WBI Energy Transmission, Inc.; Notice of Application, 12549-12550 [2020-04321]

Download as PDF Federal Register / Vol. 85, No. 42 / Tuesday, March 3, 2020 / Notices j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–3452–017. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is ready for environmental analysis at this time. l. The Oak Orchard Project consists of the following existing facilities: (1) A concrete gravity dam containing a spillway with a crest elevation of 507.6 feet mean sea level (msl) surmounted by 2-foot-high flashboards and two 5-foothigh, 5-foot-wide flood gates; (2) a forebay with a surface area of 0.25 acre and a storage capacity of 3 acre-feet at the normal pool elevation of 509.6 feet msl; (3) an intake structure with trashracks; (4) a 7-foot-diameter, 85-footlong welded steel penstock from the intake to the turbine; (5) a 20-foot-long, 43-foot-wide powerhouse containing a single turbine-generator unit with a rated capacity of 350 kilowatts; (6) a tailrace located on the left (west) bank of Oak Orchard Creek; (7) a 55-foot-long underground generation lead; (8) three single-phase 167-kilovolt-ampere polemounted power transformers; (9) a 400foot-long access road; and (10) appurtenant facilities. Erie operates the project off of flows provided to it from the barge canal. During the navigation season, the Canal Corporation provides approximately 225 cubic feet per second (cfs) of water. Under normal operating conditions, Erie uses approximately 200 cfs of the provided water for project operation and the remaining water (approximately 25 cfs) is discharged directly to Oak Orchard Creek. During the period from 2009 to 2016, the average annual generation was approximately 1,147 megawatt-hours. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. All filings must (1) bear in all capital letters the title COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Deadline for filing comments, recommendations, terms and conditions, and prescriptions ................................................... Reply comments due ............................................................................................................................................................... Commission issues EA ............................................................................................................................................................ Comments on EA due ............................................................................................................................................................. Dated: February 26, 2020. Kimberly D. Bose, Secretary. DEPARTMENT OF ENERGY [FR Doc. 2020–04322 Filed 3–2–20; 8:45 am] lotter on DSKBCFDHB2PROD with NOTICES BILLING CODE 6717–01–P Federal Energy Regulatory Commission [Docket Nos. CP20–52–000; PF19–7–000] WBI Energy Transmission, Inc.; Notice of Application Take notice that on February 14, 2020, WBI Energy Transmission, Inc. (WBI), 1250 West Century Avenue, Bismarck, North Dakota 58503, filed in the above VerDate Sep<11>2014 17:19 Mar 02, 2020 Jkt 250001 PO 00000 Frm 00056 Fmt 4703 12549 Sfmt 4703 April 2020. June 2020. September 2020. October 2020. referenced docket an application pursuant to section 7(c) of the Natural Gas Act, requesting authorization to construct, modify, operate, and maintain the North Bakken Expansion Project located in northwestern North Dakota, all as more fully described in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the E:\FR\FM\03MRN1.SGM 03MRN1 lotter on DSKBCFDHB2PROD with NOTICES 12550 Federal Register / Vol. 85, No. 42 / Tuesday, March 3, 2020 / Notices Commission’s website web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Specifically, WBI proposes to: (i) Construct approximately 61.9 miles of new 24-inch-diameter natural gas pipeline from WBI Energy’s Tioga Compressor Station in Williams County, North Dakota to the proposed Elkhorn Creek Compressor Station in McKenzie County, North Dakota; (ii) construct approximately 0.3 mile of new 24-inchdiameter natural gas pipeline from the proposed Elkhorn Creek Compressor Station to a new interconnect with Northern Border Pipeline Company in McKenzie County; (iii) construct approximately 20.4 miles of new 12inch-diameter natural gas pipeline loop along WBI Energy’s Line Section 25 in Mountrail and Burke Counties, North Dakota; (iv) construct approximately 9.4 miles of new 12-inch-diameter natural gas pipeline loop along WBI Energy’s Line Section 30 in Williams County; (v) construct approximately 0.5 mile of new 20-inch-diameter receipt lateral to the Tioga Compressor Station; (vi) uprate Line Section 25; (vii) install an additional 22,500 hp at the Tioga Compressor Station; (viii) construct a new compressor station totaling 3,750 hp, the Elkhorn Creek Compressor Station, in McKenzie County; and (ix) install new, and modify, existing delivery, receipt, and transfer stations along the pipeline routes, replace small segments of pipeline facilities and install block valves, pig launcher/ receiver stations and other associated appurtenances. WBI says that the project will allow it to provide an additional 350 MMcf/ d of incremental firm transportation capacity from the Williston Basin in northwest North Dakota to a new interconnect with Northern Border’s existing mainline. WBI estimates the cost of the project to be $300 million. Any questions regarding this application should be directed Lori Myerchin, Director, Regulatory Affairs and Transportation Services, WBI Energy Transmission, Inc., 1250 West Century Avenue, Bismarck, North Dakota 58503, by telephone at (701) 530–1563 or by email at lori.myerchin@ wbienergy.com. On July 3, 2019, Commission staff granted WBI’s request to utilize the PreFiling Process and assigned Docket No. PF19–7–000 to staff activities involved in the project. Now, as of the filing of VerDate Sep<11>2014 17:19 Mar 02, 2020 Jkt 250001 this application on February 14, 2020, the Pre-Filing Process for this project has ended. From this time forward, this proceeding will be conducted in CP20– 52–000, as noted in the caption of this Notice. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 3 copies of filings made in the proceeding with the Commission and must provide a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party PO 00000 Frm 00057 Fmt 4703 Sfmt 9990 to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. As of the February 27, 2018 date of the Commission’s order in Docket No. CP16–4–001, the Commission will apply its revised practice concerning out-of-time motions to intervene in any new Natural Gas Act section 3 or section 7 proceeding.1 Persons desiring to become a party to a certificate proceeding are to intervene in a timely manner. If seeking to intervene out-oftime, the movant is required to show good cause why the time limitation should be waived, and should provide justification by reference to factors set forth in Rule 214(d)(1) of the Commission’s Rules and Regulations.2 The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on March 18, 2020. Dated: February 26, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–04321 Filed 3–2–20; 8:45 am] BILLING CODE 6717–01–P 1 Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at 50 (2018). 2 18 CFR 385.214(d)(1). E:\FR\FM\03MRN1.SGM 03MRN1

