WBI Energy Transmission, Inc.; Notice of Application, 12549-12550 [2020-04321]
Download as PDF
Federal Register / Vol. 85, No. 42 / Tuesday, March 3, 2020 / Notices
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–3452–017.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is ready for environmental analysis
at this time.
l. The Oak Orchard Project consists of
the following existing facilities: (1) A
concrete gravity dam containing a
spillway with a crest elevation of 507.6
feet mean sea level (msl) surmounted by
2-foot-high flashboards and two 5-foothigh, 5-foot-wide flood gates; (2) a
forebay with a surface area of 0.25 acre
and a storage capacity of 3 acre-feet at
the normal pool elevation of 509.6 feet
msl; (3) an intake structure with
trashracks; (4) a 7-foot-diameter, 85-footlong welded steel penstock from the
intake to the turbine; (5) a 20-foot-long,
43-foot-wide powerhouse containing a
single turbine-generator unit with a
rated capacity of 350 kilowatts; (6) a
tailrace located on the left (west) bank
of Oak Orchard Creek; (7) a 55-foot-long
underground generation lead; (8) three
single-phase 167-kilovolt-ampere polemounted power transformers; (9) a 400foot-long access road; and (10)
appurtenant facilities.
Erie operates the project off of flows
provided to it from the barge canal.
During the navigation season, the Canal
Corporation provides approximately 225
cubic feet per second (cfs) of water.
Under normal operating conditions, Erie
uses approximately 200 cfs of the
provided water for project operation and
the remaining water (approximately 25
cfs) is discharged directly to Oak
Orchard Creek. During the period from
2009 to 2016, the average annual
generation was approximately 1,147
megawatt-hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title COMMENTS, REPLY
COMMENTS, RECOMMENDATIONS,
TERMS AND CONDITIONS, or
PRESCRIPTIONS; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestone
Target date
Deadline for filing comments, recommendations, terms and conditions, and prescriptions ...................................................
Reply comments due ...............................................................................................................................................................
Commission issues EA ............................................................................................................................................................
Comments on EA due .............................................................................................................................................................
Dated: February 26, 2020.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
[FR Doc. 2020–04322 Filed 3–2–20; 8:45 am]
lotter on DSKBCFDHB2PROD with NOTICES
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[Docket Nos. CP20–52–000; PF19–7–000]
WBI Energy Transmission, Inc.; Notice
of Application
Take notice that on February 14, 2020,
WBI Energy Transmission, Inc. (WBI),
1250 West Century Avenue, Bismarck,
North Dakota 58503, filed in the above
VerDate Sep<11>2014
17:19 Mar 02, 2020
Jkt 250001
PO 00000
Frm 00056
Fmt 4703
12549
Sfmt 4703
April 2020.
June 2020.
September 2020.
October 2020.
referenced docket an application
pursuant to section 7(c) of the Natural
Gas Act, requesting authorization to
construct, modify, operate, and
maintain the North Bakken Expansion
Project located in northwestern North
Dakota, all as more fully described in
the application which is on file with the
Commission and open to public
inspection.
The filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
E:\FR\FM\03MRN1.SGM
03MRN1
lotter on DSKBCFDHB2PROD with NOTICES
12550
Federal Register / Vol. 85, No. 42 / Tuesday, March 3, 2020 / Notices
Commission’s website web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Specifically, WBI proposes to: (i)
Construct approximately 61.9 miles of
new 24-inch-diameter natural gas
pipeline from WBI Energy’s Tioga
Compressor Station in Williams County,
North Dakota to the proposed Elkhorn
Creek Compressor Station in McKenzie
County, North Dakota; (ii) construct
approximately 0.3 mile of new 24-inchdiameter natural gas pipeline from the
proposed Elkhorn Creek Compressor
Station to a new interconnect with
Northern Border Pipeline Company in
McKenzie County; (iii) construct
approximately 20.4 miles of new 12inch-diameter natural gas pipeline loop
along WBI Energy’s Line Section 25 in
Mountrail and Burke Counties, North
Dakota; (iv) construct approximately 9.4
miles of new 12-inch-diameter natural
gas pipeline loop along WBI Energy’s
Line Section 30 in Williams County; (v)
construct approximately 0.5 mile of new
20-inch-diameter receipt lateral to the
Tioga Compressor Station; (vi) uprate
Line Section 25; (vii) install an
additional 22,500 hp at the Tioga
Compressor Station; (viii) construct a
new compressor station totaling 3,750
hp, the Elkhorn Creek Compressor
Station, in McKenzie County; and (ix)
install new, and modify, existing
delivery, receipt, and transfer stations
along the pipeline routes, replace small
segments of pipeline facilities and
install block valves, pig launcher/
receiver stations and other associated
appurtenances.
WBI says that the project will allow
it to provide an additional 350 MMcf/
d of incremental firm transportation
capacity from the Williston Basin in
northwest North Dakota to a new
interconnect with Northern Border’s
existing mainline. WBI estimates the
cost of the project to be $300 million.
Any questions regarding this
application should be directed Lori
Myerchin, Director, Regulatory Affairs
and Transportation Services, WBI
Energy Transmission, Inc., 1250 West
Century Avenue, Bismarck, North
Dakota 58503, by telephone at (701)
530–1563 or by email at lori.myerchin@
wbienergy.com.
On July 3, 2019, Commission staff
granted WBI’s request to utilize the PreFiling Process and assigned Docket No.
