal
health and safety of security force personnel and no other
immediately apparent action consistent with the license conditions
and technical specifications can provide adequate or equivalent
protection. This suspension of security measures must be approved,
as a minimum, by a licensed senior operator, with input from the
security supervisor or manager, before taking this action.
By letter dated April 15, 2019 (ADAMS Accession No. ML19105B237),
the licensee requested an exemption from 10 CFR 73.55(p)(1)(i) and
(ii), pursuant to 10 CFR 73.5, ``Specific exemptions.'' Consistent with
10 CFR 50.54(y), Entergy intends to have a CFH, in addition to a
licensed senior operator, approve the suspension of security measures
in an emergency or during severe weather at Indian Point 2 and 3.
III. Discussion
The NRC's security rules have long recognized the potential need to
suspend security or safeguards measures under certain conditions.
Accordingly, 10 CFR 50.54(x) and (y), first published in 1983, allow a
licensee to take reasonable actions in an emergency that depart from
license conditions or technical specifications when those actions are
immediately ``needed to protect the public health and safety,'' and no
actions consistent with license conditions and technical specifications
that can provide adequate or equivalent protection are immediately
apparent (48 FR 13970; April 1, 1983). As originally issued, the
departure from license conditions or technical specifications must be
approved, as a minimum, by a licensed senior operator. In 1986, in its
final rule, ``Miscellaneous Amendments Concerning the Physical
Protection of Nuclear Power Plants'' (51 FR 27821; August 4, 1986), the
Commission issued 10 CFR 73.55(a), stating in part:
In accordance with Sec. [Sec. ] 50.54 (x) and (y) of Part 50,
the licensee may suspend any safeguards measures pursuant to Sec.
73.55 in an emergency when this action is immediately needed to
protect the public health and safety and no action consistent with
license conditions and technical specification that can provide
adequate or equivalent protection is immediately apparent. This
suspension must be approved as a minimum by a licensed senior
operator prior to taking the action.
In 1996, the NRC made a number of regulatory changes to address
decommissioning. One of the changes was to amend 10 CFR 50.54(x) and
(y) to authorize a non-licensed operator called a ``certified fuel
handler,'' in addition to a licensed senior operator, to approve such
protective actions in an emergency situation at a permanently shutdown
facility. Specifically, in addressing the role of the CFH during
emergencies, the Commission stated in the proposed rule,
``Decommissioning of Nuclear Power Reactors'' (60 FR 37379; July 20,
1995):
The Commission is proposing to amend 10 CFR 50.54(y) to permit a
certified fuel handler at nuclear power reactors that have
permanently ceased operations and permanently removed fuel from the
reactor vessel, subject to the requirements of Sec. 50.82(a) and
consistent with the proposed definition of ``Certified Fuel
Handler'' specified in Sec. 50.2, to make these evaluations and
judgments. A nuclear power reactor that has permanently ceased
operations and no longer has fuel in the reactor vessel does not
require a licensed individual to monitor core conditions. A
certified fuel handler at a permanently shutdown and defueled
nuclear power reactor undergoing decommissioning is an individual
who has the requisite knowledge and experience to evaluate plant
conditions and make these judgments.
In the final rule (61 FR 39298; July 29, 1996), the NRC added the
following definition to 10 CFR 50.2: ``Certified fuel handler means,
for a nuclear power reactor facility, a non-licensed operator who has
qualified in accordance with a fuel handler training program approved
by the Commission.'' However, the decommissioning rule did not propose
or make parallel changes to 10 CFR 73.55(a), and did not discuss the
role of a non-licensed CFH at a permanently shutdown facility.
In the final rule, ``Power Reactor Security Requirements'' (74 FR
13926; March 27, 2009), the NRC relocated the security suspension
requirements from 10 CFR 73.55(a) to 10 CFR 73.55(p)(1)(i) and (ii).
The role of a CFH was not discussed in the rulemaking; therefore, the
suspension of security measures in accordance with 10 CFR 73.55(p)
continues to require approval, as a minimum, by a licensed senior
operator, even for a permanently shutdown facility.
Under 10 CFR 73.5, the Commission may, upon application of any
interested person or upon its own initiative, grant exemptions from the
requirements of 10 CFR part 73 as it determines are authorized by law,
will not endanger life or property or the common defense and security,
and are otherwise in the public interest. As explained below, the
proposed exemption is authorized by law, will not endanger life or
property or the common defense and security, and is otherwise in the
public interest.
[[Page 13675]]
A. The Exemption is Authorized by Law
The proposed exemption from 10 CFR 73.55(p)(1)(i) and (ii) would
remove the requirement that a licensed senior operator at Indian Point
2 and 3 approve the suspension of security measures under certain
emergency conditions or severe weather. The licensee intends to use the
authority of a non-licensed CFH, in addition to a licensed senior
operator, to approve the suspension of security measures in an
emergency or during severe weather. Although the exemption is effective
upon receipt, the exemption may not be implemented at Indian Point 2
and 3 until the respective 10 CFR part 50 license no longer authorizes
operation of the reactor or the emplacement or retention of fuel in the
reactor vessel in accordance with 10 CFR 50.82(a)(2).