Agencies

[Federal Register Volume 85, Number 42 (Tuesday, March 3, 2020)]
[Notices]
[Pages 12549-12550]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-04321]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP20-52-000; PF19-7-000]


WBI Energy Transmission, Inc.; Notice of Application

    Take notice that on February 14, 2020, WBI Energy Transmission, 
Inc. (WBI), 1250 West Century Avenue, Bismarck, North Dakota 58503, 
filed in the above referenced docket an application pursuant to section 
7(c) of the Natural Gas Act, requesting authorization to construct, 
modify, operate, and maintain the North Bakken Expansion Project 
located in northwestern North Dakota, all as more fully described in 
the application which is on file with the Commission and open to public 
inspection.
    The filing is available for review at the Commission in the Public 
Reference Room or may be viewed on the

[[Page 12550]]

Commission's website web at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC at [email protected] or call toll-free, (866) 208-3676 or 
TTY, (202) 502-8659.
    Specifically, WBI proposes to: (i) Construct approximately 61.9 
miles of new 24-inch-diameter natural gas pipeline from WBI Energy's 
Tioga Compressor Station in Williams County, North Dakota to the 
proposed Elkhorn Creek Compressor Station in McKenzie County, North 
Dakota; (ii) construct approximately 0.3 mile of new 24-inch-diameter 
natural gas pipeline from the proposed Elkhorn Creek Compressor Station 
to a new interconnect with Northern Border Pipeline Company in McKenzie 
County; (iii) construct approximately 20.4 miles of new 12-inch-
diameter natural gas pipeline loop along WBI Energy's Line Section 25 
in Mountrail and Burke Counties, North Dakota; (iv) construct 
approximately 9.4 miles of new 12-inch-diameter natural gas pipeline 
loop along WBI Energy's Line Section 30 in Williams County; (v) 
construct approximately 0.5 mile of new 20-inch-diameter receipt 
lateral to the Tioga Compressor Station; (vi) uprate Line Section 25; 
(vii) install an additional 22,500 hp at the Tioga Compressor Station; 
(viii) construct a new compressor station totaling 3,750 hp, the 
Elkhorn Creek Compressor Station, in McKenzie County; and (ix) install 
new, and modify, existing delivery, receipt, and transfer stations 
along the pipeline routes, replace small segments of pipeline 
facilities and install block valves, pig launcher/receiver stations and 
other associated appurtenances.
    WBI says that the project will allow it to provide an additional 
350 MMcf/d of incremental firm transportation capacity from the 
Williston Basin in northwest North Dakota to a new interconnect with 
Northern Border's existing mainline. WBI estimates the cost of the 
project to be $300 million.
    Any questions regarding this application should be directed Lori 
Myerchin, Director, Regulatory Affairs and Transportation Services, WBI 
Energy Transmission, Inc., 1250 West Century Avenue, Bismarck, North 
Dakota 58503, by telephone at (701) 530-1563 or by email at 
[email protected].
    On July 3, 2019, Commission staff granted WBI's request to utilize 
the Pre-Filing Process and assigned Docket No. PF19-7-000 to staff 
activities involved in the project. Now, as of the filing of this 
application on February 14, 2020, the Pre-Filing Process for this 
project has ended. From this time forward, this proceeding will be 
conducted in CP20-52-000, as noted in the caption of this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 3 copies of filings made in the proceeding with the Commission 
and must provide a copy to the applicant and to every other party. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commenters will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commenters will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    As of the February 27, 2018 date of the Commission's order in 
Docket No. CP16-4-001, the Commission will apply its revised practice 
concerning out-of-time motions to intervene in any new Natural Gas Act 
section 3 or section 7 proceeding.\1\ Persons desiring to become a 
party to a certificate proceeding are to intervene in a timely manner. 
If seeking to intervene out-of-time, the movant is required to show 
good cause why the time limitation should be waived, and should provide 
justification by reference to factors set forth in Rule 214(d)(1) of 
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------

    \1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at 
50 (2018).
    \2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 3 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on March 18, 2020.

    Dated: February 26, 2020.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2020-04321 Filed 3-2-20; 8:45 am]
 BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.