PF19–7–000 to staff activities involved
in the project. Now, as of the filing of
VerDate Sep<11>2014
17:19 Mar 02, 2020
Jkt 250001
this application on February 14, 2020,
the Pre-Filing Process for this project
has ended. From this time forward, this
proceeding will be conducted in CP20–
52–000, as noted in the caption of this
Notice.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
3 copies of filings made in the
proceeding with the Commission and
must provide a copy to the applicant
and to every other party. Only parties to
the proceeding can ask for court review
of Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
PO 00000
Frm 00057
Fmt 4703
Sfmt 9990
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
As of the February 27, 2018 date of
the Commission’s order in Docket No.
CP16–4–001, the Commission will
apply its revised practice concerning
out-of-time motions to intervene in any
new Natural Gas Act section 3 or section
7 proceeding.1 Persons desiring to
become a party to a certificate
proceeding are to intervene in a timely
manner. If seeking to intervene out-oftime, the movant is required to show
good cause why the time limitation
should be waived, and should provide
justification by reference to factors set
forth in Rule 214(d)(1) of the
Commission’s Rules and Regulations.2
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
Comment Date: 5:00 p.m. Eastern
Time on March 18, 2020.
Dated: February 26, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–04321 Filed 3–2–20; 8:45 am]
BILLING CODE 6717–01–P
1 Tennessee Gas Pipeline Company, L.L.C., 162
FERC 61,167 at 50 (2018).
2 18 CFR 385.214(d)(1).
E:\FR\FM\03MRN1.SGM
03MRN1
Agencies
[Federal Register Volume 85, Number 42 (Tuesday, March 3, 2020)]
[Notices]
[Pages 12549-12550]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04321]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP20-52-000; PF19-7-000]
WBI Energy Transmission, Inc.; Notice of Application
Take notice that on February 14, 2020, WBI Energy Transmission,
Inc. (WBI), 1250 West Century Avenue, Bismarck, North Dakota 58503,
filed in the above referenced docket an application pursuant to section
7(c) of the Natural Gas Act, requesting authorization to construct,
modify, operate, and maintain the North Bakken Expansion Project
located in northwestern North Dakota, all as more fully described in
the application which is on file with the Commission and open to public
inspection.
The filing is available for review at the Commission in the Public
Reference Room or may be viewed on the
[[Page 12550]]
Commission's website web at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC at [email protected] or call toll-free, (866) 208-3676 or
TTY, (202) 502-8659.
Specifically, WBI proposes to: (i) Construct approximately 61.9
miles of new 24-inch-diameter natural gas pipeline from WBI Energy's
Tioga Compressor Station in Williams County, North Dakota to the
proposed Elkhorn Creek Compressor Station in McKenzie County, North
Dakota; (ii) construct approximately 0.3 mile of new 24-inch-diameter
natural gas pipeline from the proposed Elkhorn Creek Compressor Station
to a new interconnect with Northern Border Pipeline Company in McKenzie
County; (iii) construct approximately 20.4 miles of new 12-inch-
diameter natural gas pipeline loop along WBI Energy's Line Section 25
in Mountrail and Burke Counties, North Dakota; (iv) construct
approximately 9.4 miles of new 12-inch-diameter natural gas pipeline
loop along WBI Energy's Line Section 30 in Williams County; (v)
construct approximately 0.5 mile of new 20-inch-diameter receipt
lateral to the Tioga Compressor Station; (vi) uprate Line Section 25;
(vii) install an additional 22,500 hp at the Tioga Compressor Station;
(viii) construct a new compressor station totaling 3,750 hp, the
Elkhorn Creek Compressor Station, in McKenzie County; and (ix) install
new, and modify, existing delivery, receipt, and transfer stations
along the pipeline routes, replace small segments of pipeline
facilities and install block valves, pig launcher/receiver stations and
other associated appurtenances.
WBI says that the project will allow it to provide an additional
350 MMcf/d of incremental firm transportation capacity from the
Williston Basin in northwest North Dakota to a new interconnect with
Northern Border's existing mainline. WBI estimates the cost of the
project to be $300 million.
Any questions regarding this application should be directed Lori
Myerchin, Director, Regulatory Affairs and Transportation Services, WBI
Energy Transmission, Inc., 1250 West Century Avenue, Bismarck, North
Dakota 58503, by telephone at (701) 530-1563 or by email at
[email protected].
On July 3, 2019, Commission staff granted WBI's request to utilize
the Pre-Filing Process and assigned Docket No. PF19-7-000 to staff
activities involved in the project. Now, as of the filing of this
application on February 14, 2020, the Pre-Filing Process for this
project has ended. From this time forward, this proceeding will be
conducted in CP20-52-000, as noted in the caption of this Notice.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 3 copies of filings made in the proceeding with the Commission
and must provide a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list and will be
notified of any meetings associated with the Commission's environmental
review process. Environmental commenters will not be required to serve
copies of filed documents on all other parties. However, the non-party
commenters will not receive copies of all documents filed by other
parties or issued by the Commission and will not have the right to seek
court review of the Commission's final order.
As of the February 27, 2018 date of the Commission's order in
Docket No. CP16-4-001, the Commission will apply its revised practice
concerning out-of-time motions to intervene in any new Natural Gas Act
section 3 or section 7 proceeding.\1\ Persons desiring to become a
party to a certificate proceeding are to intervene in a timely manner.
If seeking to intervene out-of-time, the movant is required to show
good cause why the time limitation should be waived, and should provide
justification by reference to factors set forth in Rule 214(d)(1) of
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------
\1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at
50 (2018).
\2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original and 3 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Comment Date: 5:00 p.m. Eastern Time on March 18, 2020.
Dated: February 26, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-04321 Filed 3-2-20; 8:45 am]
BILLING CODE 6717-01-P