Per 10 CFR 73.5, the NRC may grant specific exemptions from the
requirements of 10 CFR part 73. Granting the proposed exemption is
consistent with the Atomic Energy Act of 1954, as amended, and not
otherwise inconsistent with NRC regulations or other applicable laws.
Therefore, the exemption is authorized by law.
B. The Exemption Will Not Endanger Life or Property or the Common
Defense and Security
The requested exemption would permit a CFH, in addition to a
licensed senior operator, to approve the suspension of security
measures in an emergency or during severe weather at Indian Point 2 and
3 only when that respective reactor is permanently shut down and
defueled. The NRC staff finds that the exemption will not endanger life
or property or the common defense and security for the reasons
discussed below.
First, 10 CFR 73.55(p)(2) will continue to require that
``[s]uspended security measures must be reinstated as soon as
conditions permit.''
Second, the suspension of security measures for emergencies under
10 CFR 73.55(p)(1)(i) will continue to be invoked only ``when this
action is immediately needed to protect the public health and safety
and no action consistent with license conditions and technical
specifications that can provide adequate or equivalent protection is
immediately apparent.'' Thus, the exemption would not prevent the
licensee from meeting the underlying purpose of 10 CFR 73.55(p)(1)(i)
to protect the public health and safety.
Third, the suspension of security measures for severe weather under
10 CFR 73.55(p)(1)(ii) will continue to be used only when ``the
suspension of affected security measures is immediately needed to
protect the personal health and safety of security force personnel and
no other immediately apparent action consistent with the license
conditions and technical specifications can provide adequate or
equivalent protection.'' The requirement in 10 CFR 73.55(p)(1)(ii) to
receive input from the security supervisor or manager will remain.
Therefore, the exemption would not prevent the licensee from meeting
the underlying purpose of 10 CFR 73.55(p)(1)(ii) to protect the health
and safety of the security force.
Additionally, by letter dated December 18, 2019 (ADAMS Accession
No. ML19333B868), the NRC approved the Indian Point 2 and 3 CFH
Training and Retraining Program. The NRC staff found that, among other
things, the program addresses the safe conduct of decommissioning
activities, the safe handling and storage of spent fuel, and the
appropriate response to plant emergencies. Because a CFH at Indian
Point 2 and 3 will be sufficiently trained and qualified under an NRC-
approved program, the NRC staff considers the CFH to have sufficient
knowledge of operational and safety concerns, such that allowing the
CFH to suspend security measures in emergencies or during severe
weather will not result in undue risk to the public health and safety.
In addition, since the exemption allows a CFH the same authority
currently given to the licensed senior operator under 10 CFR
73.55(p)(1)(i) and (ii), no change is required to physical security.
Since no change is required to physical security, the exemption would
not reduce the overall effectiveness of the Indian Point 2 and 3
physical security plan and would not adversely impact the licensee's
ability to physically secure the site or protect special nuclear
material at Indian Point 2 and 3, and thus, would not have an adverse
effect on the common defense and security. The NRC staff has determined
that the exemption would not reduce security measures currently in
place to protect against radiological sabotage. Instead, the exemption
would align the requirements of 10 CFR 73.55(p)(1)(i) and (ii) with the
existing requirements of 10 CFR 50.54(y).
For these reasons, granting the exemption from the requirements in
10 CFR 73.55(p)(1)(i) and (ii) and permitting a CFH, in addition to a
licensed senior operator, to approve the suspension of security
measures in an emergency or during severe weather at Indian Point 2 and
3 when that respective reactor is permanently shut down and defueled
will not endanger life or property or the common defense and security.
C. The Exemption is Otherwise in the Public Interest
The proposed exemption would allow a CFH, in addition to a licensed
senior operator, to approve the suspension of security measures in an
emergency when ``immediately needed to protect the public health and
safety,'' or during severe weather events when ``immediately needed to
protect the personal health and safety of security force personnel'' at
Indian Point 2 and 3 when that respective reactor is permanently shut
down. If the exemption is not granted, Indian Point 2 and 3 will be
required to have a licensed senior operator available to approve the
suspension of security measures in an emergency or during severe
weather for a permanently shutdown plant, even though there would no
longer be an NRC requirement for Entergy to maintain a licensed senior
operator at Indian Point 2 and 3 after the certifications required by
10 CFR 50.82(a)(1)(i) and (ii) are submitted respective to each
reactor.
This exemption is in the public interest for the following reasons.
Without the exemption, there would be uncertainty regarding how the
licensee will invoke the temporary suspension of security measures that
may be needed for protecting the public health and safety or the
personal health and safety of the security force personnel in
emergencies or during severe weather, given the differences between the
requirements in 10 CFR 73.55(p)(1)(i) and (ii), and 10 CFR 50.54(y).
