Notice of Filing, 8856-8857 [2020-03062]
Download as PDF
lotter on DSKBCFDHB2PROD with NOTICES
8856
Federal Register / Vol. 85, No. 32 / Tuesday, February 18, 2020 / Notices
d. Applicant: Boyne USA, Inc.
e. Name of Project: Boyne River
Hydroelectric Project.
f. Location: On the Boyne River in
Boyne Valley Township, Charlevoix
County, Michigan.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Randall Sutton,
Boyne Mountain Resort Area Manager
Boyne USA, Inc., P.O. Box 19, Boyne
Falls, MI 49713; (231) 549–6076;
rsutton@boynemountain.com.
i. FERC Contact: Patrick Ely at
patrick.ely@ferc.gov or (202) 502–8570.
j. Cooperating Agencies: Federal,
state, local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: March 31, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–3409–032.
m. The application is not ready for
environmental analysis at this time.
n. The Boyne River Hydroelectric
Project (project) consists of a reservoir
with a gross storage capacity of 356
acre-feet and a surface area of 68 acres
at a pool elevation of 636.8 feet National
VerDate Sep<11>2014
17:48 Feb 14, 2020
Jkt 250001
Geodetic Vertical Datum 1988. The
project includes: (a) An existing 610foot-long by 30-foot-high (left) earth-fill
dam embankment, a 180-foot-long by
18-foot-high (right) earth-fill dam
embankment, a 75-foot-long concrete
spillway; (b) a 132-foot-long by 50 to 72foot-wide by 12-foot-deep concrete lined
headrace channel; (c) a 74-foot-long
steel penstock consisting of two 5-footdiameter and one 7-foot-diameter
sections; (d) a 20-foot-long by 8.3-footwide to 16-foot-wide by 4-foot-deep
stilling basin; and (e) a 24-foot-long by
24-foot-wide concrete powerhouse with
a single 250-kilowatt propeller turbine.
The project also consists of a 2.5-milelong, 12.5-kilovolt transmission line and
appurtenant facilities. The project
generates about 661 megawatt-hours
annually. The applicant proposes to
continue to operate the project in a runof-river mode.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)—
March 2020
Request Additional Information (if
necessary)—March 2020
Issue Scoping Document 1 for
comments—July 2020
Request Additional Information (if
necessary)—September 2020
Issue Scoping Document 2 (if
necessary)—October 2020
Issue Notice of Ready for Environmental
Analysis—October 2020
Commission issues EA—April 2021
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
Dated: February 11, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–03125 Filed 2–14–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Filing
Docket Nos.
Balfour, Scott C. .............
Bennett, Robert R. ..........
Blunden, Gregory W. ......
Muldoon, Daniel P. .........
Schwartz, David E. .........
Strickland, Valerie C. ......
Weatherford, William W.
ID–7646–004
ID–7647–002
ID–7981–001
ID–8749–001
ID–3396–002
ID–8254–001
ID–8850–000
Take notice that on February 10, 2020,
Scott C. Balfour, Robert R. Bennett,
Gregory W. Blunden, Daniel P.
Muldoon, David E. Schwartz, Valerie C.
Strickland, and William W.
Weatherford, submitted for filing,
applications for authority to hold
interlocking positions, pursuant to
section 305(b) of the Federal Power Act,
16 U.S.C. 825d(b) (2019) and section
45.8 of the Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR part
45.8 (2019).
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the eLibrary
link and is available for electronic
review in the Commission’s Public
E:\FR\FM\18FEN1.SGM
18FEN1
Federal Register / Vol. 85, No. 32 / Tuesday, February 18, 2020 / Notices
Reference Room in Washington, DC.
There is an eSubscription link on the
website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on March 2, 2020.
Dated: February 10, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–03062 Filed 2–14–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2879–012]
lotter on DSKBCFDHB2PROD with NOTICES
Green Mountain Power Corporation;
Notice of Application Tendered For
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2879–012.
c. Date Filed: January 30, 2020.
d. Applicant: Green Mountain Power
Corporation (Green Mountain Power).
e. Name of Project: Bolton Falls
Hydroelectric Project.
f. Location: The existing project is
located on the Winooski River in
Washington County, Vermont. The
project does not affect federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. John
Greenan, P.E., Engineer, Green
Mountain Power Corporation, 1252 Post
Road, Rutland, Vermont 05701; phone:
(802) 770–2195 or email at
John.Greenan@
greenmountainpower.com.