The exemption would allow the licensee to make decisions pursuant to 10
CFR 73.55(p)(1)(i) and (ii) without having to maintain a staff of
licensed senior operators at a nuclear power reactor that has
permanently ceased operations and permanently removed fuel from the
reactor vessel. The exemption would also allow the licensee to have an
established procedure in place to allow a CFH to suspend security
measures in an emergency or during severe weather after the
certifications required by 10 CFR 50.82(a)(1)(i) and (ii) have been
submitted. Finally, the consistent and efficient regulation of nuclear
power plants serves the public interest, and this exemption would
ensure consistency between the regulations in 10 CFR part 73 and 10 CFR
50.54(y) and the requirements concerning licensed operators in 10 CFR
part 55.
The NRC staff has determined that granting the proposed exemption
would allow the licensee to designate a CFH
[[Page 13676]]
with qualifications appropriate for a permanently shutdown and defueled
reactor to approve the suspension of security measures in an emergency
to protect the public health and safety and during severe weather to
protect the personal health and safety of the security force personnel.
The actions permitted by the exemption may be implemented at each
Indian Point 2 and 3 unit separately when both the ``Certification of
Permanent Cessation of Operations'' and the ``Certification of
Permanent Fuel Removal'' for that respective reactor is submitted in
accordance with 10 CFR 50.82(a)(1)(i) and (ii), which is consistent
with the similar authority provided by 10 CFR 50.54(y). Therefore, the
exemption is in the public interest.
D. Environmental Consideration
The NRC's approval of the proposed exemption belongs to a category
of actions that the Commission, by rule or regulation, has declared to
be a categorical exclusion, after first finding that the category of
actions does not individually or cumulatively have a significant effect
on the human environment. Pursuant to 10 CFR 51.22(b), as determined by
the Commission, an environmental assessment or an environmental impact
statement is not required for any action within a category of actions
included in the list of categorical exclusions set out in paragraph (c)
of Section 51.22. Specifically, the NRC's approval of the exemption is
categorically excluded from further environmental analysis under 10 CFR
51.22(c)(25).
Under 10 CFR 51.22(c)(25), the granting of an exemption from the
requirements of any regulation of Chapter I to 10 CFR is a categorical
exclusion provided that: (i) There is no significant hazards
consideration; (ii) there is no significant change in the types or
significant increase in the amounts of any effluents that may be
released offsite; (iii) there is no significant increase in individual
or cumulative public or occupational radiation exposure; (iv) there is
no significant construction impact; (v) there is no significant
increase in the potential for or consequences from radiological
accidents; and (vi) the requirements from which an exemption is sought
involve: Recordkeeping requirements; reporting requirements; inspection
or surveillance requirements; equipment servicing or maintenance
scheduling requirements; education, training, experience,
qualification, requalification or other employment suitability
requirements; safeguard plans, and materials control and accounting
inventory scheduling requirements; scheduling requirements; surety,
insurance or indemnity requirements; or other requirements of an
administrative, managerial, or organizational nature.
The NRC staff has determined that granting the proposed exemption
involves no significant hazards consideration because allowing a CFH,
in addition to a licensed senior operator, to approve the security
suspension at a permanently shutdown and defueled power plant does not
(1) involve a significant increase in the probability or consequences
of an accident previously evaluated, or (2) create the possibility of a
new or different kind of accident from any accident previously
evaluated, or (3) involve a significant reduction in a margin of
safety. The proposed exemption is unrelated to any operational
restriction. Accordingly, there is no significant change in the types
or significant increase in the amounts of any effluents that may be
released offsite and no significant increase in individual or
cumulative public or occupational radiation exposure. The proposed
exemption is not associated with construction, so there is no
significant construction impact. The proposed exemption does not
concern the source term (i.e., potential amount of radiation in an
accident) or mitigation. Thus, there is no significant increase in the
potential for or consequences from radiological accidents. Finally, the
requirement regarding suspensions of security measures involves either
safeguards, materials control, or managerial/organizational matters.
Therefore, pursuant to 10 CFR 51.22(b) and (c)(25), no
environmental impact statement or environmental assessment need be
prepared in connection with the approval of the proposed exemption.
IV. Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
73.5, the exemption is authorized by law, will not endanger life or
property or the common defense and security, and is otherwise in the
public interest. Therefore, the Commission hereby grants the licensee's
request for an exemption from the requirements of 10 CFR 73.55(p)(1)(i)
and (ii) to authorize that the suspension of security measures must be
approved, as a minimum, by either a licensed senior operator or a CFH
at Indian Point 2 and 3 during emergency or severe weather, once the
respective unit's certifications required under 10 CFR 50.82(a)(1) have
been submitted.
Dated at Rockville, Maryland, this 28th day of February, 2020.
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. 2020-04710 Filed 3-6-20; 8:45 am]