i. FERC Contact: Michael Tust, (202)
502–6522 or michael.tust@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The project
consists of the following constructed
facilities: (1) A 92-foot-high, 275-footwide timber crib dam with a 5-foot-high
rubber dam atop the timber crib
VerDate Sep<11>2014
17:48 Feb 14, 2020
Jkt 250001
construction with a maximum crest
elevation of 397 feet referenced to
National Geodetic Vertical 1929 Datum
and a 196-foot-long reinforced concrete
spillway cap at a crest elevation of 392
feet; (2) a 59-acre impoundment with a
total storage capacity of 300 acre-feet at
a normal operating elevation of 397 feet;
(3) a forebay with two concrete intakes,
each with a 3-inch-spaced trashrack; (4)
two 10-foot diameter, 120-foot-long steel
penstocks encased in concrete,
extending from each intake through the
dam to the generating units; (5) a 73foot-long, 57-foot-wide powerhouse
containing two horizontal, 3,750kilowatt Kaplan turbines with a total
installed capacity of 7,500 kilowatts; (6)
a 36-inch diameter steel bypass pipe
with an invert elevation of 383 feet that
discharges near the left side of the
spillway base; (7) an approximately 130foot long, 5-kilovolt underground
transmission line connecting to an
adjacent switchyard; (8) a 600-foot-long,
34.5-kilovolt overhead transmission line
connecting to a second switchyard; and
(9) appurtenant facilities. Green
Mountain Power also maintains day-use
recreation facilities at the project,
including a picnic area, parking lot,
trails, fishing access, and a canoe launch
and portage trail.
Green Mountain Power proposes to
operate in automated run-of-river mode
as it does under its current practice but
instead of providing a 300-cfs minimum
flow into the bypassed reach via spill
over the dam or through the
powerhouse, Green Mountain Power
proposes to provide a seasonal aesthetic
spill flow of 75 cfs or inflow, whichever
is less, into the bypassed reach during
daylight hours from April 1 through
December 15. Green Mountain Power
would only provide leakage flows from
the dam into the bypassed reach during
nighttime hours from April 1 through
December 15 as well as during day and
nighttime hours from December 16
through March 31. Under normal flow
conditions during periods when
aesthetic spillage is required, Green
Mountain proposes to maintain the
impoundment at an elevation of 397.25
feet. During periods when aesthetic
spillage over the dam is not required,
Green Mountain Power proposes to
maintain the reservoir at an elevation of
397 feet as it does under its existing
operation. In addition to operating and
maintaining its existing recreation
facilities, Green Mountain Power
proposes the following improvements to
its recreation facilities: (1) Relocate the
existing parking area out of the
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
8857
floodplain; (2) place barriers and
signage to redirect foot traffic away from
areas with state-designated rare creeping
lovegrass at the day-use area; (3) add
two picnic tables and an information
kiosk to the day-use area; (4) improve
signage at the portage landing and along
the portage trail for boaters; (5)
construct an improved portage landing;
and (6) clear brush along the portage
trail.
Green Mountain Power is proposing
to remove approximately 9.2 acres of
lands and water from the current project
boundary because these areas do not
contain any project recreation facilities
and are not necessary for project
operation and maintenance. These areas
include 4.2 acres of land south of the
existing portage trail and northwest of
the VELCO transmission line, 2.9 acres
of land south of Power Plant Road, and
2.1 acres of the Winooski River and
shoreline downstream of the dam
located outside of the project bypassed
reach and tailrace. In addition, Green
Mountain Power is proposing to add
approximately 7.6 acres of land to the
project boundary. These areas include:
(1) Approximately 1.4 acres of land
along a secondary access road located to
the south of the portage trail take-out;
(2) approximately 4.1 acres of land
along the middle section of the portage
trail to fully enclose the portage trail;
and (3) approximately 2.1 acres of lands
along the primary project access road to
provide vehicular and pedestrian access
to the project for operation and
maintenance purposes as well as access
to the project’s day-use recreation area.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website at https://
www.ferc.gov using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
E:\FR\FM\18FEN1.SGM
18FEN1
Agencies
[Federal Register Volume 85, Number 32 (Tuesday, February 18, 2020)]
[Notices]
[Pages 8856-8857]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-03062]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Filing
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
Balfour, Scott C..................................... ID-7646-004
Bennett, Robert R.................................... ID-7647-002
Blunden, Gregory W................................... ID-7981-001
Muldoon, Daniel P.................................... ID-8749-001
Schwartz, David E.................................... ID-3396-002
Strickland, Valerie C................................ ID-8254-001
Weatherford, William W............................... ID-8850-000
------------------------------------------------------------------------
Take notice that on February 10, 2020, Scott C. Balfour, Robert R.
Bennett, Gregory W. Blunden, Daniel P. Muldoon, David E. Schwartz,
Valerie C. Strickland, and William W. Weatherford, submitted for
filing, applications for authority to hold interlocking positions,
pursuant to section 305(b) of the Federal Power Act, 16 U.S.C. 825d(b)
(2019) and section 45.8 of the Federal Energy Regulatory Commission's
(Commission) Rules of Practice and Procedure, 18 CFR part 45.8 (2019).
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date. On or
before the comment date, it is not necessary to serve motions to
intervene or protests on persons other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
eLibrary link and is available for electronic review in the
Commission's Public
[[Page 8857]]
Reference Room in Washington, DC. There is an eSubscription link on the
website that enables subscribers to receive email notification when a
document is added to a subscribed docket(s). For assistance with any
FERC Online service, please email [email protected], or call
(866) 208-3676 (toll free). For TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on March 2, 2020.
Dated: February 10, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-03062 Filed 2-14-20; 8:45 am]
BILLING CODE 6717-01-P